LBT Q3 2007 Engineering Review

LBT Q3 2007 Engineering Review. ROT Rotators. Highlights (Q3/2007). BG mechanics being manufactured Electronics design complete, boards fabbed BG integration equipment being made BG gear test fit on bearing (for AGW test). Open Issues. Technical Many details still incomplete

lev
Download Presentation

LBT Q3 2007 Engineering Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBT Q3 2007 Engineering Review ROT Rotators

  2. Highlights (Q3/2007) • BG mechanics being manufactured • Electronics design complete, boards fabbed • BG integration equipment being made • BG gear test fit on bearing (for AGW test) LBT Q3 2007 Engineering Review

  3. Open Issues • Technical • Many details still incomplete • Undocumented telescope changes • Cable chain is high risk, may be impossible • Schedule • Integration and installation delayed • No visibility on software schedule LBT Q3 2007 Engineering Review

  4. Open Issues (cont.) • Financial • Most items costing more than budgeted • Scope creep also driving up costs • Resource • Competition with other projects • Availability of telescope • Integration/install will require mtn support LBT Q3 2007 Engineering Review

  5. Progress (Q3/2007) • More design details complete • Major BG component manufacture started • Electronics design/layout nearly complete • BG integration stand manufacture started • BG lab integration to start soon • Integration and test plan in process LBT Q3 2007 Engineering Review

  6. Progress (Q3/2007) (cont.) • App board fabbed, being stuffed • SACB board done, in-house • RIM enclosure ready for fab • Reef IM VHDL code done and tested with SW, ready for test on HW • Servo code ready for test LBT Q3 2007 Engineering Review

  7. Planning (Q4/2007) • Complete design and manufacture • Complete telescope work (cable trays) • Complete and build work platform • Test electronics and software on simulator • Begin integrating BG rotators in Tucson • Build cable chain prototype LBT Q3 2007 Engineering Review