Time Meeting March 19, 2013. Agenda Safety Schedule Machine and system reports. Safety and training. Ed Lessard. Schedule. Continue to follow the preliminary schedule. BLIP Run continues NSRL Run13A RHIC run Physics (ramp/store development continues).

Download Presentation

Time Meeting March 19, 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Time MeetingMarch 19, 2013 Agenda • Safety • Schedule • Machine and system reports Time Meeting, Run 13

  2. Safety and training • Ed Lessard Time Meeting, Run 13

  3. Schedule Continue to follow the preliminary schedule • BLIP Run continues • NSRL Run13A • RHIC run Physics • (ramp/store development continues) • March 18: NSRL run 13A started • March 20: Scheduled Maintenance (LIPA outage 6:00-18:00) • March 27: APEX Time Meeting, Run 13

  4. Schedule * Ramp/store development concurrently with physics runs. Time Meeting, Run 13

  5. Machine and system reports • RHIC pp Run13 Vahid Ranjbar • STAR Len Eun • PHENIX Hubert van Hecke • AGS Haixin Huang • OPPIS Anatoli Zelenski • Maintenance Paul Sampson • Operations Peter Ingrassia • RCF Michaels Ernst Time Meeting, Run 13

  6. Next Time Meeting • Next Time Meeting: Tuesday, March 26 1:30PM, Snyder Time Meeting, Run 13