1 / 22

G’Day!

G’Day!. Stefan H ö rnlund University of South Australia stefan.hornlund@unisa.edu.au. Planning ahead. Learning Objectives. After this lecture you should be able to; explain why we need to plan for the completion of a building project break down a project into a number of activities

majed
Download Presentation

G’Day!

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. G’Day! Stefan Hörnlund University of South Australia stefan.hornlund@unisa.edu.au

  2. Planning ahead

  3. Learning Objectives After this lecture you should be able to; • explain why we need to plan for the completion of a building project • break down a project into a number of activities • prepare a chart (precedence diagram) showing how these activities relate to each other, i.e. that some must be completed in a certain order whilst others can be carried out independently • list some of the many considerations that the planner must take into account

  4. Why do project planning? • To achieve a stated objective in the way best suited to the particular project. • To estimate what resources, like materials and labour, are needed and when they are needed. • To provide a method of measuring and comparing actual progress with what was planned. • To foresee problems and prepare for them.

  5. Planning versus Control Planning decisions set the objectives to be accomplished and an agreed program of the activities required to accomplish that objective. In other words - we must do A, B and C etc to achieve our objective. Control decisions check the accomplishment of the activities and the agreed procedure for further activities or even changes to the objective, if the outcome of each activity is not in accordance with the planning decisions already made.

  6. Constructability Constructability is the optimum integration of construction knowledge and experience in planning, engineering, procurement and field operations to achieve overall project objectives. (CII 1983)

  7. No Door?

  8. List of activities for a ‘Project’ A. Getting up B. Going to the bathroom C. Getting dressed D. Making breakfast E. Collecting the newspaper F. Eating breakfast G. Reading the paper H. Washing up I. Get briefcase J. Leave and lock door

  9. Precedence diagram A B C D E F G H I J

  10. Who does the planning? • Senior management • Client organization • Estimating department • Design team • Site management team • Subcontractors

  11. Construction Descriptionor Work List • Describe your activities • State any assumptions made

  12. Method statement • Method study techniques

  13. Erection of timber framed partitions in two-storey blocks of units. Framing material: Timber 35-45 x 90-120 mm. Activity content Starting point: Material in materials storage area Content: Transportation Erection of frame including bottom plate, studs, top plate and noggins. Finishing point: Frame ready for cladding Work time Accumulated work time (t) in hours/m2 for 5000 m2 wall area Average area (m2) of each panel 4 5 7 10 15 Transportation of materials 0.01 0.01 0.01 0.01 0.01 Erection of frames with studs at centres: 0.4 m 0.33 0.30 0.26 0.24 0.21 0.6 m 0.29 0.25 0.22 0.19 0.17 0.9 m 0.25 0.22 0.19 0.16 0.14 Quantity of work Correction factors for work time at different total quantity of work Quantity of work (m2) 500 1000 2000 5000 10000 Correction factor 1.27 1.18 1.10 1.00 0.93 Slower Faster

  14. Learning curve Time/unit Number of units

  15. Special considerations • Small site • Geotechnical problems • Remote location • etc

  16. Activities networks Precedence network A B C D E F G Arrow & Node network 1 2 3 5 6 7 4

  17. Barchart Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 Day Excavation Formwork Reinforcing Concreting Curing Form stripping

  18. Heartbeat diagram Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 Day Excavation Formwork Reinforcing Concreting Curing Form stripping

  19. Calendar 2007 March April 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 Activity M T W T F S S M T W T F S S M T W T F S S A H B O C L D I E D F A Y

  20. Linked Barchart (Gantt chart) A B C D E

  21. Activity Draw a bar chart based on the following information Activity Duration (days) Depends on -------------------------------------------------------------------- A 5 Can start immediately B 5 A C 12 A D 3 C E 6 B and 2/3 of C F 8 B and 2/3 of C G 14 A H 5 D, E, F and G

  22. Solution 5 10 15 20 25 30 A B C D E F G H

More Related