SSFATE MODELING

SSFATE MODELING. COMPUTATIONAL HYDRAULICS AND TRANSPORT. TOPICS. MODEL SETUP / HEM3D SEDIMENT SOURCES SEDIMENT TESTING MODEL VALIDATION. SEDIMENT SOURCES. FIELD TESTS ACCORD / TASS TGU RESUSPENSION FACTOR. RESUSPENSION RATES. CUTTERHEAD DREDGE (1-5%) CLAMSHELL DREDGE (2-8%).

mabyn
Download Presentation

SSFATE MODELING

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SSFATE MODELING COMPUTATIONAL HYDRAULICS AND TRANSPORT

  2. TOPICS • MODEL SETUP / HEM3D • SEDIMENT SOURCES • SEDIMENT TESTING • MODEL VALIDATION

  3. SEDIMENT SOURCES • FIELD TESTS • ACCORD / TASS • TGU • RESUSPENSION FACTOR

  4. RESUSPENSION RATES • CUTTERHEAD DREDGE (1-5%) • CLAMSHELL DREDGE (2-8%)

  5. SEDIMENT TESTING • RECEIVED SEVERAL SAMPLES • GRAIN SIZE ANALYSIS • SETTLING TESTS

  6. MODEL VALIDATION • DATA COLLECTED BY VIMS IN 1978 IN ELIZABETH RIVER • 7 SEPTEMBER • 19 SEPTEMBER • 26 SEPTEMBER • 28 SEPTEMBER

  7. DREDGING DATA • CUTTERHEAD DREDGE • 200 FT SWING EVERY 5 MIN • CUT – 5 FT DEEP AND 6 FT FORWARD • 100% LESS THAN 74 MICRONS

  8. MODEL PARAMETERS • 50% CLAY, 35% FINE SILT, 15% COARSE SILT • VERTICAL DISTRIBUTION OVER LOWER 2.5 M • POINT SOURCE • LINE SOURCE MOVING 1728 FT IN 24 HOURS • 3% RESUSPENSION

  9. MODEL COMPARISON WITH POINT SOURCE • SLACK 50 FT S , CONC = 140 (OBS 76) • SLACK 200 FT S , CONC = 10 (OBS 5) • FLOOD 260 FT S , CONC = 5 (OBS 27) • EBB 220 FT N , CONC = 40 (OBS 38) • EBB 320 FT S , CONC =30 (OBS 63) • EBB 440 FT N , CONC = 25 (OBS 56) • EBB 870 FT N , CONC = 10 (OBS 27)

  10. MODEL COMPARISON WITH LINE SOURCE • SLACK 200 FT CONC = 20 (OBS 20) • SLACK 50 FT CONC = 100 (OBS 76) • FLOOD 260 FT CONC = 20 (OBS 27) • EBB 220 FT CONC = 40 (OBS 38) • EBB 320 FT CONC = 20 (OBS 63) • EBB 440 FT CONC = 10 (OBS 56) • EBB 870 FT CONC = 5 (OBS 27)

  11. ACTIVITIES • SEDIMENT TESTING • VALIDATION RUNS FOR OTHER PERIODS IN SEPTEMBER 1978 • MODEL DREDGING OF THE TRENCH • MODEL EFFLUENT DISCHARGE • MODEL PLACEMENT OF ROCK