1 / 10

ENERGY RENOVATION OF THREE OBJECTS OF GENERAL HOSPITAL TRBOVLJE IN SLOVENIA

ENERGY RENOVATION OF THREE OBJECTS OF GENERAL HOSPITAL TRBOVLJE IN SLOVENIA. Presentation for the “EWRC- European Week of Regions and Cities ” in Brussels by Zorislava Cimperman Construction Engineer of the Slovenian Ministry of Health and Project M anager.

mellor
Download Presentation

ENERGY RENOVATION OF THREE OBJECTS OF GENERAL HOSPITAL TRBOVLJE IN SLOVENIA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ENERGY RENOVATION OF THREE OBJECTS OF GENERAL HOSPITAL TRBOVLJE IN SLOVENIA Presentationforthe “EWRC-EuropeanWeekofRegionsandCities” in Brussels byZorislava Cimperman ConstructionEngineeroftheSlovenianMinistryofHealthand Project Manager

  2. 1. PARTICIPANTS IN ENERGY REPAIR CONTRACTIONG AUTHORITY:MINISTRY OF HEALTH OF REPUBLIC OF SLOVENIA USERORGANIZATION:GENERAL HOSPITALTRBOVLJE DESIGNER AND CONSTRUCTION SUPERVISOR:IBT SPI, Ltd., Trbovlje CONTRACTORS (JV-Jointventure):RUDIS, Ltd., TrbovljeAGM Nemec, Ltd., Laško INDEPENDENT MONITOR:Transparency International Slovenia

  3. 2. BASIC PROFESSIONAL CONTENTS OF REPAIR MEASURES • INSTALLATION OF THERMAL ISOLATION ON THE CEILINGS AGAINST THE UNHEATED ATTIC IN THE OLD PEDIATRIC BUILDING, THE LEFT AND RIGHT EXTENSION OF TRBOVJE PRIMARY HOSPITAL AND THE ROOF ON THE ADMINISTRATIVE BUILDING • ISOLATION OF ROOF PARTS • ROOF REPLACEMENT ON THE ADMINISTRATIVE BUILDING • RENOVATION OF THE FOUNDATION ON THE FRONT OF THE BUILDINGS (MOISTURE TRANSMISSION PREVENTION AND REPAIR AND PREVENTION OF DAMAGE TO THE STRUCTURE DUE TO THE MOISTURE TRANSITION) • BEGINNING OF WORKS: 05/16/2018 • COMPLETION: 31/8/2019 • PROFESSIONAL SCOPES OF THE PROJECT: • RENOVATION OF THE FACADE OF THE BUILDINGS - OLD PEDIATRIC HOSPITAL, NEW OBJECTS TO THE LEFT AND RIGHT OF THE PRIMARY HOSPITAL OF TRBOVLJE AND OF ITS ADMINISTRATIVE BUILDING • REPLACEMENT OF OLD WINDOWS, ENTRY DOORS AND EXTERIOR GLASS WALLS IN ALL THREE OBJECTS • EXTERIOR BLINDS - BLINDS ON OLD PEDIATRIC HOSPITAL AND ROLLING SHUTTERS ON THE ADMINISTRATION BUILDING

  4. 3. BASIC REPAIR ACTIVITIES • VENTILATION OF HOSPITAL ROOMS AND CLINICS • INSTALLATION OF WELDING LAMPS, SENSORS AND REPAIR OF ELECTRIC CABINETS • REPLACEMENT OF RADIATORS • INSTALLATION OF THERMOSTATIC VALVES AND HYDRAULIC BALANCING OF THE HEATING SYSTEM • TOTAL REPAIR OF THREE HEATING STATIONS • INSTALLATION OF THE SOLAR HEATING SYSTEM FOR THE PREPARATION OF THE SANITARY HEATING WATER • INSTALLATION OF THE CCS (CENTRAL CONTROL SYSTEM)

  5. 4. ABOUT TRANSPARENCY INTERNATIONAL SLOVENIA • Ministry of Health and Transparency International Slovenia - Transparency International Slovenia signed an Integrity Pact on November 24, 2016, pursuant to the Cooperation Agreement of October 29, 2015, which they pledged to consistently ensure at all stages of the procurement process complied with the provisions of the law governing public procurement and other sectoral laws and legislation in the field of integrity assurance, and will consistently strive for transparent and ethical action in accordance with generally valid moral values. • On 11 October 2017, Trbovlje General Hospital signed a Form for Accession to theIntegrity Pact, stating that it agreed to accede to the Integrity Pactand to the rights enshrined in the Integrity Pactand committed itself to diligently fulfilling the obligations arising from theIntegrity Pact. • Transparency International Slovenia - The Integrity Society acts as an independent monitorin the project. • Cooperation between the public administration (Ministry of Health, Slovenia) and civil society Solid cooperation between Ministry of Health and Transparency International Slovenia TI Slovenia IP team with external experts has been a great addition to the project, providing independent monitoring in all phases of the tender (legal, analytical, technical skills) . Active cooperation with other stakeholders of the project in Trbovlje. • All the initiatives of the RS Integrity Pactserve as an example of good practice I feel the cooperation between Ministry of Health and Transparency International Slovenia has so far been very good. In two words I would describe it as strong and substantial. I am saying this as an project leader with 42 years of working experience. The work of the Transparency International Slovenia Integrity Pacts team with their external experts was in my opinion excellent in all the tender phases and as independent monitors they were a great addition to the project in analytical, technical and legal sense. They have checked every document, asked meaningful questions and provided us at the MinIstrywith useful recommendations. Through diligent weekly field monitoring they have also engaged with other stakeholders of the project with good results. They provided the hospital staff with the whistle-blower hotline and are still working with the hospital management to monitor the effects and savings of the energy renovation. They have also engaged with the local stakeholders with meetings at the start of the project and I would say they had good response from the local community in Trbovlje.

  6. 5. SOME IMAGES OF THE TRBOVLJE GENERAL HOSPITAL a) The building of the old hospital (built in 1925) anditsrenovation

  7. b) Administrationbuilding

  8. c) Pediatricclinic

  9. d) One ofthe extensions of the Trbovljeprimaryhospitalbuliding

  10. 6. FINAL VIEW OVER THE COMPLEX OF TRBOVLJE GENERAL HOSPITAL