1 / 12

Stephen White October 23-25, 2013 Anaheim, CA

Stephen White October 23-25, 2013 Anaheim, CA. Loads and Resources Subcommittee Report . Overview. Approval Item: Completion of the 2013 WECC Power Supply Assessment (PSA). 2013 PSA Standard Cases.

mahdis
Download Presentation

Stephen White October 23-25, 2013 Anaheim, CA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Stephen WhiteOctober 23-25, 2013Anaheim, CA Loads and Resources Subcommittee Report

  2. Overview • Approval Item: Completion of the 2013 WECC Power Supply Assessment (PSA)

  3. 2013 PSA Standard Cases • Eight cases are included in the 2013 PSA that evaluate whether there are sufficient resources (e.g., local generation, planned and potential additions, and transmission import capacity) in each subregions to meet the peak load.

  4. 2013 PSA Temperature Sensitivity Cases • Four temperature sensitivity cases are included in the 2013 PSA. • Cases 9 and 10 examine a WECC-wide 1-in-20-year extreme temperature-driven demand increase for both summer and winter. • Cases 11 and 12 reflect 1-in-20 year extreme temperature peak demand increases for the summer in the Desert Southwest and Southern California, and a peak demand increase for the winter in Canada, the northwest US, and Northern California.

  5. Adequacy Reserve Margin Values in PSA • The Building Block target reserve margins were developed under the direction of the LRS to consider four uncertainties that BAAs face: • Contingency Reserves • Regulating Reserves • Reserves for additional forced outages • Reserves for 1-in-10 weather events • Separate Building Block target reserve margin values were developed for each BA and then aggregated by subregion using a megawatt-based weighted average. • The PRM calculation indicates sufficient resources when the PRM is equal to or greater than the Building Block target reserve margin. • These calculations but do no supplant BAA resource adequacy requirements, nor supersede regional planning assessments.

  6. Planning Reserve Margin Values used in PSA Using the Building Block methodology, a Planning Reserve Margin (PRM) is calculated for each subregion

  7. PSA Results (Common Cases 1-8) – Summer(Years in which the forecast PRM drops below the calculated are indicated in yellow)

  8. PSA Results (Common Cases 1-8) – Winter(Years in which the forecast PRM drops below the calculated are indicated in yellow)

  9. PSA Results (Temperature Sensitivity Cases 9-12

  10. PSA Caveats • The analysis is based on L&R data submitted in March 2013. The demand forecasts and reported resources for each BA were “locked” as of May 2013. New generation projects announced after the data were “locked” are not included in the resource totals. • WECC does not speculate which units may retire due to environmental requirements or financial considerations. Therefore, only generating units that were reported with a planned retirement date are incorporated in these studies. • The LRS recognizes that the results of this assessment may differ from the results of similar assessments performed by other parties. • Promod is a production cost dispatch model and transfers resources from areas with surplus generation to deficit areas, considering transfer path constraints and transmission losses. Simultaneous flows, loop flows, and other transfer restrictions are approximated by the restricted transfer limits that were used in the studies.. • The Promod model allows WECC staff to capture the West-wide coincidental peak demand. The model uses static hourly demand curves for each BAA within WECC. • For hydro plants in the Northwest and California, the model employs an algorithm that shapes the available hydro energy based on the shape of the area’s energy load. This means there can be hydro capacity that is unavailable because it is constrained by the available energy in the hydro system. • Transmission constraints apply between zones. All generation within a zone is deemed deliverable within the zone. • Wind generation is based on curves created using at least five years of actual hourly wind generation data. Solar generation curves were created using up to five years actual hourly solar generation data.

  11. Recommendation • The PCC approves the 2013 Power Supply Assessment.

  12. Questions?

More Related