Commissioning / Reliability Runs / Dry runs

Commissioning / Reliability Runs / Dry runs. Safety OK before summer. Keep system working / software. LBDS Reliability Run in Local. Planned 17/02/14 – 09/05/2014: 12 weeks Aim: Find initial system faults (bathtub curve) Confirm reliability numbers from the past with

marek
Download Presentation

Commissioning / Reliability Runs / Dry runs

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Commissioning / Reliability Runs / Dry runs Safety OK before summer Keep system working / software Jan Uythoven, LIBD meeting on LBDS Reliability Run

  2. LBDS Reliability Run in Local • Planned 17/02/14 – 09/05/2014: 12 weeks • Aim: • Find initial system faults (bathtub curve) • Confirm reliability numbers from the past with • Modified equipment freshly installed • Running at increased energy • Our main concerns at the moment • Voltage holding at top energy • Assume running at 7.1 TeV • Extensive running at full energy • Stability of the pulses at injection energy • Especially after longer period at full energy • Sufficient number of pulses for fault statistics Jan Uythoven, LIBD meeting on LBDS Reliability Run

  3. Proposed programme t flat top pulse E 7.1 TeV pulse 450 GeV dtinj t inj t • Infinite number of loops WinCC Simulator Cycle Simulation • Add dt pulses at flat bottom energy • t flat top = 10 h ; t inj = 2h 5 min; dtinj = 10 min; t ramp = 20 min • An energy scan once per week  see next slide • Option to (later) integrate in AccTesting with automatic analysis Jan Uythoven, LIBD meeting on LBDS Reliability Run

  4. Energy Scan 5 pulses at each energy. Add the higher energies. Jan Uythoven, LIBD meeting on LBDS Reliability Run

  5. Total Number of Pulses expected • Compared to B1 in 2008, only 14 % of the number of pulses (but twice as many as for B2) • Are the number of pulses sufficient for statistics? • Roberto’s thesis requests 3 months running period, 75 % running efficiency and pulse on average one time every hour: would expect six failures 2 LBDS systems for SIL3 system. This is ’only’ 1’512 pulses which we expect to easily achieve, but not at 7 TeV… • Don’t want to wear out the system too much • However, effective running time at 7 TeV should be high Jan Uythoven, LIBD meeting on LBDS Reliability Run