Pallatana GBCCPP. Unit 1 - 363.3 MW – Sch. commissioning : Dec’ 11 Unit 2 – 363.3 MW – Sch. Commissioning: Mar’ 12 Being established by ONGC Tripura Power Company Limited (OTPC) at Pallatana, Tripura. Power Allocation. Power Evacuation System.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Pallatana GBCCPP' - mandell


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
pallatana gbccpp
Pallatana GBCCPP
  • Unit 1 - 363.3 MW – Sch. commissioning : Dec’ 11
  • Unit 2 – 363.3 MW – Sch. Commissioning: Mar’ 12
  • Being established by ONGC Tripura Power Company Limited (OTPC) at Pallatana, Tripura
power evacuation system
Power Evacuation System
  • Required by December 2011 along with Unit-1 (363.3 MW).
  • Group -1
    • Pallatana Switchyard - OTPC
    • Pallatana - Silchar T/L – NETC
    • Silchar sub-station – POWERGRID

B. Group -2

    • Pallatana- Surajmani Nagar T/L – POWERGRID
    • Surajmani Nagar sub-station – TSECL

C Group -3

    • Silchar – Hailakandi T/L – POWERGRID
    • Hailakandi sub-station – AEGCL

D Group -4

    • Silchar- Srikona T/L- POWERGRID
    • Srikona sub-station – AEGCL

E Group - 5

    • Silchar- PK Bari T/L – POWERGRID
    • PK Bari sub-station – TSECL
power evacuation system continued
Power Evacuation System (Continued)

F. Group - 6

    • Silchar- Imphal T/L – POWERGRID
    • Imphal (new)sub-station – POWERGRID
  • Group – 7 – POWERGRID
  • Silchar – Melriat T/L
  • Melriat (new)sub-station
  • Group – 8 – POWERGRID
  • Passighat- Roing – Tezu- Namsai T/L
  • Roing sub-station
  • Tezu sub-station
  • Namsai sub-station

I. Group- 9 – POWERGRID

  • LILO of Kathalguri – Misa T/L at Mariani (new)
  • Mariani (new) – sub-station
  • Mariani (new) – Mokochung T/L
  • Mokochung sub-station
  • Mokochung (POWERGRID) – Mokochung (Nagaland) T/L
power evacuation system continued1
Power Evacuation System (Continued)
  • Required by March 2012 along with Unit-2 (363.3 MW).
  • Group -1
    • Silchar – Bongaigaon T/L - NETC
    • Bongaigaon sub-station – POWERGRID

B. Group -2

    • LILO of Silcahr –Bongaigaon line at Byrnihat sub-station – MeECL
    • Byrnihat sub-station – MeECL

C. Group -3

    • LILO of Silcahr –Bongaigaon line at Azara – AEGCL
    • Azara sub-station – AEGCL