Project Management – Part 2

Project Management – Part 2. Yale Braunstein School of Information Management & Systems UC Berkeley. More on previous topics. The “weekend problem” We changed the working schedule, but this may cause problems if schedule changes (Alt-T-H)

lovie
Download Presentation

Project Management – Part 2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management – Part 2 Yale Braunstein School of Information Management & SystemsUC Berkeley

  2. More on previous topics • The “weekend problem” • We changed the working schedule, but this may cause problems if schedule changes(Alt-T-H) • Alternate approach: assign “dummy resource” and change its schedule (Select resource on Resource Sheet, then either Alt-T-H or right click) • Splitting tasks • Finding and “using” slack (tasks off the critical path) • Free slack – delays don’t delay ANY other task • Total slack – delays don’t delay project finish date

  3. Track progress with MS Project • When tasks & timeline are set, save baseline • Several alternatives for tracking progress • Enter % completed • Enter time to complete • Enter date completed (more than one is allowed) • Review for changes in critical path • It is now possible to modify the baseline in Project 2000 • But think about why you want to do this! • Work-around for Project 98

  4. Useful source of additional information

  5. Wide variety of tables, charts, views, reports,… • Use Help to sort through the many options • Use the topic “What view to print?” to see what gets printed in each view • “Determine the report to print” gives information on the many reports that are available. • See handouts • Use page format options

  6. Project Summaries Alt-P-P-Statistics gives more than Alt-F-Properties-Contents