de srec procurement program overview n.
Download
Skip this Video
Download Presentation
DE SREC Procurement Program Overview

Loading in 2 Seconds...

play fullscreen
1 / 11

DE SREC Procurement Program Overview - PowerPoint PPT Presentation


  • 82 Views
  • Uploaded on

DE SREC Procurement Program Overview. Call-in for this webinar is (917) 338-1451 PIN: 361734# Audio also available on your computer. www.SRECDelaware.com srecdelaware@srectrade.com (877) 466-4606 x100. Webinar Program. Basic Program Overview Sample Facility Application

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'DE SREC Procurement Program Overview' - nalanie


Download Now An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
de srec procurement program overview

DE SREC Procurement Program Overview

Call-in for this webinar is (917) 338-1451 PIN: 361734#

Audio also available on your computer

www.SRECDelaware.com

srecdelaware@srectrade.com

  • (877) 466-4606 x100
webinar program
Webinar Program
  • Basic Program Overview
  • Sample Facility Application
  • Questions and Answers
    • All questions will be asked through the chat feature
    • Questions may be asked at any time, answers will be provided at the end of the presentation
basic requirements
Basic Requirements
  • Existing projects – Must have an “Accepted Completed Solar System Interconnection Application” dated Dec 1, 2010 or later.
  • Proposed projects – Must commence operation within 12 months of the award date.
  • All projects – Must not have received supplemental funding from a public source, other than grants associated with the Delaware Green Energy Program (“GEP”) or grants in lieu of the investment tax credit.
tiers
Tiers

*The procurement of SRECs for Tier 4. for the 2011 compliance year was satisfied in full with the purchase of SRECs from the Dover Sun Park Project. Accordingly, the process for procuring SRECs from Tier 4 projects is not included in the initial pilot SREC Procurement Pilot Program.

tiers1
Tiers

*The procurement of SRECs for Tier 4. for the 2011 compliance year was satisfied in full with the purchase of SRECs from the Dover Sun Park Project. Accordingly, the process for procuring SRECs from Tier 4 projects is not included in the initial pilot SREC Procurement Pilot Program.

pricing
Pricing

*projects that received a GEP grant before December 10, 2010

award process tier 1 and 2a1
Award Process - Tier 1 and 2A

There is no competitive advantage to submitting Tier 1 and 2A applications at 8:01 on April 2nd!

Submitting applications earlier in the week does give bidder more time to resolve any issues with bid or receipt of bid deposit.

application requirements
Application Requirements
  • Owner representative for all projects less than 100kw
  • Bid deposit of $100/kw for projects not yet built - wire deposit, letter of credit, or bid bond.
  • Performance credit support for all Tier 3 projects
    • Years 1-10, 5% of value of 1st year SREC quantity
    • Years 11-20, 10% of value of year 10 SREC quantity