1 / 59

Air Permitting and Compliance

Air Permitting and Compliance. Clean Air Act Basics & Primer Construction Permitting Title V/Operations Permitting Typical Activities Requiring Permits/Permit Modifications Information Needs /Review Process. Air Permitting and Compliance Con't.

Download Presentation

Air Permitting and Compliance

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Air Permitting and Compliance • Clean Air Act Basics & Primer • Construction Permitting • Title V/Operations Permitting • Typical Activities Requiring Permits/Permit Modifications • Information Needs/Review Process

  2. Air Permitting and Compliance Con't. • Emission Quantification, Tracking & Reporting (AETS, 12-Month Rolling Average, Annual Inventories, etc.) • CFC/HCFC (“Refrigeration”) • RMP (PSM Relationship) • General “Air” Summary • Code Of Fed. Reg./General Air Links

  3. Air Permitting and Compliance Clean Air Act Basics • CAA History • NAAQS • NSPS/NESHAP • 1970 Orig. CAA, 1977 CAAA (PSD), 1990 CAA Amendments

  4. Clean Air Act Basics • CAA Dates Back To 1970’s • 1970 CAA Contained NSPS @ Part 60 & NESHAPS @ Part 61 = Risk-Based/Few Perfect Stds. Covering Only 8 HAPS • Great Deal Of Non-Compliance W/ Orig. Intent Of 1970 CAA • Only Handful Of NSPS/NESHAPS Promulgated From 1970 To Mid 1980’s • CAA Amended 1990(Former Pres. Bush)

  5. Clean Air Act Basics Con't. • 1990 CAAA Designed To Curb 3 Major Threats To Human Health & Environ. = Acid Rain, Urban Air Pollution, & Toxic Air Emissions • National Permits Program Established To Make Law Workable & Enforceable • Phase Out Ozone-Depleting Chemicals, Add Research & Development, Add RMP

  6. Clean Air Act Basics Con't. • Encourage Market-Based Principles = Performance Based Stds. (Vs. Risk-Based Stds.) AND Emission Banking & Trading • Set Stds. For Alternative Clean Fuels = I.D. Best Combo Of Fuels & Technology • Limit Fossil Fuel Sulfur Content AND Promote Innovative Control Technology Via Acid Rain Program

  7. Clean Air Act Basics Con't. • Cut U.S. Import Oil Dependency By 1MM Barrels/Day • Promote Energy Conservation Via Acid Rain Program = Utilities Receive Credit For Emission Reductions Via Customer Programs Encouraging Energy Conservation

  8. Air Permitting & Compliance Clean Air Act Primer • Basis For Limits • Ambient Air/NAAQS • Regulated Pollutants, SIP & PSD • 1990 CAAA Overview (Titles I, III & V) = Attain/Maintain NAAQS, HAPs, Ops. Permit • BACT/MACT/LAER • Risk Mgt. Planning (RMP) • Potential To Emit (PTE)

  9. Clean Air Act Primer • Regulation Of Air Emission Sources: Emission Stds., NAAQS • Emission Limits: Lbs/Hour, Tons/Year, Lbs/Ton, Lbs/MMBTU, % Opacity, % Efficiency, etc. • Basis For Limits: 1970 NSPS @ Part 60, 1970 NESHAP @ Part 61, SIP’s, 1990 NESHAP (Stationary Source Categories), Acid Rain @ Parts 73 & 76, Stratospheric Ozone @ Part 82

  10. Clean Air Act Primer Con't. • What Is Ambient Air? That Portion Of The Atm., External To Bldgs., To Which The General Public Has Access --- Typically Site Boundary Outward If Have Perimeter Fencing --- Attainment Demonstrated Via Air Disp. Modeling & Ambient Monitoring • NAAQS: Micrograms/Cubic Meter & Based On “Acceptable Risk” – (1 : 1,000,000 CR) • NAAQS Basis: NAAQS @ Part 50, PSD 1977 CAAA @ Part 52, & State Stds.

  11. Clean Air Act Primer Con't. • Primary NAAQS: Set @ Levels “Allowing An Adequate Margin Of Safety…Requisite To Protect The Public Health” • Secondary NAAQS: Set @ Levels To Protect “The Public Welfare” • Regulated Pollutants: PM-10 (PM-2.5 Soon?), SO2 (Sulfur Dioxide), NO2 (Nitrogen Dioxide), O3 (Ozone/VOC), CO (Carbon Monoxide) & Pb (Lead) --- “Criteria Pollutants” = TSP/PM, SOx, NOx, VOC, CO & Pb (Const. Permits)

  12. Clean Air Act Primer Con't. • SIPs: Attain/Maintain NAAQS, Establish Emission Limits, Review Impacts Of New Growth, Revised As New Regs. Are Passed • PSD: Prevent Sig. Deterioration = Const. Permitting Via 1977 CAAA --- Based On “Potential Emissions”, Regulates Emissions & Ambient Air Quality, Affects Lg. Sources • PSD Goals: Allow Economic Growth While Protecting Air Resources, Protect Public Health & Welfare, & Enhance Air Quality

  13. Clean Air Act Primer Con't. • PSD Review Req.: Ambient Monitoring, Dispersion Modeling, Control Device Review, Additional Impacts, Class I Assessment (Not Title V Class I) = Impacts To Soils, Plant Life, Visibility, --- National Parks, etc. • 1990 CAAA Overview (11 Titles - 3 Main): • *Title I = Attain/Maintain NAAQS • *Title III = HAPs/Air Toxics • *Title V = Permits/Operating Permits

  14. Clean Air Act Primer Con't. • Title I (Attain/Maintain NAAQS): *“Attainment” Of NAAQS Req. For Const. Permitting (i.e., PSD)To Apply *”Non-Attainment” Of NAAQS PSD Not Applicable & Any Proposed Project/Mods. Must Actually Reduce Overall Emissions

  15. Clean Air Act Primer Con't. • Title III (HAPs): *Previous Approach = Risk-Based, W/ Few Perfect Stds., Which Covered Only 8 HAPs *New Approach = Technology-Based Stds., Emission Reductions For 188 HAPs That Apply To “Major” & “Area OR Minor” Sources Of HAPs --- See Link To List Of 1990 CAAA HAPS* & Defn. Of VOC* = I.D.’ed @ End Of Presentation

  16. Clean Air Act Primer Con't. • Title III (HAPs) Cont.: *HAP Emission Source: “Major” Stationary Source = Contiguous Area, Common Control, W/ > 10 TPY Single HAP OR 25 TPY Aggregate HAP --- “Area” Source Is One That Is Not Major (Must Include Fugitive) *MACT: Max. Achievable Control Tech. --- New Sources = Meet Best Controlled Similar Source --- Existing Sources = Ave. 5 Best (>30 Sites) OR Ave. Best 12% (<30)

  17. Clean Air Act Primer Con't. • Title III (HAPs) Cont.: • *Interim MACT (BACT = Best Avail. Control Technology): Transitional Program Until All MACT Stds. Are Issued, Applies To Constructed & Re-Constructed Sources • Title III (Accidental Releases = RMP): • *Risk Mgt. Plans For Listed Chemicals (Flammable & Toxic Lists) That Exceed Threshold Amounts --- “General Duty” Clause --- Extension Of OSHA PSM

  18. Clean Air Act Primer Con't. • Title V (Operating Permits): *Single Enforcement Document To Assist Both Industry & Regulators *Applicability: HAPs @ 10 TPY Single OR 25 TPY Aggregate; Criteria Pollutants 100 TPY --- All Based On Potential To Emit (PTE) = Annual Emission/Actual Hrs. Ops. * 8,760 *PTE: Max. Emissions Continuous Ops. (8,760 Hrs/Yr) W/ No Controls Except Fed. Enforceable Permit Restrictions = NSPS, NESHAP, BACT/MACT/LAER, Permit Cond.

  19. Air Permitting & Compliance Construction Permitting • When Required? “Allowable Emissions” Increase/Decrease OR When Modify Process &/Or Control Equipment (Even “Like Kind” Replacement) = Not One Size Fits All! • Proposed Changes That Increase “Potential Emissions” By The Following (PSD Sig.): *PM @ 25 TPY Or >, PM-10 @ 15 TPY Or >, SOx, NOx, OR VOC @ 40 TPY Or >, CO @ 50 TPY Or >, Pb @ 0.6TPY Or >, Single HAP @ 2.5 TPY/Combined HAPs @ 10 TPY Or >

  20. Construction Permitting Con't. • ”Allowable Emissions” = Emissions Rate Of Stationary Source Calc. Using Max. Rated Capacity Of Source (Unless Fed. Enforceable Limit Applies) AND Most Stringent Of NSPS, NESHAP, SIP, OR Existing Permit Condition(s) • Must Quantify Past Actual To Future Potential = NOT Potential To Potential, etc. • Must I.D. Whether NESHAP Applicable (“Major” Source 10/25 TPY PTE) W/ HAP Increase Of 2.5/10 TPY PTE Proposed

  21. Construction Permitting Con't. • Many Proposed Mods. Involving HAPs Require Some Form Of BACT Analysis = BACT Is Analysis To I.D. Max. Degree Of Emission Reduction Achievable Considering Energy, Env., & Economic Impacts (Other Than Costs) --- Typically $3K To $4K/Ton Pollutant Removed Is Cut Off --- Must @ Least Be As Stringent As NSPS Or NESHAP --- BACT Is An Interim Step Towards MACT/NESHAPS Scheduled For Future But Have Yet To Be Promulgated ---See Proposed Rule ISSN 1521-9402 Link *

  22. Construction Permitting Con't. • Proposed Rule ISSN 1521-9402 * Would Regulate HAP Emissions From Coatings/ Paints Applied To Misc. Metal Parts & Products --- It Would Only Apply To “Major” Sources Of HAPs (i.e., PTE >10 TPY Single HAP OR >25 TPY Of Combined HAPs) • Est. Reg. To Cost Metal Coating Industry $57MM/Year = Added Costs Incurred For “Control” Of Emissions (Capture-&-Reclaim Systems, More Costly Reformulated Subs., etc.) --- Powder Vs. Wet Painting Benefit!

  23. Construction Permitting Con't. • Dispersion Modeling: Is Used To Demonstrate Compliance W/ NAAQS, Is Required For PSD, Is not Typically Performed For Minor Source Permits = Most Likely Not Required For Valmont Locations --- Background AAQ Monitoring • Non-Attainment Permitting: Offsets, LAER, All Other Sources In State Must Be In Compliance, Alternative Sites May Be Assessed To I.D. If Source Could Go To Another Area Reasonably

  24. Construction Permitting Con't. • Application Contents: General Info. About The Source, Process Info., Fuel Combustion Data, & Certification --- Supplemental Info. May Include Air Dispersion Modeling, Control Technology Review (BACT For PSD AND/OR HAPs, & LAER For Non-Attainment Areas), & Class I Impacts Analysis (NOT Title V Class I Terminology)

  25. Construction Permitting Con't. • PSD Permitting Almost Certainly Will Not Be Applicable For Valmont Locations = Requires “Major” Source I.D. Via Const. Permit Regs. = 250 TPY/Criteria Pollutant (Except For The 28 Listed Sources = 100 TPY/Criteria Pollutant) Prior To Const. Event AND Const. Event In & Of Itself Must Be “Significant” Per PSD Thresholds • 8 HAPS Regulated By PSD = Asbestos, Beryllium, Mercury, Vinyl Chloride, Fluorides, Sulfuric Acid Mist, Hydrogen Sulfide & Total Reduced Sulfur

  26. Construction Permitting Con't. • “Non-Attain. Area” - Area That Is Not Meeting NAAQS (i.e., CA Trip Reduction Reqs. If >30-40 People – Ozone/Smog, etc.) • “Attainment/Non-Attainment” Status Are On A Pollutant By Pollutant Basis • Overall Reduction Of 10% To 50% Req. = Can Be Costly & Prevent New Industry From Entering Or Existing Industry From Expanding Operations In A Particular Area • Ultimately, The NAAQS Would Be Achieved Over Time

  27. Air Permitting & Compliance Operations Permitting • When Is An Operating Permit Required? *These Are Generally State Specific Req. Based From 40 CFR Part 70 • Various Permit Types W/ Assoc. Req. Exist *Class I Or Title V Major = >100 TPY (PTE & Actual) PM/TSP, PM-10, SOx, NOx, & CO; Pb >5 TPY; HAP (Single) >10 TPY; & HAP (Combo) >25 TPY *Class II Syn. Minor, Voluntary, OR FESOP = PTE > “Major Source” & Actuals < “Major”

  28. Operations Permitting Con't. *Class II Minor Or Small Source Permit = PTE < “Major Source” W/ Actuals <50% “Major Source” Thresholds OR < “Significant Increase Thresholds” By PSD/Pre-Const. Permit Thresholds *VOC General Permit Alternative In Some States = Actuals Remain < Class I VOC/HAP *No Permit Req. = When PTE & Actuals Either Under “Major Source” Thresholds OR Both Are < “Sig. Increase Thresholds” By PSD/Pre-Const. Permit Thresholds

  29. Operations Permitting Con't. • Permit Limits & Content: Citation Authority For Each Applicable Req., Future Req., Alternative Operating Scenarios, Permit Shield, Monitoring & Record Keeping Req., Voluntary Limits & Expiration Date = Typically Effective For 5 Year Period • ”App. Shield” = Allows Facility To Operate W/O Permit While App. Being Reviewed • “Permit Shield” = Protect Facility From Enforcement So Long As Comply W/ Existing Permits

  30. Operations Permitting Con't. • Federal Enforceability: Ensures Conditions Placed On Emissions Are Enforceable By EPA & Citizens (Ops. Permit, Limits By Rule, General Permits, & Const. Permits) • Applicable Req.: A Provision, Std., Or Req. In Any Reg. Or Statute As Applied To An Emission Unit = Emission Limits, NESHAPs, Air Quality Permits/Regs., etc. • Compliance Determination/Demo Plan

  31. Operations Permitting Con't. • Operational Flexibility, Agency Review, Completeness Determination, Draft Permit, Public Involvement, Public Participation & Confidentiality, Title V Fees

  32. Air Permitting and Compliance Typical Permitted Process & Control Equip. • Process Equipment *Equipment For Cutting Of Metal, Welding, Grinding, Sawing, Metal Surface Prep (i.e., blasting, Caustic Degreasing, etc.), Surface Coating Ops. (I.e., Anodizing, Galvanizing, Painting (Dry & Wet), Fossil Fuel Combustion Equip. (i.e., Nat. Gas, Propane, etc.), Storage Tanks, Some Maintenance Activities, Adhesives, Cleaning, Marking, Aerosols, etc.

  33. Air Permitting and Compliance Typical Permitted Process & Control Equip. Con't. • Control Equipment *Bag house Filter Systems, Cartridge Filters, Cyclones, Bag Filters, Submerged Welding, Water Table Cutting, etc.

  34. Air Permitting and Compliance Primary Pollutant(s) For This Industry/Process(es) • Volatile Organic Compounds (VOCs) • Hazardous Air Pollutants (HAPs) • Particulate Matter (TSP, PM, PM-10, etc.)

  35. Air Permitting and Compliance Typical Activities Req. Permits/Mods. • Include But Not Limited To Following: *Installation Of Additional (New Or Used) Process OR Air Emissions Control Equip. *Mod. Existing Process OR Control Equip. *Projects To Increase Production Capacity = “Debottleneck” *Product Substitutions

  36. Air Permitting and Compliance Typical Activities Req. Permits/Mods. Con't. *Acquire Additional Production Locations *Promulgation Of New Reg. Requirements = New NSPS, NESHAP, etc. *Unable To Maintain Compliance W/ Existing OR New Permit Limits

  37. Air Permitting and Compliance Info. Needs/Review Process • Includes But Not Limited To Following: *General Project Description, Anticipated Timeline, Facility Location, Facility Contact W/ Telephone #, etc. *Existing Process Flow Diagram Including Processing Equip., Control Equip./% Eff., Equip. Aspirated, Aspiration Flow Rates, Processing Rates, Emission Points, Raw Material Inputs, Waste(s) Generated, etc.

  38. Air Permitting and Compliance Info. Needs/Review Process Con't. *Proposed PFD W/ Process Equip., Control Equip./% Eff., Process Rates, Raw Material Inputs, Waste(s) Generated, etc. *I.D. Of Substances (Name & Part #) Utilized In Process, Copies Of MSDS For Each Substance, I.D. Quantity Of Each Substance Used For Previous 12-Month Rolling Time Frame, Hours Of Operation For Subject Process(es), Projected Operating Schedule (Hrs/Day, Days/Week, & Weeks/Year), etc.

  39. Air Permitting and Compliance Info. Needs/Review Process Con't. *More Detailed Info. May Be Req. After Initial Evaluation Procedures = Plot Plan Showing Proposed Equip. Location, Engineering Design/Selection Calcs. (Plans & Specs.), Mfg. Info., Stack Location, Stack Diameter/Height/Gas Exit Velocities, Scale, Property Lines (Or Provide Distance To Nearest), Fuel Type(s) W/ Related Equip. Capacity, Equip. Aspirated, Aspiration Flow Rates, etc.

  40. Air Permitting and Compliance Emission Quantification/Tracking/Inventory • When Is An Emissions Inventory Typically Required? = Most States Req. Quantification Of Emissions On An Annual Basis W/ Report Development & Submittal • For Most Part, Title V Major Sources Not Only Quantify Emissions & Report, They Also Pay Annual Emissions Fees (Specified $/Ton Of Pollutant) = $/Ton Calculated Following Submittal Of All Emissions W/ Dept. Budget Divided By # Of Tons To Back Into The $/Ton Figure

  41. Air Permitting and Compliance Emission Quantification/Tracking/Inventory Con't. • Reports Cover The Previous Years Emissions, May Have $/Ton Or Some Fixed Pricing Based On Permit Level/Type, & Utilities Were Successful In Lobbying For Caps/Pollutant (i.e., 4,000 Tons Max.) • Emissions Oftentimes Req.’ed To Be Determined On Daily, Weekly, Or Monthly Basis & Tracked As 12-Month Rolling Ave. = Doc. To Verify In Compliance W/ Permit Limits @ Time Of Inspections W/ Permit Established To Meet NAAQS, etc.

  42. Air Permitting and Compliance Emission Quantification/Tracking/Inventory Con't. • AETS Developed To Help Address Tracking @ Larger Sites = Data Mgt. System Based On Stores Inventory --- As Items Are Checked Out, They Are Considered Emitted (VOC & HAPs) = Able To Tie To Particular Permit Limit, Emissions Unit, etc. --- See Link To AETS @ End Of This Presentation * • Wally Bell Presentation On The AETS W/ Req.’s For Implementing @ Off-Site Locals = Call Him, AETS Use Instruc., etc.

  43. Air Permitting and Compliance Emission Quantification/Tracking/Inventory Con't. • Emission Factors Published By EPA, etc. From Data That Has Been Obtained Over Time May Assist W/ Emission Quantification = May Be Used As Basis For Permit App., May Alleviate Stack Testing Req.’s, etc. • Links For These Emission Factor Databases Are Provided @ End Of The Presentation --- Provided For: AP-42 *, AIRS/FIRE *, etc.

  44. Air Permitting and Compliance CFC/HCFC ("Refrigeration") • Industrial Process Refrig. Leak Repair Regs.= “Process”, “Commercial” & “Comfort Cooling” Are Regulated (Section 608 CAA) • Need I.D. All Units W/ > 50 Lbs Max. Charge Capacity, I.D. Specific CFC/HCFC Put Into System, & I.D. How Determined Max. Charge (i.e., Calc., Mfg. Specs., etc.) • All Service On Coolant Loop(s) Require Cert. & Documentation = Obtain Records For Last 2 Events CFC/HCFC Were Added

  45. Air Permitting and Compliance CFC/HCFC ("Refrigeration") Con't. • Determine Which Classification Applies/ System = “Industrial” & “Commercial” @ 35% OR “Comfort Cooling” @ 15% Leak Rate Triggers Respectively • Calc. Annual Leak Rate Per Formula On Pg. D-1 Of Compliance Guidance Doc. (See Link @ End Of Presentation) = Need I.D. Time Between Last 2 Cooling Loop Service Events Where CFC/HCFC’s Were Added

  46. Air Permitting and Compliance CFC/HCFC ("Refrigeration") Con't. • Follow 6-Pg. Refrig. Leak Repair Flow Chart @ Very End Of Guidance Doc. = If Annual Leak Rate W/in Req. Specs., Document To File (May Need Do Again W/in Next 30 Days) --- If Not, Need Address Leak Repair, Retrofit/Retire Option That Applies & Is Desired • Determine Course Of Action To Complete Required Mods. W/in Specified Time Frame(s) (i.e., 30 Days To Fix, Dev. Plan, ~1 Year For Retrofit/Retire Option, etc.)

  47. Air Permitting and Compliance CFC/HCFC ("Refrigeration") Con't. • Air (Vs. Water) Cooled Compressors Have Eliminated Water Discharges But May Now Be Subject To This Req. --- Look @ ARS Chillers, Office Bldg. Cooling, etc. • See Link For Identification Of Class I & II Ozone Depleting Chemicals W/ Assoc. Labeling * AND Refrigerant Usage Requirements * --- Appliances (i.e., @ Stationary And Motor Vehicle Systems) Are Regulated During Use, Servicing & Disposal = Goal To Prevent Loss To Atmos.

  48. Air Permitting & Compliance Chemical Accident Prevention (RMP) • Risk Mgt. Planning (RMP) = Do Not Believe Too Great Impact To Valmont But Need To Be Aware Of Reqs. --- For Example, Propane “Stayed” @ Present, HCl 37% Conc. & > @ 15,000 lbs, & Fuming H2SO4 @ 10,000 lbs are reg. • List Each Of 66 Flammable & 77 Toxic Substances That Require Planning If Trip Respective Thresholds (i.e., 10,000 Lbs For Flammables & 500 To 20,000 Lbs For Specific Toxic Compounds)

  49. Air Permitting & Compliance Chemical Accident Prevention (RMP) • “General Duty Clause” Is Another Way That One May Be Drawn Into Being Regulated Even If Do Not Meet The Defn. For Being Covered = Essentially A “CYA” For The Regulators Should A Problem Occur Outside Of The Reqs. For Being Regulated • Bhopal, India, etc. Catastrophes Were Primary Drivers For This Regulation • Problem W/ Info. Reqs. & Terrorism!

  50. Air Permitting & Compliance Chemical Accident Prevention (RMP) Con't. • 3 Parts = Hazard Assessment, Emergency Response Program & A Prevention Program • Perform Hazard Assessment Using Worse Case & Alternative Releases To Determine Endpoints, Release Scenarios, Meteorological Conditions, Screening Approach (“Look-up” Tables), &/OR Refined Modeling