1 / 50

Material Management Class Note # 6 Project Scheduling & Management

Material Management Class Note # 6 Project Scheduling & Management. Prof. Yuan-Shyi Peter Chiu Feb. 2012. ◇. §. P 1: Introduction to Project Management. ■  Planning function at all levels of an organization ■ Poor project management  cost overruns

Download Presentation

Material Management Class Note # 6 Project Scheduling & Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Material Management Class Note # 6 Project Scheduling & Management Prof. Yuan-Shyi Peter Chiu Feb. 2012

  2. §. P 1: Introduction to Project Management ■  Planning function at all levels of an organization ■Poor project management  cost overruns  delay ■ eg. Launching new products Organizing research projects Building new production facilities

  3. §. P 2: Two common techniques for Project Management ■  Critical Path Method (CPM) ~ deterministic problems  ■ Project Evaluation and Review Technique ( PERT ) ~ randomness allowed in the activity times.

  4. §. P 3 : Critical Path Analysis (1).Project definition ~ clear statement (2).Activity definition ~ project broken down into a set of indivisible tasks or activities (3).Activity relationships ~ precedence constraints (4).Project scheduling ~ starting & ending times (5).Project monitoring

  5. §. P 4 : Gantt Chart Fig.9-1 p.487 ~ Gantt Chartdoes not show the precedence constraints among tasks

  6. §. P 5 : Network • ■   can show the precedence • constraints • ■is a collection of nodes and • directed arcs •  arc : activity •  node : event ( start or • completion of a project) •   ■ Two conventional expressions: • Activity-on-arrow • Activity-on-node

  7. [ Eg. 9-2 ] Activity Predecessors A - B - C A D B E C , D Fig.9-2 p.488

  8. [ Eg. 9-3x ] Activity Predecessors A - B - C A D A , B E C , D P Fig.9-4 p.489

  9. §. P 6 : Common Questions about Project   (1)The minimum time required to complete the project ? (2) Starting & ending times for each activities ?    (3)  What activities can be delayed without delaying the entire project?

  10. [ Eg. 9-3x ] From Fig.9-4 there are 3 paths 1-2-4-5 A-C-E 1-2-3-4-5 A-P-D-E 1-3-4-5 B-D-E • The Minimum time required to • complete the project = Longest path Activity Time Predecessors A 1.5 - B 1.0 - C 2.0 A D 1.5 A , B E 1.0 C , D

  11. [ Eg. 9-3x ] A-C-E 4.5 A-P-D-E 4.0 B-D-E 3.5 *Critical path!! A-C-E Critical Path Critical activities ! Other activities have slack.

  12. [ Eg. 9-4 ] Task Time(in weeks) Immediate Predecessors A 3 - B 4 A C 2 A D 6 B , C E 5 C F 3 C G 7 E H 5 E , F I 8 D , G , H

  13. Network for Example 9-4 Fig.9-5 p.491

  14. § P7 : Finding the Critical Path (1) compute the earliest times for each activity ~ forward pass (2)  compute the latest times for each activity ~ backward pass

  15. § P7 : Finding the Critical Path (3) Critical Activity: ESi = LSi orEFi = LFi ESi : Earliest Starting time EFi : Earliest Finishing time LSi : Latest Starting time LFi : Latest Finishing time EFi = ESi + ti LSi = LFi –ti ESi EFi LSi LFi

  16. § P7.1 : Forward Pass → Fig.4

  17. § P7.2 : Backward Pass ← Fig.5

  18. § P 7.3 : Critical Path The set of critical activities and in proper order e.g. A – C – E – G – I

  19. §. P 7.4: Class Problems Discussion Chapter 9 : [# 3 a,b,c,4 a,b,c; 5 a,b;6 a,b,c,d]p. 496 Preparation Time : 25 ~ 30 minutes Discussion : 10 ~ 15 minutes

  20. § P 8 : Project cost & Alternatives Schedules  ■ Expediting costs ~ activity time can be reduced at additional cost ◆ Normal time ◆Expedited time ◆ One of the CPM cost-time relationship : “ linear model ”

  21. [ Eg. 9-5 ] p.499 Activity Normal Expedited Norm. Exp- Cost/wk Time(wks) TimeCost Cost A 3 1 1000 3000 1000 B 4 3 4000 6000 2000 C 2 2 2000 2000 - D 6 4 3000 6000 1500 E 5 4 2500 3800 1300 F 3 2 1500 3000 1500 G 7 4 4500 8100 1200 H 5 4 3000 3600 600 I 8 5 8000 12,800 1600 29,500 48,300

  22. [ Eg. 9-5 ] (A) Using expedited time : Fig.6

  23. [ Eg. 9-5 ] (B) CP solution ( when using expedited time ) : Fig.7 # CP=16 weeks *A-C-E-G-I *A-C-E-H-I

  24. • Normal Cost = $ 29,500 ; 25 weeks • Expedited Cost =$ 48,300 ; 16 weeks • Extra Cost = $18,800 • If Benefit = $1,500/week × 9 ( i.e. 25-16 ) = $13,500 (Saved) Spent $18,800 to save $13,500 ? →Not economy in expediting non-critical activities ! [ Answer to Eg. 9-5 ]

  25. § P 9 : Expediting Procedures [ Eg. 9-5 ] • List CP & its Normal and • Expedited Time and Cost. • CP: A – C – E – G – I (from previous …) Project CP CP Norm. Exped. Cost Time Activities Time Time / Week 25 A-C-E-G-I A 3 1 1000 C 2 2 - E 5 4 1300 G 7 4 1200 I 8 5 1600 Refer to Fig.9-7:Gantt Chart p.513 For a better picture!

  26. [ Eg. 9-5 ] (2) Pick the least expensive task without deriving a new CP ∴ to reduce A from 3 to 1, cost $2000 ∴ Next on G from 7 to 5 , cost $2400 (3) Repeat (1) & (2) until no more reduction in time are beneficial !

  27. [ Eg. 9-5 ] Project CP CP Norm. Expe. Cost Time Activities Time Time Red. Week 21 A-C-E-G-I A 1 1 - A-C-E-H-I C 2 2 - E 5 4 1300 G 5 4 1200 H 5 4 600 I 8 5 1600 ﹝ • Looks like on H but must reduce G together (Why?) ∴ G+H =$1800 / wk > $1500 ( X ) • Next on E from 5 to 4 cost $1300 / wk

  28. [ Eg. 9-5 ] Project CP CP Norm. Expe. Cost Time Activities Time Time Red. Week 20 A-C-E-G-I A 1 1 - A-C-E-H-I C 2 2 - E 4 4 - G 5 4 $1200 H 5 4 600 I 8 5 1600 ﹝ ◆ At this point no more reduction can be made for < $1500 / wk

  29. [ Eg. 9-5 ] ∴ From Original 25 weeks reduced to 20 weeks Cost Benefit 2000 2400 +1300 5700 $1500 × 5 7500 Make Sense!!

  30. [ Eg. 9-5 ] ◆ Final Solution ( in diagram ) Fig.8 CP: A-C-E-G-I A-C-E-P2-H-I

  31. [ Eg. 9-5 ] ◆ Final Solution ( in Gantt Chart ) Slack Fig.9

  32. The CPM Cost-Time Linear Model Fig.9-10 p.498 Fig.9-11 p.499

  33. §. P 9.1: Class Problems Discussion Chapter 9 : [ # 8 a,b ; 10 ]p. 502 [ # 30 a,b,c]p. 532 Preparation Time : 25 ~ 30 minutes Discussion : 10 ~ 15 minutes

  34. § P 10 : PERT ~ Introduction ■ Generalization of CPM, allows uncertainty in the activity time. ■ Terms : a : minimum activity time m : most likely activity time b : maximum activity time

  35. § P 10.1 : Beta Distribution a = 5 days , b = 20 , m = 17 X → 5 10 15 17 20

  36. § P 10.1 : Beta Distribution • Finite interval • Mode within interval • Used to describe the distribution of • individual activity times σ= μ=

  37. § P 10.2 : Uniform Distribution is a special case of the beta distribution. f(t) a b

  38. § P 10.3 : PERT ■ In PERT, one assumes : Total project time ~ Normal Distribution By Central Limit theorem ∵ T= , : Independent random var.

  39. §P 11: PERT ~ procedures (1). Estimates a , b , m , for all activities. (2). Using these estimates to compute μ and σ2 for all activities. (3). Using μ to find CP (critical path) (4). Total project time : E(T) = Var(T) = (5). Applications of E(T) ~ Normal Distribution

  40. §P 11: PERT ~ procedures [ Eg. 9-6 ]p.510 (1) (2) Act. MIN Likely MAX (a) (m) (b) σ2 μ A 2 3 4 B 2 4 10 C 2 2 2 D 4 6 12 E 2 5 8 F 2 3 8 G 3 7 10 H 3 5 9 I 5 8 18

  41. §P 11: PERT ~ procedures [ Eg. 9-6 ] (3) → CP = A-C-E-G-I

  42. §P 11: PERT ~ procedures [ Eg. 9.6 ] (4) → E(T) = 3+2+5+6.83+9.17=26 Var(T)=0.11+0+1.0+1.36+4.69=7.16 (5) →Total project time Normal(μ=26, σ= = 2.68)

  43. §P 11: PERT ~ procedures [ Eg. 9-7 ]p.510 Solution:

  44. §P 11: PERT ~ procedures [ Eg. 9-7 ] (1) (2) 0.2266 0.0681

  45. §P 11: PERT ~ procedures [ Eg. 9-7 ] (3) (3) 0.90

  46. §P 12 : Path Independence If CP E(T) =26 non-CP E(T) =25

  47. §P 12 : Path Independence ■In reality, there is a chance that non-critical path become critical !! ■ A-C-E-G-I A-C-F-H-I ■ Assuming independence of 2 or more paths – more accurate than assuming a single critical path. ﹜ Are they independent ?

  48. §P 12 : Path Independence [ Eg. 9-8 ] p.533 ﹛ A-C-E-G-I : 41 B-D-F- H-I : 40 • Almost independent

  49. § P13 : Something to think about ! ■ Activity Time ~ Randomness ~ Independence ■ Single Path ~ consists of independent activity ~ path completion time Normally Distribution ( Central Limit Theorem) ■ Pathmay not be independent . how to assume ? ■ When to assume one CP ? ﹛

  50. §. P 13.1: Class Problems Discussion Chapter 9 :[ #18,19,20,21 ] p. 515-7 The End

More Related