S.C.O.R.E.S. Web Application Project Update

S.C.O.R.E.S. Web Application Project Update. James Moore CS 491 Sponsor: Marshall University Office of Recruitment. Last Semester. Database finalized Administration Section Event, Contestant/Team, High School, Account, and Setting creation, modification, and deletion features implemented

maina
Download Presentation

S.C.O.R.E.S. Web Application Project Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. S.C.O.R.E.S. Web ApplicationProject Update James Moore CS 491 Sponsor: Marshall University Office of Recruitment

  2. Last Semester • Database finalized • Administration Section • Event, Contestant/Team, High School, Account, and Setting creation, modification, and deletion features implemented • Event and College Reports implemented • Counselor Section • Contestant and Team creation features implemented • Registration implemented • Student Schedule and Master Schedule Report implemented

  3. Last Semester Cont. • Event Supervisor Section • Scoring Events • Event Contestants ReportTraining Manuals constructed for Administrators and Counselors • Nightly database backups running

  4. Over Break • Counselor Section testing completed by S.C.O.R.E.S. staff • Comprehensive Winner Report finished • Included Pagination for pages with more than 25 records • Bug Fixes • Lots of CSS and HTML changes made

  5. Formatting Update

  6. Recent Developments • Server moved to UCS hosted site and is now accessible without VPN • Counselors are currently beta testing the application • Goal of opening outside registration by January 21 or 22

  7. Completed Deliverables • Design and Implementation of the Database • Design and Implementation of the Administrator Functionality • Design and Implementation of the Counselor Functionality • Event Reports • Contestants by College and Event • Contestant Reports • All Contestants, Number of Students Registered by School, Contestant Schedule, Counselor Master Schedule

  8. Outstanding Deliverables • Event Supervisor Section • Internally tested • Will start beta testing when counselor’s section goes live (approximately January 22) • Winner Reports • Comprehensive Winners is completed but not tested • Winners by Division and School are awaiting clarification

  9. Success Criteria • Opening of the Registration Process • Goal of January 21 • Completion of the Registration Process with little or no errors • Cutoff date March 8 • Completion of the Event Supervisor section • This includes creating the training manual for Event Supervisors • Normal Operation/Functionality on the day of the S.C.O.R.E.S. Competition

  10. Timeline • 1/21/2013 – Registration officially opens • 1/28/2013 – Event Supervisor beta testing • 3/8/2013 – Registration Cutoff • Backup of all database information • Print all registration information as backup • 4/6/2013 – Day of Competition

  11. Conclusion • Ahead of Schedule in terms of Development • Need to finish Event Supervisor section • Continue to update formatting and CSS • Issues transferring the system to UCS has put project as a whole behind schedule • Had hoped to open registration 1/2/2013 • Barring any major issues, things are back on track