An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 5 Space Technology “Tomorrow’s Technology Today” GSFC Section 19.0 Combined Ground System Irene Bibyk Ground System Manager ST5 PDR June 19-20, 2001

  2. Agenda • Introduction • Mission Operation Center Integration • Ground Data System - ASIST • Ground Station/Network • Flight Dynamics • ST5 Technology Demonstration - SatTrack • Risk Mitigation

  3. 5 Space Technology “Tomorrow’s Technology Today” GSFC Introduction ST5 PDR June 19-20, 2001 19-3

  4. Combined Ground System & Operations Launch Dress Rehearsal SIM GROUP 1 SIM GROUP 2 SIM GROUP 3 Readiness Test-9 & 10 Readiness Test-7& 8 Readiness TeST5 Readiness Test-4 Readiness Test-1 Readiness Test-6 Readiness Test-3 Readiness Test-2 Tech. Aliveness Test-1 . Test-30 . Test-2 . Test-1 . Test-4 Tech. Aliveness Test-3 Tech. Aliveness Test-2 Network Test-1 Network Test-3 Network Test-2 Compat Launch Compat Compat Compat Msn Msn Msn Msn Msn Msn Msn Msn 3/02 6/02 9/02 9/01 3/03 6/01 9/03 12/01 6/03 12/02 12/15/03 MRR MOR CDR FOR PDR Draft FPD Final FPD Final DMR Final OCD Draft FOP Fin FOP Review OCD

  5. Documentation • Operations Concept Document - Preliminary complete • Flight Operations Plan • Flight Procedures Document • Launch & Early Orbit Handbook • Detailed Mission Requirements Document - Preliminary complete • ASIST ICD - Heritage from MAP & EO-1 • FD ICD • SatTrack Requirements Document - Complete • SatTrack Statement of Work - Complete • SatTrack ICD • Ground Station Requirements Document - Complete • Ground Station Statement of Work - Preliminary complete • Ground Station RF ICD

  6. Major Milestones

  7. 5 Space Technology “Tomorrow’s Technology Today” GSFC Mission Operation Center Integration 19-7 ST5 PDR June 19-20, 2001

  8. Requirements/Approach • The GDS shall provide interface support for the Autonomous Network Scheduling and Orbit Determination S/W(MRD 30401000) • ASIST shall interface with SatTrack via a TCP/IP socket for ascii file transfer • The mission shall be capable of supporting “lights out” operations(MRD 30500000) • Standard GSFC automation approach with ASIST and SERS, except for the addition of the ST5 tech demo of SatTrack • Approach • In-house mission operations center will be co-located with one of the existing MOCs in Bldg. 14, such as MAP, TRACE or EO-1 • Heritage system in an existing facility will reduce risk and save money by taking advantage of security perimeter, redundant utilities and communications. (Note: FOT and systems are not planned to be shared) • FOT training and control center checkout to occur during I&T

  9. Data Flow Diagram GPS - Ranging - Data transfer - Science event GSFC-site ST5 Experimenter Operations Center ST5 Mission Operations Center - Exp Planning - Instrument Eval - Experiment Data Processing EARTH RealTime System Offline System RTADS (Nominal) RTADS (L&EO) -Near RealTime Attitude Determination for Launch & Early Orbit - Maneuver Planning Magnetometer (ASIST Assoc) - Uplink/Downlink on X-Band - Two way Doppler Tracking Attitude Telemetry MMFD/Nom Ops -Bldg 28 - Orbit Predict JPL CCNT Ground System Commands - Sun sensor - Magnetometer - Attitude Ground Station Recorder Data/VC# - Predicted Orbit NISN ASIST - Telemetry Monitoring - Command Load & Uplink - Data Storage - Limit Checking - Events Monitor - Automated STOL Proc Exec Real time Data/VC# Mission Planning System Planning Aids SatTrack/Tech Demo - Automated Ground Station Scheduling and - Orbit Determination Commands/VC# Data Auto-STOL Proc/Status NASA Integrated Services Network Orbit Pred Tracking Tracking Orbit Skytel Paging Service VMOC Data Server PAGE FOT

  10. Mission Readiness Test Flow Three Series of Tests (FlatSat, S/C No.1, Constellation) Jan’03 - Apr’03 May’03 - Jul’03 S/C No.2 & No.3 Integration & Test S/C No.2 & No.3 Environmental Tests Aug’02 - Oct’02 Nov’02 - Mar’03 S/C No.1 Integration & Test S/C No.1 Enviromental Tests Apr’03 - Jun’03 Nov’02 - Mar’03 May’02 - Oct’02 Constellation Test Series - RF Compatibility Tests (No.2&No.3 - Pre-TV) - Technology Aliveness Test No.3 - Comprehensive Timing Test No.3 - FINAL End - to - End Test (Cmd & Tlm Test) S/C No.1 Test Series - Basic Timing Test No.2 Tech Aliveness Test No.2 - PTP Validation Test - RF Compatibility Test(Pre-TV) - Basic Timing Test No.2 (in TV) - RF Compatibility Test (Post-TV) FlatSat Test Series - Basic Timing Test -MOC Set-up Test - Tlm & Cmd Processing Test - Tech Data Validation Test -Cmd Management Test Apr’03 - Jun’03 Ground Segment Test Series with FlatSat and/or S/C No.1 - TT&C Ground Station Tests Mission Planning & Scheduling Tests - SatTrack Lights-out Test Comprehensive Ground Station Test - Mission Science Data Processing Test Feb’03 Aug’02 Jul’03 Simulation No.2 S/C 1 (Env) Simulation No.1 (FlatSat) Simulation No.3 S/C 2 & 3 (Env)

  11. Status • High level integrated schedule with I&T developed • H/W and S/W purchases (ASIST/FEDS) • I&T, Ops, subsystem staffing for I&T, Mission Readiness Tests and Mission Operations in work

  12. 5 Space Technology “Tomorrow’s Technology Today” GSFC Ground Data System-ASIST 19-12 ST5 PDR June 19-20, 2001

  13. Requirements • The Mission shall validate the ability to take measurements and to handle the downlink and ground data processing of multiple data streams from multiple S/C (MRD 20300000) • New ASIST capability where the FEDS will contain multiple ingest cards and data streams will be sorted by S/C ID • Existing data interface protocols will be used with SERS, FD, MPSS, and new technologies (SatTrack and CCNT) • The facility shall have the ability to connect with the vehicle(s) at both baseband (i.e. Hard-Line) and RF (MRD10303080 - supporting) • Heritage connection where the FEDS shall have the ability to connect to the vehicles during I&T • CCSDS recommendations shall apply to space/ground com channels and to basic space/ground services provided to instruments by the S/C (MRD 10303050) • CCSDS applications are heritage systems

  14. Requirements/Approach • Time correlation between the S/C clock & Coordinated Universal Time (UTC) shall be known to within 5 msec (3 sigma) (MRD 20500000 - supporting) • Heritage from EO-1 for Return Data Delay (RDD) time correlation • Ground station will append the time each VC0 CADU was received at the ground station to the internet protocol data unit (IPDU) header and the FEDS will read both S/C time and ground station time tag to determine S/C to UTC time difference • Approach: Heritage systems from IMAGE, EO-1 and MAP; ST5 FSW re-using MAP FSW; ST5 C&DH re-using MAP processor

  15. S/C 1 S/C 2 C & DH HDS S/C 3 I&T and Operations Command & Telemetry Flows ASIST Science Workstations I & T Only CCNT Workstations S/C Data System Bit Sync I & T GSE ASIST Primary Workstation ASIST Associate Workstations S-Band Rcvr X- to S- Down Converter S/C Test Connection Data CLK I/F Box Diplexer X-Band Xponder RF PCI Serial I/O FEDS TSS2000 Modulator BPSK ACB2 S- to X- Up Converter Packet Distribution System R/T Buffer (S/W) Frame Sync (S/W) (CRC, RS) Cmd Processor Gnd Stat I/F NISN Ground Station Time Code Card Digital History Data Storage (DHDS) TCPIP Ops Only

  16. Status • ASIST Workstation deliveries to FSW and GNC (for HDS) completed • FEDS (Front End Data System) in development for C&DH • Timing card will be included • FEDS and ASIST deliveries to FlatSat and FSW in first quarter FY02 • Testing multiple ingest cards in FEDS • ASIST Build 9.1 (some updates with multiple data streams) • Working data management and verification of crosslink data from CCNT

  17. 5 Space Technology “Tomorrow’s Technology Today” GSFC Ground Station/Network 19-17 ST5 PDR June 19-20, 2001

  18. Requirements • The ground segment shall provide one 20-minute contact window per S/C every orbit below 5 Re altitude (MRD 10801000) • For nominal operations, ground stations being required to provide 30 minutes of visibility for simultaneous data command, telemetry, and tracking, • Extra time added for link acquisition and margin • Stations must be compatible with new ST5 technology transponder; sweep, acquire and lock as listed in the ground station requirements specification • Data recovery goal for ground station is 90% (space to ground), in support of technology and science validation requirements minimum of 70% of on-orbit generated data constellation in total shall be received by the ground(MRD 10800000 - supporting)

  19. Requirements • The ground station network shall provide X-band command uplink capability, in at least 1 station(MRD 10104041) • 2 stations are highly desirable for more coverage with orbit uncertainties and as a back-up station • Nominal operations may be capable to work with a less-than-once-per-orbit uplink command window (i.e., every 2nd/3rd pass) • Time correlation (update S/C clock), tracking and operational scenarios will determine the uplink contact frequency • The system uplink data rate shall be 1 Kbps.(MRD 10303061 - supporting) • New X-band equipment required, but data rate is not challenging

  20. Requirements • The S/C shall have 2, ground selectable, downlink data rates: 1 Kbps (2 Ksps) and 100 Kbps (200 Ksps) (MRD 10303063 - supporting) • The S/C shall be capable of supporting the high rate downlink to a communications range of 5 Re.(MRD 10303065 - supporting) • The S/C shall be able to support the low data rate downlink at any point in the orbit(MRD 10303066 - supporting) • The ground station shall be capable of performing Doppler tracking in support of orbit determination (MRD 10301020) • The system radiometric Doppler tracking accuracy shall be sufficient to support ground antenna pointing at distances of 2 to 5 Re. (MRD 10301011 - supporting) • Ground station oscillator must be stable enough to support • The system shall be capable of supporting the mission using only one-way Doppler measurements from the S/C (10301012 - supporting) • Transponder oscillator will determine performance

  21. Orbit Scenario Nominal Operations Total contact time required per orbit: ~90 mins (1.5 hrs) - Range limited between 2 - 5 Re for simultaneous: - Recorder downlink at 100 kbps (range limiting factor) - Real-time downlink at 1 kbps - Command uplink at 1 kbps - Two-way Doppler tracking Apogee @ ~5:15 5 Re @ ~7:08 L&EO: No time specs, need schedule flexibility Any Point in Orbit for simultaneous: - Real-time downlink at 1 kbps - Command uplink at 1 kbps - Two-way Doppler tracking 2hrs&24mins 144mins 5 Re @ ~3:22 2 Re @ ~9:32 Perigee @ ~10:31 2 Re @ ~0:58 Notes (for s/c illustration): All attitude and orientations not to scale S/C and antenna beam not to scale S/C distances not to scale Perigee @ ~0:00

  22. Orbit Analysis - Preliminary Assumptions: Apogee at ascending node, perigee at descending node, Epoch December, Antenna spinning 86-40ºoff boresight, inclination of 25 º, eclipse not included L&EO Req: Flexibility to ensure H&S C/O----> Nominal Operations Req: 180 mins/day ---->

  23. Requirements • Ground station-received AGC levels in addition to auto-tracking antenna angles shall be provided (MRD 10104024) • Ground stations to provide data each pass in support of transponder performance validation • Information is currently available today - no changes • Time correlation between the S/C clock and UTC shall be known to within 5 msec (3 sigma) (MRD 20500000 - supporting) • Telemetry received by the ground network shall be time tagged to an accuracy of at least 1 msec (3 sigma) of UTC (20504000) • With today’s GPS H/W at the ground stations, this can be accomplished easily

  24. Approach • Modify an existing station network to support ST5 • Many existing stations have S-band transmitter with an X-band receiver and the receiver is compatible with ST5 transponder • DSN only station network with X-band transmitter and receiver (not planning to use DSN for ST5 Operations)

  25. Status • Requirements document (ST5-495-052) completed • SOW (ST5-495-064) and Task Order in process • Preliminary visibility analysis completed • Major Milestones • Ground station (commercial or government) on board - August 2001 • Ground Station ICD - December 2001 • RF Compatibility tests - November 2002 • MRT- Operational Readiness - May 2003

  26. 5 Space Technology “Tomorrow’s Technology Today” GSFC Flight Dynamics ST5 PDR June 19-20, 2001 19-26

  27. Approach • Pre-launch-develop and verify tracking method • Pre-launch support for 2-way Doppler tracking requirement definition and verification • Post launch, MMFD located in Bldg 28 (GSFC) is prime for OD support at launch and during nominal mission operations • Orbit determination within 10 km for ground antenna pointing • An 11-m ground antenna at a distance of 2 Re from S/C, orbit position knowledge of 24Km (3 sigma) or a deviation of no more than 8Km (1 sigma) • Maneuver support during launch and early orbit • Attitude and orbit determination • Attitude and orbit product generation • Products required throughout operations

  28. 5 Space Technology “Tomorrow’s Technology Today” GSFC Autonomous Network Scheduling and Orbit Determination S/W Requirements 19-28 ST5 PDR June 19-20, 2001

  29. Technology Demonstration • Technology Provider - Bester Tracking Systems, Inc. • Technology Description • Future Ground Operations Automation for Constellations Enabling Technology • S/W tool to perform autonomously • Ground station scheduling and orbit determination • Experience • 1st revision to be used on HESSI • HESSI uses GSFC’s ITOS ground system • Technology Readiness Level => Currently: 4 (SatTrack) => Currently: 2 (New tools) => Phase D: 7 • Ground station schedule conflict resolution • Station view periods, dynamic link margin, S/C emergencies, time constrains • Flight Dynamics Requirements • Includes comprehensive products such as orbit determination, mission planning products, state vectors, real-time graphic & alphanumeric displays

  30. Requirements • The system shall validate the Autonomous Network Scheduling and Orbit Determination S/W (MRD 10108000) • In addition to actual assets for the mission (i.e. 3 S/C and 2 ground stations), a set of virtual assets (i.e. both S/C and ground stations) shall be simulated and supplied to the Autonomous Network Scheduling and Orbit Determination S/W for processing (MRD 10108020) • Flight validation of the Autonomous Network Scheduling and Orbit Determination S/W shall be accomplished through comparison of the generated output with standard orbit determination S/W and manual ground resource scheduling techniques (MRD 10108010) • Anomalous operation of the Autonomous Network Scheduling and Orbit Determination S/W shall not degrade the operation of the S/C (MRD 10108040)

  31. ST5 Mission Operations Scenario of 3 real and 97 virtual satellites

  32. Data Flow for SatTrack Validation Ground Station(s) Multi-Mission Flight Dynamics Tracking Data Orbit Determination Mission Planning Product Generation Schedules Telemetry Commands ASIST/FEDS SatTrack Commanding Telemetry Monitoring Data Storage Automated STOL Procedure Initiation Orbit Determination Mission Planning Product Generation Ground Station Scheduling Status feedback Command Loads Mission Planning / Scheduling System Mission Planning Load Generation Ground Station Scheduling Mission Planning Products

  33. SatTrack S/W Technology • Used for efficient management and Autonomous Operation of a Satellite Constellation • Autonomous scheduling of ground station contacts • Calculate station access based on number of constraints (line-of-sight, geometry, link margin) • Calculate priorities to resolve conflicts based on various input parameters • data volumes, station capability & availability, science requirements, S/C emergencies, operator overrides, etc. • Autonomous Orbit Determination • Derive updated state vectors from angle & range rate measurements • Verify & archive new state vectors • Generate mission planning products with new state vectors

  34. SatTrack Status • Status • Requirements document (ST5-495-046) completed • SOW (ST5-495-045) completed, waiting for proposal • Major Milestones • S/W delivery 1 (Orbit Determination Tool)-July 2002 • S/W delivery 2 (Automated Scheduling Tool)-February 2003 • Mission Readiness Test-April 2003

  35. 5 Space Technology “Tomorrow’s Technology Today” GSFC Risk Mitigation ST5 PDR June 19-20, 2001 19-35

  36. Risk Mitigation • Risk: No ground stations are currently compatible with ST5 transponder which lead to uncertainties with costs and schedule for upgrades • Mitigation: CSOC has identified potential vendors with a fixed-price cost estimate • Risk: Actual launch scenario not fully defined resulting in ground system uncertainty • Mitigation: Concerned about ground station visibility to meet requirements for L&EO, tracking, health & safety, and data recovery • Preliminary analysis has identified visibility against typical launch scenario • Risk: Staffing in the timeframe prior & during S/C No.2 & No.3 flow • Mitigation: Relying on subsystem personnel to supplement Mission Operations activities • Relying on an existing GSFC MOC facility with most interfaces for Mission Operations in place