習題 16.6

習題 16.6. A 產品的 BOM 表如下圖,存貨紀錄資料如下表。在產品 A 的主生產排程中,第 8 個星期 MPS 的原始數量為 500 單位,前置時間為 2 個星期。請發展未來 6 個星期,項目 B 、 C 、 D 的物料需求計畫。. A. C(1). D(1). B(2). C(1). D(2). D(2). BOM. 存貨紀錄.

morela
Download Presentation

習題 16.6

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.