INSPECTION PENRICE ANGASTON QUARRY OPERATION

INSPECTION PENRICE ANGASTON QUARRY OPERATION. Thursday 19 February 2009. MPL 118 . Determine compliance against the applicable obligations as set out in the Mining Act 1971, the lease conditions and approved mining and rehabilitation program, number 2008/026.

marek
Download Presentation

INSPECTION PENRICE ANGASTON QUARRY OPERATION

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. INSPECTION PENRICE ANGASTON QUARRY OPERATION Thursday 19 February 2009

  2. MPL 118 • Determine compliance against the applicable obligations as set out in the Mining Act 1971, the lease conditions and approved mining and rehabilitation program, number 2008/026.

  3. “The Licencee must in constructing and operating the Licence, ensure that there are no public nuisance impacts from noise emanating from the Licence. “ • Noise levels from onsite sources are below the SA EPA Environmental Protection (Noise) Policy 2007. • Use of heavy mine vehicles and equipment only between the hours from 7am to 5.30pm, Monday to Friday and 9am to 1pm Saturdays. (non public holidays)

  4. no nuisance impacts to local residents and adjacent land uses from air emissions and dust generated by mining operations • Within 3 months of licence commencement a suitable qualified consultant will develop a nuisance dust sampling program • Dust analysis not more than the National health Standard

  5. “..responsible for recording and addressing complaints received from the public with respect to the mining operations “. • Penrice are now entering all complaints on a register and this information is being presented at the PCCG. • One of the complaints alleges that considerable noise was generated from a road trucks leaving the site at 2.15am on the 8 February 2009. On inspection of the timesheets and the road truck logs it was found that the last truck left the site at 2145 hours on the 7 February 2009.

  6. “..ensure that there is no clearance of native vegetation within the riparian zone of the Jaeckeli Creek • Compliance with the Native Vegetation Act 1991 • A vegetation management plan to be in place within 3 months • Management strategy is for no overburden to be placed within a 25m buffer each side of the centre line of Jaeckeli Creek outside the Private Mine.

  7. “..ensure that the existing soil quality and quantity is maintained. “ • topsoil is being excavated and stockpiled for reuse in advance of the overburden being dumped.