1 / 11

Engineering Operations

Engineering Operations. New hazards in the NTC associated with upgrade activities: Ladders, scaffolds, man-lifts. Cranes, rigging, forklifts. Welding, burning, grinding. Activated/Contaminated radiological work. Electrical Confined spaces. Chemical use. Eye hazards. Uneven work surfaces.

mareo
Download Presentation

Engineering Operations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Engineering Operations • New hazards in the NTC associated with upgrade activities: • Ladders, scaffolds, man-lifts. • Cranes, rigging, forklifts. • Welding, burning, grinding. • Activated/Contaminated radiological work. • Electrical • Confined spaces. • Chemical use. • Eye hazards. • Uneven work surfaces. • A Health and Safety Plan (HASP) and Work Control Center Procedures in force. • Address the control of hazards • Maintain configuration control • Coordinate required permits, technical procedures, etc.

  2. Engineering Operations • Heavy Construction started this winter: • TF turnbuckles and clevis pads have been ground away.

  3. Engineering Operations • Space has been cleared for the 2nd Neutral Beam.

  4. Engineering Operations • Additional rib welding completed on the upper/lower domes. • New machine platforms installed.

  5. Engineering Operations • In-vessel metrology for NB armor installed and brackets welded in place. • Passive plates were reinstalled in April.

  6. Engineering Operations • Outer TF coils #7 and #11 have been removed.

  7. Engineering Operations • Platform modifications/usage required for the TF work

  8. Engineering Operations • Bay J-K nozzles have been cut away

  9. Engineering Operations • Upcoming Vessel Modifications: • Installation of In-vessel stiffeners at Bays J-K. • Ongoing welding of new TF Clevis pads onto VV. • Weld the new Bay J-K Cap onto the vacuum vessel in early July for the new NB port. • Vacuum vessel cuts at Bay L in mid-July for MPTS. • Vacuum leak checking • Remove platforms at Bays J-K-L in preparation for neutral beam work

  10. Engineering Operations • Neutral Beam work in the NTC: • Penetrations into NTC for cryo/electrical systems. • Move Beam-Line into NTC in early August. • Move lid/cryo-panels, 90” flange, torus and ion source interfaces into NTC in Aug/Sept • Decontamination of both the NTC and the TTC • Installation of beam-line systems and HVE’s throughout the fall.

  11. Engineering Operations • Future NTC Access: • Upon completion of the NB equipment moves, we should be able to provide greater access to the perimeter of the test cell. • Access to the North door will remain limited while assembling/commissioning the NB HVE’s and transmission lines. • Internal and External access to the vessel itself will remain restricted into the spring of 2013 due to ongoing welding of the umbrella legs, PF supports, etc.

More Related