An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Long-Term Postclosure Maintenance and Corrective Action Financial Assurances for Landfills Rural Counties’ ESJPA Board December 13, 2007

  2. Our Legacy “We do not inherit the land from our ancestors; we borrow it from our children” Native American Proverb

  3. See the Future Half of California’s landfills will close by 2009 First landfill will be beyond 30 years PCM in 2021 By end of century unassured PCM costs may be $600M

  4. Tale of 3 Futures Star Trek future Mad Max future Goldie Locks future

  5. Goal: Protect Public Health and Safety & Financial Exposure into the Future Plans Cost Estimates Financial Demonstrations

  6. Goal: Protect Public Health and Safety & Financial Exposure into the Future • Closure Cost Estimate Dialogue • Closure/Postclosure Cost Estimate Regulations • Long-term Financial Assurances Study • Contractor Study • Staff Report

  7. Closure Closure Cost Estimate DialogueScope • Issue: What costs should be included for environmental control systems? • Objective: Clarify current practice based on current regulations • Stakeholder Workshops

  8. Closure Closure Cost Estimating DialogueOutcomes • Refined Business Practice • Fund-as-you-fill Approach • Triage Matrix

  9. Closure Cost Estimate DialogueOutcomes

  10. Goal: Protect Public Health and Safety & Financial Exposure into the Future • Closure Cost Estimate Dialogue • Closure/Postclosure Cost Estimate Regulations • Long-term Financial Assurances Study • Contractor Study • Staff Report

  11. AB 2296 requirements By January 1, 2008, the CIWMB shall Adopt regulations (Phase I) requiring closure and postclosure maintenance cost estimates to be based on reasonably foreseeable costs the state may incur including Labor Code (Prevailing Wage) Replacement and repair costs for longer lived items such as repair of the environmental control systems

  12. C/PC Cost Estimate Regulations (Phase I) • Clarify Third Party Costs are the State’s Costs • Prevailing Wage • Caltrans Rates • Operator May Justify Alternative Costs • Increase Financial Means Test from $10M to $15M • Updated Estimates to Reflect ”current costs on a unit basis (unit costs)”

  13. AB 2296 requirements By July 1, 2009, the CIWMB shall Adopt regulations (Phase II) and develop recommendations for needed legislation to implement the findings of the study

  14. Goal: Protect Public Health and Safety & Financial Exposure into the Future • Closure Cost Estimate Dialogue • Closure/Postclosure Cost Estimate Regulations • Long-term Financial Assurances Study • Contractor Study • Staff Report

  15. AB 2296 requirements By January 1, 2008, the CIWMB shall Conduct a study to define the conditions that potentially affect solid waste landfills identify potential long-term threats to public health and safety and the environment technologies and engineering controls designed to mitigate potential risks financial assurance mechanisms that would protect the state from long-term postclosure and corrective action costs

  16. AB 2296 requirements Consult with representatives of the League of California Cities, the County Supervisors Association of California, private and public waste services, and environmental organizations

  17. The Study Is • A Major Milestone • Powerful Tools • Together meets the study requirements of AB 2296

  18. The Study is NOT • The Final Answer • A Site-specific Risk Assessment • A Repeat of the Geosyntec Landfill Study • Define End of PCM

  19. Long-term Mechanism Evaluation Results Can Current Mechanisms Assure More Money Longer? Most mechanisms would require few if any changes Some mechanisms have built-in limits on how much can be assured Many mechanisms require periodic renewal

  20. Mechanism Evaluation Summary

  21. Pledge of Revenue • CIWMB staff strongly disagrees with Contractor’s Assessment • Contractor suggested improvements include: • Ensure “control” over pledged revenue • Add eligibility criteria as with other “self-insurance/guarantee” mechanisms • Clarify requirements of annual demonstration • Seek Legal Opinion on enforceability

  22. State Pooled Fund Working Model Model is a flexible tool for testing variety of scenarios Model designed to allow changes to inputs and assumptions, except for funding constraint (only active LFs make contributions) Addresses uncertainty and variation through probabilistic methods (e.g., Monte Carlo simulation) Uses proxy factors Excel 2003 spreadsheet model Test Case results in Final Report

  23. PCM and/or CA defaults only All PCM and/or CA costs PCM costs Y years after LF closure PCM costs changing over time Disposal rates changing over time Fund ceiling/floor $$ amount Scenarios that Can be Evaluated with the Working Fund Model

  24. Landfill Characteristics Data Used in Model • Owner type • Current operational status • Permitted capacity • Annual rainfall • Proximity to urban areas • Expected year of closure, if currently open • Estimated PCM cost/year (and CA cost estimates) • Depth to groundwater • Design level

  25. Test Case Assumptions, Absent Good Data • CA frequency and magnitude • Default rates for public sector entities’ LFs

  26. Test Case Assumption: CA Occurrence Average Number of Corrective Actions by Type and Landfill SizeOver the Modeling Period for a Single Landfill

  27. Test Case Assumption: CA Frequency Average Frequency of Corrective Actions by Type andLandfill Size Over the Modeling Period for a Single Landfill

  28. Key Inputs: Test Case Default Rates 1%/year for single-owner LFs, both private and public .15% year for private LFs not singly owned .17%/year for public LFs not singly owned LFs with high-cost CAs have double the probability of default 1%/year for event-driven group defaults 1% of defaults are “permanent”

  29. Landfill Screening Tool Purpose Develop factors and method that are simple to use for quickly judging the potential relative CA/PCM concern at California landfills Potential uses of tool characterize LF universe setting priorities informing FA requirements pooled fund contributions

  30. Criteria Governing Factors and Methodology Not a site-specific risk assessment Use a limited number of indicator factors Three categories: high, medium, and low Factors must have a quantitative basis and relate to potential occurrence, duration, and costs of CA and/or PCM Evaluate the method considering importance/weighting of factors and effect on ranking scores; data from individual landfills were not used in the analysis

  31. Final List of Proxy Factors 13 factors considered Siting/climate factors: rainfall intensity Landfill design, construction, and maintenance: engineering controls (e.g., cap and liner design) permitted capacity Potential for migration/distance to sensitive receptors: hydrogeology proximity to urban areas

  32. Pooled Insurance Insurer Concerns: 1-3 year policies possible, not 10 years underwriting costs substantial (> $11 million) moral hazard and credit risk concerns “all risk” problematic immediate full payment problematic right to void coverage desired limits of $100M too high, even with $10M deductible

  33. Goal: Protect Public Health and Safety & Financial Exposure into the Future Closure Cost Estimate Dialogue Closure/Postclosure Cost Estimate Regulations Long-term Financial Assurances Study Contractor Study Staff Report

  34. Staff Report Approach Broader than Requirements of AB 2296 Encompasses Scope of ICF’s Study Request for Direction Application of New Requirements to Closed Landfills Implement Now Continue to Develop Pursue No Further Closure Postclosure Corrective Action Financial Demon-strations

  35. Staff RecommendationsImplement Now Closure Fund-As-You-Fill

  36. Post-30 year FA Demonstration Options Plus 11 Years to PCM Cost Estimates • Provides assurance that funds will continue to be available for routine PCM • May not require contingency or Pooled Fund

  37. Post-30 year FA Demonstration Options Maintain 30-Year PCM • Holding at 30-year value until the waste no longer poses a threat • Will greatly extend time funds are available for PCM, but not indefinitely if default

  38. Post-30 year FA Demonstration Options Rolling PCM • Allowing reductions initially will lessen impact to operator and extend time funds are available for routine PCM, but not indefinitely • Better in tandem with Pooled Fund

  39. Key Issues:Application of New Requirements to Closed Landfills Potential Grandfathering of Closed Landfills In - benefits of some proposals Pooled Fund Out – newly created financial requirements Post-30 FA demonstrations Non-Water Quality Related Reasonably Foreseeable Corrective Action

  40. Long-Term PCM and CA Staff Requests for Direction Summary Implement Now Closure Fund-As-You-Fill Permit Option Water Quality Related Reasonably Foreseeable Corrective Action Financial Assurances Closure Postclosure Corrective Action Financial Demon-strations

  41. Long-Term PCM and CA Staff Requests for Direction Summary Continue to Develop – Phase II regs Issues deferred from Phase I PCM cost estimate contingency Submittal of as-built costs Insurance Amendments Improvements to Pledge of Revenue Post-30 year FA demonstrations Non-water quality related CA Closure Fund-As-You-Fill through FA demonstrations

  42. Long-Term PCM and CA Staff Requests for Direction Summary Continue to Develop – May require additional statutory authority Pooled Fund Working Model Use of Risk Scoring Model

  43. Long-Term PCM and CA Staff Requests for Direction Summary Pursue No Further Annuities and GICs for Long-Term FA Demonstrations Umbrella Insurance PCM Period to Mirror Subtitle D

  44. Next Steps February 2008 – Pooled Fund Model Scenarios Workshop March 2008 – Informal Workshop for Phase II Rulemaking May/June 2008 – Request for Direction for Phase II Rulemaking (adopt by July 1, 2009) May/June 2008 – July 1, 2009 – Recommendations for Additional Statutory Authority Closure Postclosure Corrective Action Financial Demon-strations