An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 南丫島北角碼頭之維修工程

  2. 主要工程資料 • 工程開展時間 : 2008年10月尾至11月初 • 維修工程期 : 大概3.5月

  3. 維修工程計劃書

  4. 臨時接駁艇之安排 固定點 渡輪 固定點 通道 臨時駁艇 固定點 固定點

  5. 臨時接駁艇

  6. 石矢磚切面圖 北角碼頭 金屬鍥子 石矢磚 護石 袋裝石矢 海床

  7. 擬維修之工程 • 用袋裝石矢填補碼頭地基之空隙及用金屬楔子填補石矢磚間之間縫 • 安裝固定樁 • 修補損毀之梯台及更換損毁之護舷

  8. 安裝固定樁切面圖 固定樁 石層

  9. 原有梯台及護舷損毀情況

  10. 沿梯台安裝護舷膠

  11. 環保設施 • 施工期間安裝臨時隔泥幕環繞工作地點 • 安裝地盤圍板 • 每日清潔地盤

  12. 臨時隔泥幕

  13. 終結