1 / 25

D0 Trigger Status

D0 Trigger Status. 7 MHz input rate Data. Status reports March and Beyond. Framework. Data Log. L1 4.2 m s. L2 100 m s. L3 48+ ms. 50 Hz. 5-10 kHz. 1000 Hz. 48 nodes. 256 terms 128 bits. 128 bits. L1CAL. Detector/L1/L2 Components. L1 LUM.

manny
Download Presentation

D0 Trigger Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. D0 Trigger Status 7 MHz input rate Data • Status reports • March and Beyond Framework Data Log L1 4.2 ms L2 100ms L3 48+ms 50 Hz 5-10 kHz 1000 Hz 48 nodes 256 terms 128 bits 128 bits

  2. L1CAL Detector/L1/L2 Components L1 LUM LUM L2Cal CAL L1 FPS FPS L2PS CFT/ CPS Global L2 L1 CTP L2CFT L2STT SMT L2 Muon L1 Muon Muon L2FW:Combined objects (e, m, j) L1FPD FPD L1FW: towers, tracks, correlations

  3. Luminosity Monitor March 1 • Electronics • TDC preprod boards expected this week • 9 production boards arrive in March • Vertex FPGA design nearly complete • 2 Vertex boards finished in April • Installation • Detector mounted for 10 months. • Cables Installation started, ~1-2 wks. • One day of beam for timing. • Completion dates for various subsystems • Expect minbias triggers to be available at first beam, with Run I electronics. • Expect luminosity will be logged and made available on ACCNET within 1 week of first beam • Expect all electronics to be in place by the end of April • Expect multiple interaction triggers, luminosity database to be completed by the end of the year March L1 Luminosity: Minbias

  4. L1 CTP/FPS/FPD Analog Status • AFE 8MCM (CFTax),(Fermilab-D0) • Have ten prototypes. • On bench, expect 2 weeks for LHB/RHB noise tests (<7 fC roughly 1 P.E.) • Four weeks to build, eights weeks to stuff. RHB mid/late-April. LHB mid-May. Need at least two weeks to check. • Earliest installation early May. • Order enough for entire central tracker. • AFE 12MCM (FPS): • Motherboard layout nearly done. • Daughterboard prototype has been simplified to reduce power consumption, heat load, and real-estate. • Corresponding reduction of capability: L3 readout of discriminated bits. • Prototype some time in April. • In April decide between modified AFE8 or AFE12

  5. L1 CTP/FPS/FPD Digital Status • Mixer(Fermilab-CD) • A half super-sector expected this month. Bare boards this week (2 of 20 boards.) • Place order in March • Full Mixer April-May • Crate/PS on hand • DFEA/DFES/Broadcasters/ Collecters(Fermi-D0) • All 120 Motherboards here. • All 125 Transition modules here. • 35 of 88 DFEA single-wide daughter boards here. Complete boards this wk. • Double wide daughter boards here, parts mostly here. • Crates: 4/4 DFE, 1of2 CTT, 2/2 PS

  6. Firmware Status • AFE: Complete • Digital: Design 90% / Code70% / Implementation 60% / 7 out of 14 units tested in hardware • Simulated/implemented entire DFEF+FPSS+FPTT Chain. • DFEA+CTOC+CTTT next few weeks • Expect CFT occupancy and track trigger April 2.

  7. L1 CTP/FPS/FPD in March • Analog • 5-10 AFE8 prototypes. • Populate outer layers of upward pointing sector. Need to coordinate overlap with minimal L1 Muon configuration • Balance installed May-June • Digital • One-half sector mixer available • Some broadcaster/collector complement available. • Useful commissioning exercise. • Hit, track trigger. March 1: Some capability, mostly Installation/commissioning

  8. L1 CAL Component Status • 10000 first stage adders(SUSB) • One for each electromagnetic and hadronic tower • Printed circuit boards complement mid-February • Require surface mounted resistors. Values recently determined imminently. Delivery late March. • Will concentrate on CC • 2500 Drivers(SUSB) • 4 calorimeter, 1 trigger tower per driver • Hybrid prototypes, 2 week turnaround, balance, six weeks. • Also need resistor values • Sufficient prototypes for 8-10 trigger towers • 320 analog pick-offs(MSU) • Now prototyped. Days. • Goal –0.8 < h < 0.8 by March 15th • Operating Status • Powered • New Control Software running. • Peparing to replace analog pickoffs.

  9. L1 Cal in March • Tower Availability • March 1st a few (<10) towers • March 15th-20th CC • Depends on availability of adders/drivers/access • Towers over threshold • Global terms • March 30th Start EC • Detector/Trigger Commissioning. • Beam data to time in calorimeter towers. Starting w/ ‘scopes. • Calibrate L1 calorimeter trigger • Turn to EC March L1 Calorimeter: Commission w/ handful of towers Increasing capability through month

  10. L1 MUON Component Status • Crate Manager(10) • 4/10 production available & reading out • Still verifying functions • Motherboard(62) • Production versions arriving 18/62, remainder ordered. • Testing in progress, worked out of box! • Preproduction as backup. • Trigger Manager Flavor Board(8) • 8/8 production due soon (<2weeks). • Should know soon if ready for March, very similar to preproduction • Preproduction as backup • Scintillator Flavor Board(28) • Submitted for production last week • Delivery ~4 weeks for stuffed boards. • Preproduction as backup

  11. L1 MUON Component Status • PDT Flavor Boards(28) • 5/28 due soon (<2weeks) • Preproduction as backup • Infrastructure & Software • Cables/PS in progress • Still need ORC. • Download in place • Preproduction versions of all firmware. • No alarms, monitoring • MCEN crate manager • Preprod testing in progress • Begin fabrication early April • MCEN Centroid finder • Production layout in progress • Begin fabrication early March • MCEN Physics Boards • Production starting (<2weeks)

  12. L1 Muon Outlook • March 30 • Central trigger crate with several wire and scintillator octants (prod) • End trigger crates each with one “scintillator” octant (prod) • One MCEN crate readout with a few MCEN’s (preprod) • April 30 • Trigger crates fully populated, cards in hand, depends on testing • July 1 • MCEN crates fully populated, in hand, depends on testing. March L1 Muon: A few central octants to start Increasing capability through month

  13. L2 Component Status • a-processors (MSU,UIC,UVa) (15 minimum): • Production Status • Preproduction: 2 worked “out-of-the-box”. • First production failed: 0/~25 boards • Diagnostics @ CD,UIC • Since November Extensive repair program at CD, UIC • Problems with broken chips, vias, non-standard design practices. • Three boards work! Two more with minor problems, Six more promising • Future • Continuing Effort. Expect 6-11 cards by March 1st. • Examining layout, use remaining parts to make ~12 new boards. In progress. May-June? • Complete redesign based on off-the-shelf hardware, prototype summer (L2BETA)

  14. L2 Components Cont. • MBT I/O Cards(U-Maryland) (30): • All production cards received. • To be checked by the end of March • Firmware functionality 90% done, complete mid-March • FIC L1/L2 Interface(SACLAY, UIC) (12) : • Boards complete • Some transmission errors noted. • Modified a single card at Saclay, testing this week. • SLIC Parallel Proc.(NIU,Columbia)(25): • Boards complete • DSP Central algorithm meet speed/efficiency requirements. Significant work on DSP forward. • Full development of software another 2 months. • CIC, SFO Muon/L2 Interface (U-Neb): • 2 CIC preprod: 1 passes, 1 has errors • SFO preprod passes most tests • Looking for production delivery end of April

  15. L2 Status Continued • Operating Software • C++ Framework exists • Various Drivers in place by mid-March to April • Processor algorithms,fairly well developed • Global in simulation January • Cal in simulator January • Muon March • Infrastructure: • MCH and test stand racks and crates 95% done. • Cabling 65%, long runs complete, will start final dressing soon. • Complete in March

  16. L2 Prospects • Feb/March • 6-11 Alphas: Test Stand (2), Global (2), Muon or Cal (2) • Attempt to complete Muon Integration (CIC/SLIC/SFO/ MBT/ALPHA) • Begin Cal Integration (FIC/MBT/ALPHA) • April/May • 6-23 Alphas: Test Stand (2), Global (2), Muon (2-4) or Cal (2-4), CTT/PS (2-5) • Preprocessors to Global • L3/DAQ • Start PS/CTT March L2: Depends on Repair Success, Commissioning Muon/CAL.

  17. Digitizing Crates (2 of 16 groups) Data pathway o o o Receiver Collector (1 of 8) o o o VBDs Fiber Path (8 total) Event Tag Generator Levels 1,2 Trigger data o o o o o o Event tag path o o o o o o Segment Bridge Processor Nodes (4 groups of 16) DAQ/L3 Currently VRC, SB, ETG emulated w/ capability of ~500 kByte/second.

  18. Implementation December, 2000 • Four unique types of cards • Event Tag Generator (ETG) (1) • Event Tag Generator Int. (ETGI) (4) • VBD Interface (VBDI) (8) • Serial Interface Board (SIB) (256) • SIB appeared in almost all components • VRC = VBDI + SIB • SB = ETGI + 12 SIB • Node = Motherboard + 4 SIB • SIB design nearly complete but could not be routed according to design rules. Too ambitious for form factor.

  19. Implementation January 2001 • Response: • Simplify designs by building cards with functionality limited to specific site. • Short term: • Build a SIB1 or “SIBling” with functionality only required for VRC (to be used later in ETG) • Supplement this with increased ethernet capabilities. ~100Hz • Long term: • Stage upgrade by building SIB2 and SIB3 which are more specifically targeted to SB, L3Nodes, ETG and final VRC. • Current Status • SIB1 • At vendor, 20 bare boards to be shipped between Thursday and Tuesday • Assembled, at Brown 2/22 • VBDi • At vendor today or tomorrow. • Assembled, at Brown 2/22 • Designs of other cards well along, can be derived from work with original SIB

  20. L3/DAQ Schedule • Stage1 3/22 • 50 Hz • VBDi/SIB at D0 • Ethernet upgrade • >100 Hz • Still discussing implementation • Stage 2 6/14 • ~200 Hz • Additional VRC,SB Hardware • Stage 3 7/19 • 1 kHz • Final Hardware • L3 Review Committee (Schamberger, Fuess, Blazey) reviewing design, schedule weekly March L3: 50 Hz Improving Capability

  21. Filtering • Extensive Operating Experience • July Participated in SiDet 10% tests. • Sept unpacking calorimeter, muon • Nov Demonstrated streaming • January Mark&Pass, muon unpacking, TFW • Currently ported to NT • Filtering Control: L3FMarkandPass, L3Prescale • Filter tools: l3tCalunptool, l3fmuo_unpack • At First Beam • Calorimeter: MarkandPass, Calunpack, Single Jet, Missing Et • Muon: Scintillator Coincidence March L3filtering: Calorimeter unpacking Muon scintillator coincidence

  22. Database • Trigger Database design nearly complete, includes all three levels. • Contains triggers lists for online running, trigger simulation, early running. • Production release soon. Hope to go on-line within a month or two. • Starting to work on user interfaces.

  23. Trigsim • Production Release p06.00.01 now available • All L3 levels in ROOT format • Raw Data and Cal Trigger Tower Chunks • Default output • MC information • L1 Cal towers • L1FT, PS • L1 FWK • L2 Cal jet, mEt, electrons • L2 global jets, electrons • L3 Cal mEt, jets, kt jets, electrons, cft, global tracking, smt, tau • Use d0sim p07.00.01 • P08 Release • Will have a L1/L2 Trigger Menu • L1muon, L1ft, L2Global improvements

  24. March Expectations • Level 1: • Minbias trigger • Commissioning Track/Preshower Trigger • Handful Calorimeter Trigger Towers • A few Muon Octants • Level 2: • Not in trigger • Depends on Alpha Repair • Integrating Muon first • Level 3: • Optimistically 50 Hz • Cal/Muon filtering March : Enough to get started Rapidly Changing

  25. Long Term Expectations • Luminosity April • L1 Tracker (Central) >May • L1 Tracker (Forward) >June • L1 Calorimeter May • L1 Muon May • L2 Global/Cal/Muon June • L3 1kHz July • Some final comments • Lots of progress • People are working very hard. • Still along way to go • Preoccupation with hardware has lead to a great need for help with on-line programming.

More Related