Deepwater Horizon . Oyster Advisory Committee May 23, 2012. Natural Resource Damage Assessment -- Early Restoration. LA Oyster Cultch Project. $14.9 Million Part 1: Cultch Placements on Public Seed Grounds 850 acres 6 locations Locations being sampled

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Oyster Advisory Committee May 23, 2012' - liluye


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Deepwater Horizon

Oyster Advisory Committee

May 23, 2012

la oyster cultch project
LA Oyster Cultch Project
  • $14.9 Million
  • Part 1: Cultch Placements on Public Seed Grounds
    • 850 acres
    • 6 locations
    • Locations being sampled
  • Part 2: Construction of an Oyster Hatchery Facility
    • Grand Isle, La.
    • Produce 1 billion eyed larvae per season
la oyster cultch project1
LA Oyster Cultch Project
  • Hackberry Bay
    • $1.4 million
    • 200-acre site
    • Limestone
    • Completed May 21
  • Sister Lake
    • $1.93 million
    • 300-acre site
    • Limestone
    • Scheduled for completion May 29
emergency restoration cultch plants
Emergency Restoration Cultch Plants
  • Mississippi Sound
    • 300-acre site
    • Scattered shell bottoms
    • St. Bernard Parish
  • California Bay
    • 300-acre site
    • Crushed concrete, limestone, oyster shell
    • Plaquemines Parish
derp ea phase i overview
DERP/EA Phase I Overview
  • December 14, 2011 - draft plan released for 60-day public comment ending February 14, 2012.
  • $57 Million for 8 Projects including:
    • Oyster cultch and hatchery projects
    • Marsh creation
    • Dune restoration
    • Boat ramps
  • Includes 2 Louisiana projects totaling more than $28 million.
slide13

Finalizing the ERP/EA Phase I

  • Comments received are currently under consideration and responses are being finalized
  • Finalize approved projects with BP based on public comments
  • If project is selected, project implementation begins
  • Future rounds of Early Restoration projects