1 / 13

D2 Roadway Discussion Sound Transit Board September 22, 2011

D2 Roadway Discussion Sound Transit Board September 22, 2011. Today’s Presentation. Up-date on the D2 Analysis Discussion next steps. D2 Transitway Operations. EIS evaluates joint bus-rail operations and rail only operation Both options are feasible

manny
Download Presentation

D2 Roadway Discussion Sound Transit Board September 22, 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. D2 Roadway Discussion Sound Transit Board September 22, 2011

  2. Today’s Presentation • Up-date on the D2 Analysis • Discussion next steps

  3. D2 Transitway Operations • EIS evaluates joint bus-rail operations and rail only operation • Both options are feasible • During the East Link construction the D2 will be closed to all traffic • Experience with Downtown Seattle Transit Tunnel (DSTT) indicates joint operations impacts transit reliability 3

  4. Future Light Rail Network Lynnwood • Two operating lines in the future • The peak load point for the system is in the DSTT • Assumes 8 min. headways and 4-car trains • Critical that NB trains from the south and east arrive at the merge point on schedule • Potential to operate 6-min. headways with 3-car trains Northgate 4-min. Headways Overlake D2 Transitway Area 8-min. Headways/ 4-car trains Kent / Des Moines

  5. Status of Analysis • Operations and Administration Committee was briefed on the D2 Roadway operations at the July 21st meeting • Since July ST has been working closely with Metro, WSDOT, and the City of Seattle to refine options which include: • Modifications to joint operations • Adding a bus only lane on the D2 • Surface options if buses do not use the D2 • Possible bus/rail integration options at S. Bellevue Park & Ride and Mercer Island

  6. D2 Busway Joint Use ROW • D2 covers 1.4 miles • Several tight curves and grades • EB and WB lanes separated by barrier

  7. Rail Operations on the D2(Under Joint Operations) • With joint operations trains will not be able to use Automatic Train Protection (ATP) mode which potentially affects safety and reliability • Instead trains will operate in line of sight mode: • “Operate at a speed that would allow the operator to identify, react and stop the train within ½ of the distance of the obstruction ahead.” • Train speeds under joint operations are estimated to be 1 minute slower WB and 1.5 minutes slower EB

  8. Bus Only Lane on the D2 • Light rail tracks would be constructed to one side • An 11ft wide bus lane would be added to the D2 • Bus lane evaluated as reversible or outbound only • Bus travel times are faster than with joint use • Light rail vehicle would be able to run in ATP mode • Additional engineering is required, as is approval from WSDOT and FHWA

  9. Surface Street Options • D2 would be rail only • Buses would use either I-90 mainline to 4th Ave or Rainier Ave and Dearborn St. to and from downtown • Results in longer bus travel times, especially in the PM peak period • Affects bus reliability

  10. Bus Integration Option • Bus travel times are longer to the south end of downtown due to transfer • Bus hours savings could be redeployed

  11. Conclusions

  12. Next Steps • With Board concurrence, ST will recommend to FTA that the ROD specify rail only on the D2 Roadway • ST and King County will enter into an agreement and develop a work plan to evaluate the busway option and other options including bus/rail integration • If the busway option proves to be unfeasible, ST and KCM will jointly reconsider other alternatives

  13. Summary of Options Considered

More Related