Efficient Construction Scheduling Methodologies

Learn how to plan and schedule construction projects effectively with detailed examples and calculations to optimize workflow.

Download Presentation

Efficient Construction Scheduling Methodologies

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. [例 1] 某项目经理部拟承建一工程,该工程由Ⅰ、 Ⅱ 、Ⅲ、Ⅳ、Ⅴ等五个施工过程。施工时在平面上划分四个施工段,每个施工过程在各个施工段上的流水节拍如表所示。规定施工过程Ⅱ完成后,其相应施工段至少养护2天;施工过程Ⅳ完成后,其相应施工段要留有1天的准备时间。为了尽早完工,允许施工过程Ⅰ和Ⅱ之间搭接施工1天,试编制流水施工方案。 [解] 根据题设条件,该工程只能组织无节奏专业流水。 1.求流水节拍的累加数列 Ⅰ:3,5,7,11 Ⅱ :1,4,9,12 Ⅲ :2,3,6,11 Ⅳ:4,6,9,12 Ⅴ:3,7,9,10 施工 过程 流水节拍(天) Ⅰ Ⅱ Ⅲ Ⅳ Ⅴ 施工段 ① 3 1 2 4 3 ② 2 3 1 2 4 ③ 2 5 3 3 2 ④ 4 3 5 3 1

  2. 2.确定流水步距 (1)K Ⅰ,Ⅱ 3,5,7,11 -) 1,4,9, 12 3,4,3,2,-12 所以 K Ⅰ,Ⅱ =max { 3 , 4 , 3 , 2 , -12} = 4 天 (2)K Ⅱ,Ⅲ 1,4,9,12 -) 2 ,3,6 , 11 1,2,6,6,-11 所以 KⅡ,Ⅲ=max { 1,2,6,6, -11} = 6 天

  3. (3)K Ⅲ,Ⅳ 2,3,6,11 -) 4,6,9, 12 2,-1,0,2,-12 所以 K Ⅲ,Ⅳ =max { 2 , -1 , 0 , 2 , -12} = 2 天 (4)K Ⅳ,Ⅴ 4,6,9,12 -) 3 ,7,9 , 10 4,3, 2, 3, -10 所以 KⅣ,Ⅴ=max { 4,3,2,3, -10} = 4 天

  4. 3.确定计划工期 又题给条件可知: Z Ⅱ,Ⅲ=2天,G Ⅳ,Ⅴ =1天,C Ⅰ,Ⅱ=1天,代入公式得: 公式: T=(4+6+2+4)+(3+4+2+1)+2+1-1=28天 4.绘制流水施工进度图 T=∑K + ∑tiV +Z Ⅱ,Ⅲ+G Ⅳ,Ⅴ-C Ⅰ,Ⅱ 施工过程 施工进度(天) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 ① ③ ② ④ Ⅰ ① ③ ④ KⅠ,Ⅱ-C Ⅰ,Ⅱ ② Ⅱ ① ③ ④ K Ⅱ,Ⅲ+Z Ⅱ,Ⅲ ② Ⅲ KⅢ,Ⅳ ① ③ ④ ② Ⅳ KⅣ,Ⅴ+GⅣ,Ⅴ ① ② ③ ④ Ⅴ ∑K +Z Ⅱ,Ⅲ+G Ⅳ,Ⅴ-C Ⅰ,Ⅱ ∑tiV T=28天

  5. [例2] 某工程由A、B、C、D等四个施工过程组成。施工时在平面上划分成四个施工段,施工顺序为:A B C D,各施工过程的流水节拍为:tA=2天,tB=4天,tC=4天,tD=2天。在劳动力相对固定的条件下,试确定流水施工方案。 [解] 本例从流水节拍特点看,可组织异节拍专业流水;但因劳动力不能增加,无法做到等步距。为了保证专业工作队连续施工,按无节奏专业流水方式组织施工。 1.确定施工段数 为使专业工作队连续施工,取施工段数等于施工过程数,即: m=n=4 2.求累加数列 A: 2,4,6,8 B: 4,8,12,16 C: 4,8,12,16 D: 2,4,6,8

  6. 3. 确定流水步距 (1)K A,B2,4, 6, 8 -) 4, 8, 12, 16 2,0,-2,-4,-16 所以 K A,B=max {2,0, -2,-4, -16} = 2 天 (2)KB,C4,8,12,16 -) 4, 8,12, 16 4,4, 4, 4, -16 所以 KB,C=max {4,4,4, 4,-16} = 4 天 (3)K C,D 4,8,12,16 -) 2,4, 6, 8 4,6,8,10,-8 所以 K C,D =max {4,6, 8,10, -8} = 10天

  7. 4.计算工期 有公式得:T= ∑K + ∑tD T=( 2 + 4 + 10 ) + 2 × 4 = 24 天 5.绘制流水施工进度图 施工进度(天) 施工过程 名 称 2 4 6 8 10 12 14 16 18 20 22 24 ① ② ③ ④ A KA,B ① ② ③ ④ B ① ③ ④ K B,C ② C ① ② ③ ④ K C,D D ∑K =16 ∑tD= 8 T=24

  8. [例3] 某项目由Ⅰ、Ⅱ、Ⅲ等三个施工过程组成,流水节拍分别为tⅠ=2天,t Ⅱ =6天,t Ⅲ =4天,试组织等步距的异节拍流水施工,并绘制流水施工进度表。 [解] 1.按公式确定流水步距Kb=最大公约数{2,6,4}=2天 2.由公式求专业工作队数 bⅠ= = = 1 个 b Ⅱ = = = 3 个 bⅢ= = = 2 个 n1=∑ bj= 1 + 3 + 2 = 6 个 3.求施工段数 为了使各专业工作队都能连续工作,取: m = n1 = 6 段 4.计算工期 T = (n1-1) · Kb +mzh·tzh T= ( 6 -1) ×2+3×4= 22 天 t1 2 t2 6 Kb 2 Kb 2 3 t3 4 Kb 2 j=1

  9. 5. 绘制流水施工进度图 施工进度(天) 施工过程 名 称 工作队 2 4 6 8 10 12 14 16 18 20 22 ① ② ③ ④ ⑤ ⑥ Ⅰ Ⅰ Kb ① Ⅱa ④ Ⅱ ② Kb ⑤ Ⅱb Kb ③ ⑥ Ⅱc Kb ① ⑤ Ⅲa ③ Ⅲ Kb ② ⑥ Ⅲb ④ (n1-1) ·Kb mzh·tzh T=22

  10. [ 例 4 ] 有六栋同型两单元组成的大板建筑,由四个工序组成,各个工序在每个单元的持续时间分别为:基础4天,构件安装8天,木结构安装4天,防水及装修4天。现组织成倍节拍流水。按流水工期公式计算划分为三个施工段时工期要多少天?画出流水施工进度表。 [解] (1)把六栋楼划分为三个施工段,即每个施工段二栋楼,共四单元。 (2)确定流水步距K,根据已知条件Kb=4天。 (3)绘制流水施工进度表。

  11. 施工队 进度(d) 工序 4 8 12 16 20 24 28 32 36 40 44 48 52 56 60 64 68 72 基础 I-1 I-3 Ⅱ-1 Ⅱ-3 Ⅲ -1 Ⅲ -3 A I-2 I-4 Ⅱ-2 Ⅱ-4 Ⅲ -2 Ⅲ -4 构件安装 Kb I-1 Ⅱ-1 Ⅲ -1 B I-3 Ⅱ-3 Ⅲ -3 Kb I-2 Ⅱ-2 Ⅲ -2 C I-4 Ⅱ-4 Ⅲ -4 木构 件 Kb I-1 I-3 Ⅱ-1 Ⅱ-3 Ⅲ -1 D Ⅲ -3 I-2 I-4 Ⅱ-2 Ⅱ-4 Ⅲ -2 Ⅲ -4 防水装修 I-1 I-3 E Kb Ⅱ-1 Ⅱ-3 Ⅲ -1 Ⅲ -3 I-2 I-4 Ⅱ-2 Ⅱ-4 Ⅲ -2 Ⅲ -4 3×16=48天 (n1-1)Kb mzh·tzh=12×4=48天 T=∑k+ ∑t=16+48=64