Joint Base San Antonio 2011 Sustainable Energy Workshop. Anthony Martinez Joint Base San Antonio (JBSA) Energy Manager 12 July 2011. Overview. Shooting at the Energy Goals Beginning the consolidated JBSA approach JBSA Initiative – Bringing it all together. JBSA Shooting At The Goals.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

Anthony Martinez Joint Base San Antonio (JBSA) Energy Manager 12 July 2011


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Joint Base San Antonio

2011 Sustainable Energy Workshop

Anthony Martinez

Joint Base San Antonio (JBSA)

Energy Manager

12 July 2011

overview
Overview
  • Shooting at the Energy Goals
  • Beginning the consolidated JBSA approach
  • JBSA Initiative – Bringing it all together
background federal energy goals
BackgroundFederal Energy Goals
  • Energy Consumption
    • Reduce energy intensity (Mbtu/sqft) 3% annually thru 2015
  • Water Consumption
    • Reduce water use 2% annually thru 2015
  • Protect And Reduce Vulnerabilities in Infrastructure
  • Facility Advanced Metering by 2012
  • Renewable Energy
    • AF Goal: 3% on-base generation by 2015
      • Where economically feasible and technically practicable
jbsa energy goals
JBSA Energy Goals
  • Lagging Energy Metrics
    • $15M of Installation Project Efforts in 2010
    • Results not immediately evident – Energy Use Increasing
slide7

JBSA Energy

  • Magnitude
    • JBSA is the largest single consumer in the San Antonio metropolitan area
    • At any given time JBSA has 70 to 100K “users”
    • JBSA peak demands over 100 MW or 670M Kwh
  • Challenge
    • Obtaining goals thru growth at each Installation
    • Combining three Installations
    • Defining JBSA Energy Reduction Scope
      • Planning and Resources
slide8

JBSA Operational Energy Management Plan (OEMP)

  • Partnering with OSD - Plan to Manage Activity
    • Sets energy reduction priorities
    • Identifies over $60M in projects saving 100M Kwh per year
    • Baselines Goals and Objectives
  • Energy Intensity Objectives
    • Create a culture of conservation
    • Find our energy hogs
    • Out with the old…get rid of the
    • energy wasters
    • In with the new
    • Use other people’s ideas, talent,
    • and treasure
    • Control what we have
slide9

JBSA Operational Energy Management Plan (OEMP)

  • Directs JBSA Installation Project/Resource Focus
    • Projects with Biggest Bang for Buck
    • Analyzed Solar Technology versus Cost Effectiveness
    • Realigning JBSA Technical Resources and Strategy Sessions
    • Funding Sources – DoD/AF Funding insufficient
    • Partnerships – Project Resources
    • Energy Management Control Systems
      • Commander focus for 2011
      • Over $19M in next 3 years; $5M focus funds FY11; $14M FY12/13
slide11

JBSA Initiative

  • JBSA-centric Awareness Program
    • Full Court Press Campaign; workshops, stakeholders, public affairs, campaign materials, housing energy reduction
  • Partnerships
    • Office of Secretary of Defense – the Plan
    • CPS is providing full time support and coordination on all levels of effort
    • SAWS – beginning the dialogue
    • DTI – Innovation Center
  • Consolidating efforts and resources
  • Control what we have
slide12

JBSA EMCS

  • Energy Management Control Systems (EMCS)
      • Directed expansion and modification of EMCS; Industrial and Housing areas - $5M in 2011
        • Currently defining needs and requirements for acquiring new systems in 3 to 6 months
      • Scoping future requirements - $14M
      • Result: Demand/Cost reduction thru HVAC set points
joint base san antonio
Joint Base San Antonio

Questions?