An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PROPOSEDPOLICE STATION/EOCOVERVIEW Special City Council Meeting March 26, 2013

  2. Opening Remarks • Vision • Need • Size • Location • Cost • Local Economic Impact

  3. Vision Historical perspective over a decade 1999-2013

  4. 1999-2010 • Since 1999 the current site was a temporary measure • Considerable discussion and analysis • 2001 Minute Excerpts forward on this project • Dialogue on location- on or off of US 17 and even @ ASACC Site on MLK Boulevard • In 2010 Design Plans were provided to Council and approved

  5. 1999-2010 • In 2010, $230 s.f.; $5 M Construction costs; 16,000 s.f. heated/cooled • Build for future- 30 years • Population Projection: 30,000; Surge 12-13,000 • Meet our Vision Plan • Prequalify contractors

  6. 1999-2010 • National avg230 s.f./employee • Plan was for 213 s.f./employee • Service Standard 2.2 officers/thousand population • Anticipate 66 sworn and 15 civilian

  7. 2011 - 2013 • April 19, 2011 – Project overview 14 page agenda item, photos, size, cost, location • May 17, 2011 – Funding Strategy Plan • February, 2012 - Vision Plan Update • May 15, 2012 - Comprehensive update on this Capital Project: Sources and Uses, Site Readiness to Proceed, Action Steps, and Council direction • July 3, 2012 – Adopt Rezoning Ordinance • July 17, 2012 - Funding Strategy Update (2nd time)

  8. 2011-2013 • July 26, 2012 - Planning & Zoning Board approved the Site Plan. In their packet it showed the building footprint, square footage, and building façade • August 7, 2012 - Adopt Ordinance to re-open Wilson Avenue due to land rights • August 7, 2012 - Council approved the Site Plan • October 2, 2012 - Council approved addtl architectural fees due to building footprint shift from closure of Wilson Avenue

  9. 2011-2013 • November 7, 2012 - Council adopts plan for adaptive reuse of former police station site • December 4, 2012 - Council approves Request for Qualifications (RFQ) process with a tentative timeline subject to change • December 4, 2012 - Funding Strategy Update (3rd time)

  10. March, 2013 • March 5, 2013 - Mayor asks for City Manager to give brief update under Comments section of agenda • March 26, 2013 - Special Council Meeting

  11. Need 20-Minute Video current facility 205 Spring St Current Organization Future Facility Components

  12. Need • The Honorable Rick Beseler, Sheriff , Clay County

  13. Future Facility Components • Lobby • Storage • Mechanical Rooms • Offices • Conference Rooms • Restrooms • Evidence • Vaults

  14. Future Facility Components • Lockers • Physical Fitness Training Area • Armory • Briefing Room • Training Room • Interview Room • Prisoner Booking Room

  15. Future Facility Components • Communications • Break Room • Sallyport

  16. Sworn Strength

  17. All Calls for Service

  18. Size 20,000 Square Foot Emergency Operations Center (EOC) Population Projections Design Elements

  19. Emergency Operations Center (EOC) • Video EOC • Chief Lorin Mock, Director, Clay County Emergency Management • John Ward, Asst Director, Clay County Emergency Management

  20. Critical Facility • Serve dual purpose as Community Meeting Room • Serve dual purpose as Emergency Operations Center • Provide Veteran’s Memorial @ Entrance • Share Local History • Build Capital Wealth • Attract Business and Industry

  21. Population Projections • Exclude impact from Outer Beltway • Exclude impact from Reynolds Industrial Park Build-out • Potential Impact from Reynolds per Comprehensive Plan is 3,919 dwelling units 10,133 population and 8 M S. F. Development, 1,500 Time Share Units, 1,650 Boat Slips • Exclude Annexations

  22. Clay County, Florida 191,143 Population Projections Low Medium High Source: UF Bureau of Economic Business Research (BEBR)

  23. Population Projections Clay County, Florida Source: Northeast Florida Regional Planning Council

  24. Population Projections Clay County Green Cove Springs Source: UF Shimberg Center

  25. Population Projections Source: City of Green Cove Springs Comprehensive Plan for 2025 Data & Analysis

  26. Location Land Purchase Discussion

  27. Idlewild Avenue Site Expenses • Final Land parcel purchase was in 2008 • Architect • $1.4 Million inception to date

  28. Site Characteristics • 3.1 acres • Frontage on SR 16 (1001 Idlewild Avenue) • Abuts Wilson Avenue • Adjacent to Melrose Avenue • On-site Stormwater • Off-street Parking

  29. Cost CoMPARE & CONtrast Per Square Foot

  30. Funding Strategy: Sources $2.244M = 43% Source: December 4, 2012 Staff Report

  31. Funding Strategy: Uses $4.5 M $5.1M Source: December 4, 2012 Staff Report

  32. Bid Tabulations Source: March 25, 2013 Bid Tabulation

  33. Funding Strategy: Uses Source: December 4, 2012 Staff Report and March 25, 2013 Bid Tabulation

  34. Funding Strategy: Sources $181 s.f. 20,000 s.f. $1.844M = 51% Source: December 4, 2012 Staff Report and March 25, 2013 Bid Tabulation

  35. Financing Options (Surtax Only) • Extend Surtax beyond December 31, 2019 • Surtax is a local option sales tax of an additional penny  $630K/year • Pledge in various combinations • Allocate a portion of surtax, nte $255K for 7 years, =$1,785 M • Allocate 100% of Surtax for 2 years = $1,260 • Impact other CIP uses in areas of parks and recreation, streets, facilities

  36. Financing Options (Surtax Only) • Fixed vs. Variable Interest Rates • Ability to Refinance • Construction Drawdown Basis • Interest only during Construction • Flexible Repayment Periods • Duration of Loan: 6 and 20 years • Negotiate Prepayment

  37. Cost Comparisons • City Hall c. 2004 • 26,709 s. f. • Built to Category 2, 110 mph standard ≠ EOC Capability • Limited Generator Power first floor only; $200K • 1.4 acres • No parking requirements • $4,037 Million • $151.15 s.f.

  38. Cost Contrasts • Proposed Police Facility c. 2013 • 16,000 s.f. under air, total 20,000 s.f. • 1,940 s.f. for EOC portion @ $400,000 w match = $533,500 is $275 s.f. • Built to Category 5, 160 mph standard =EOC Capability • Self-Sufficient for 72 hours: (Electric, Water, Fuel, etc.)

  39. Cost Contrasts • 3.1 acres • Parking requirements • $4.5 Million • $5.6 Million lowest bidder

  40. Construction Bid Costs and Time • $5.597 M - $5.897 M • $279.85 s.f. - $294.85 s.f • 300 days – 442 days

  41. Re-Design Options • Investment in Future • Do not delete perceived arbitrary elements • Lessen Impact New Construction Documents: Architect, and civil, mechanical, electrical, plumbing, landscape architect • Recommend use of planned site • Maintain architectural style for communications, no cell tower on site

  42. Cost Factors • Interest rates are at low point • Construction costs are on rise • Construction Type • Square Footage

  43. Local Economic Impact Workforce $5 M Construction Project

  44. Jobs, Wages • Direct effect: 38 jobs, $1.3 M wages, $1.783 Value added to goods at each stage of process • Indirect effect: 26 jobs, $858,853 wages • Effects are during construction period which is close to one year as a result of this economic stimulus Source: State Department of Economic Opportunity

  45. Decision-Making Process Approve/Reject Bids Loan Ordinance

  46. Conclusion Vision Proposed Plan Testimonials Bids Sources and Uses