June 27-July2: Remove Shield Wall (3.5 days, Riggers)

June 27-July2: Remove Shield Wall (3.5 days, Riggers) June 27 – July 2 : Remove Vacuum pipe spool pieces. July 3: Pull East Poletip July 5: Pull West Poletip. Install scaffolding E&W. (Charlie & Steve)

Download Presentation

June 27-July2: Remove Shield Wall (3.5 days, Riggers)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. June 27-July2: Remove Shield Wall (3.5 days, Riggers) • June 27 – July 2: Remove Vacuum pipe spool pieces. • July 3: Pull East Poletip • July 5: Pull West Poletip. Install scaffolding E&W. (Charlie & Steve) • June 27 – July 13: Remove SVT RDOs, extender cables, and cabling back to the Racks. Remove EEMC Trigger Cables. • June 27 – July 18: Install Rollers and disconnect utilities, and roll STAR to AB and connect utilities. • July 20 – Aug. 24: EEMC electronics maintenance. • July 19 – 27: Install SVT platform, FTPC West platform, and disconnect end of cone cables, remove FTPCs, and extract cone to platform. • July 30 – Aug. 14: Remove SSD, SVT, all utilities on cone, and reassemble cone. • Aug. 1 – 15: Install new BEMC PMT comm./controls system. • Aug. 16-21: Reinstall cone, reinstall FTPCs, & remove rails. Remove installation platform. • Aug. 22 – 27: Disconnect utilities. • Aug. 28 - 29: Roll STAR back into IR. • Aug. 30 – Sept. 10: Install Utilities. Draft STAR Shutdown Schedule/Plan July 2007 August 2007 Summer Sunday

  2. September 2007 • Sept. 6 – 18: Beam Pipe Bakeout • Sept. 11th: STAR in IR with utilities connected. • Sept. 11 – Oct. 12: TPC Electronics maintenance. • October 1st: TOF Trays arrive at BNL for installation. • Oct. 15 – 18: SGIS Certification. • Oct. 17th: West Poletip installed. • Oct. 24: East Poletip installed. • Oct. 25 – 30: Magnet testing. • Nov. 1st: Collider Cooldown Begins. • Nov. 1 – 2: Install BBCs. • Nov. 7th: Lose access to IR for Collider Commissioning. • Still Open: • * When/where best to install TOF trays? Best locations 2, 4, 7, & 10:00. • * Details/plan for the TOF water system? October 2007 Collider Cooldown Begins