The AGATA Project. International experimental facility for the investigation of nuclear structure, nuclear astrophysics and fundamental interactions. First 4pi  -ray spectrometer built completely from Germanium detectors. Based on the novel technique of gamma-ray tracking.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about '' - naava


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
The agata project l.jpg

The AGATA Project

International experimental facility for the investigation of

nuclear structure, nuclear astrophysics and fundamental interactions

  • First 4pi -ray spectrometer built completely from Germanium detectors.

  • Based on the novel technique of gamma-ray tracking.

  • Measures  radiation in a very large energy range, with the largest possible

    efficiency and with a very good spectral response.

  • Several orders of magnitude more powerful than any current and near-future

    –ray spectrometer in the world.

  • Key parameters are (i) an energy range < 50 keV to > 10 MeV, (ii) a photo-peak

    efficiency of about 50% at 1 MeV, (iii) a position resolution of < 5 mm and

    (vi) a trigger rate of up to 1 MHz.

NUPECC Meeting 16.3.07 J. Gerl GSI


Slide2 l.jpg

AGATA Collaboration

Clustering of the nuclear structure community around a

well organized and focused European research collaboration

Bulgaria: Sofia

Denmark: Copenhagen

Finland: Jyväskylä

France: GANIL, Lyon, Orsay, Saclay, Strasbourg

Germany: Berlin, Bonn, GSI, Darmstadt, Köln, München

Hungary: Debrecen

Italy: Padova, Milano, LNL, Firenze, Camerino, Napoli, Genova

Poland: Krakow, Swierk, Warsaw

Romania: Bucharest

Sweden: Lund, Stockholm, Uppsala

Turkey: Ankara, Istanbul

UK: Daresbury, Brighton, Keele, Liverpool, Manchester, Paisley, Surrey, York

NUPECC Meeting 16.3.07 J. Gerl GSI


Slide3 l.jpg

AGATA Facility

AGATA is intended to be an independent, movable Research Infrastructure to be coupled to stable and exotic ion beam accelerators in European host laboratories

Accepted Host Laboratories for the Demonstrator Phase 2008-2011:

LNL Legnaro GANIL Caen GSI Darmstadt ILL Grenoble

Interested Host Laboratories for the AGATA array:

FAIR / GSI Darmstadt SPIRAL 2 / GANIL Caen SPES / LNL Legnaro

REX-ISOLDE / CERN Geneve JYFL Jyväskylä ILL Grenoble ....

NUPECC Meeting 16.3.07 J. Gerl GSI


Slide4 l.jpg

AGATA R&D Phase

Prototyping, testing, commissioning...

  • Develop 36 fold segmented encapsulated detector of right shape

  • Develop cryostat for groups (“clusters”) of these detectors

  • Develop digital electronics (700 channels)

  • Finalise signal algorithms for energy, position and time

  • Develop tracking algorithms

  • Build demonstration unit to prove tracking in real situations

  • Write technical proposal for full array


Slide5 l.jpg

AGATA Demonstrator

Main objective of the R&D phase

1 symmetric triple-cluster

5 asymmetric triple-clusters

36-fold segmented crystals

540 segments

555 digital-channels

Eff. 3 – 8 % @ Mg = 1

Eff. 2 – 4 % @ Mg = 30

Full DACQwith on line PSA and -ray tracking

Test Sites:

GANIL, GSI, Köln, LNL


Slide6 l.jpg

AGATA Demonstrator Funding

Latest estimated cost:

(3 sym + 15 asym.)

k€ ex tax

Detectors 4033

Electronics 1378

DAQ 287

D&I 103

Ancillaries 24

Data analysis 20

Total 5844

Capital for the demonstrator:

France, Germany, Italy, Sweden, Turkey and UK

Total 6006 k€ ex tax

15 + 3 detector system possible (just)


Slide7 l.jpg

AGATA Detectors

Detectors in time...

  • Symmetric detectors

    • 3 delivered

  • Asymmetric detectors

    • 15 ordered, 4 delivered

  • Triple cryostats

    • 3 (soon 4) ordered

    • 1st expected May

  • Test cryostats

    • 3 delivered

    • 1 ordered (expected soon)

  • Preamplifiers

    • Core (cologne) Segment (Ganil. Milano) working


Slide8 l.jpg

AGATA Electronics

Digitizer

Preamplifier

Pre-processing, further development needed


Slide9 l.jpg

Köln in-beam test 2005

REACTION CHANNEL: (d,p)

PSASegDet

1382 keV


Slide10 l.jpg

AGATA Design and Construction

Infrastructure in time...

  • 180 geometry defined

  • Conceptual design of 180 array done

  • Details of HV, LN2 control etc. agreed, GSI test done

  • Design of AGATA demonstrator for LNL in final stage

  • Flanges manufacturing started

  • Assembly in LNL in autumn 2007


Slide11 l.jpg

Status of the AGATA Project

What remains to be done

  • Next steps

    • Build up triple detector (s)

    • Ge detector characterisation

    • Pulse-shape analysis algorithms optimised

    • Gamma-ray tracking algorithms optimised

    • Electronics and DAQ prototypes and production

  • Demonstrator ready by 2008

  • First physics campaign at Legnaro in late 2008

  • Further campaigns at GANIL, GSI, (ILL)


Slide12 l.jpg

AGATA Project Evolution

How to proceed

  • Demonstrator ready in 2008

  • Next phases discussed in 2005-2007

  • New LoI for construction phase 2005

  • First funding bids for production in D and I successful

  • New MoU in preparation (required by D in 2007 to release funds)

  • New organisational structure

  • Start construction in 2008, 1 in possible in 2011

  • Rate of construction depends on production capability

  • Physics exploitation in stages, AGATA facility development


Slide13 l.jpg

AGATA Timetable

Well structured organization based on LoIs and MoUs

2001 2003 2005 2007 2009 2011 2013 2015 2017

Proof of Principle

R&D Demonstrator

Construction Phases

Comm

.

Demonst.

Physics

Phase 1

Physics

Phase 2

Physics

Full operation

Physics

NUPECC Meeting 16.3.07 J. Gerl GSI


Slide14 l.jpg

AGATA Cost and Effort

Well structured organization based on LoIs and MoUs

2001 2003 2005 2007 2009 2011 2013 2015 2017

Preparatory phase

Invest: 6.5 M€

Effort: 120 FTE

Construction phase

Invest: 50 M€

Effort: 100 FTE

Operation

Cost: < 1 M€

TMR

I3 EURONS

EC FP7

NUPECC Meeting 16.3.07 J. Gerl GSI


Slide15 l.jpg

AGATA Funding

AGATA is a moving Research Infrastructure developed, built and operated by a truly European research collaboration

  • Too large for funding within national nuclear structure schemes

  • Too small for CNI funding in FP7 based on ESFRI criteria

  • Moving instrument, therefore no governance by any accelerator facility

A dedicated funding scheme supporting medium scale European projects is needed

  • NUPNET as "natural" funding agency contact

  • ERANET+ as appropriate funding instrument in FP7

  • Possibly governance by NuPECC

  • Operation as independent Research Infrastructure eligible for TNA support in FP7