An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bull’s Head RevitalizationWednesday, January 23, 20136:00pmUnity/St. Mary’s Campus

  2. Bull’s Head RevitalizationPublic Planning Process Timeline Overview • 2007 & 2008: Meetings with Neighborhood United • February 2009: City hires consultant for BH Public Planning Process • March 2009: Bull’s Head Project Steering Committee formed • June 2009: Bull’s Head Public Kick-Off Meeting held at St. Mary’s • September 2009: Community Wide Design Workshop held at St. Mary’s • 2009 & 2010: Steering Committee Meetings / Analysis / Progress Updates • 2011: New direction for project - preparing BOA grant application • September 15, 2011: Presentation of BOA application to SWCC • September 19, 2011: NYSDOS extends BOA app. deadline by six months • March 2012: City & Sector 4 CDC submit BOA application

  3. Bull’s Head RevitalizationTarget Area Boundary Map

  4. Bull’s Head Revitalization Land Use Concept Investment (1st Phase): 20k s.f. Police Station $ 7.5 million (Assumes City Lease) 40k s.f. Mixed-Use $15 million (Residential & Commercial) Total Investment: $22.5 million 1st Phase LEGEND Residential Mixed-Use Civic / Police Commercial

  5. Bull’s Head RevitalizationRequired Public Funding for 1st Phase • Land Assembly (Acquis., Demo., Relo.) $ 4,400,000 • Geotech(Placeholder/estimate) $ 1,500,000 • Environmental Testing (Placeholder/estimate) $ 330,000 • Environmental Clean-up (Placeholder/estimate) $ 1,500,000 • Major Utilities (Placeholder/estimate) $ 350,000 • ROW Mods / Improvements (Design) $ 320,000 • ROW Mods / Improvements (Construction) $ 2,000,000 • TOTAL: $10,400,000

  6. Bull’s Head RevitalizationWhat’s Happening Now? • Acquisition through foreclosure • Demolitions • Transition from prior planning process to BOA process

  7. Bull’s Head RevitalizationProposed BOA Area and Target Area Boundary Map

  8. Bull’s Head RevitalizationContact Information: • Rick Rynski Joan Roby-Davison • NBD / City of Rochester Sector 4 CDC • 428-6932 328-5750 • rynskir@cityofrochester.gov joan.sector4cdc@yahoo.com