1 / 15

Matteo solfaroli and Mirko Pojer

Matteo solfaroli and Mirko Pojer. Hardware commissioning during winter technical stop. Acknowledgements: R. Schmidt, M. Zerlauth, H. Thiesen, N. Catalan, K. Foraz, R. Giachino. Cryo -intervention planning. Powering test planning. 2 shifts 5/7 days for access. Chamonix: No shifts

leonardn
Download Presentation

Matteo solfaroli and Mirko Pojer

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Matteo solfaroliand Mirko Pojer Hardware commissioning during winter technical stop Acknowledgements: R. Schmidt, M. Zerlauth, H. Thiesen, N. Catalan, K. Foraz, R. Giachino

  2. Cryo-intervention planning

  3. Powering test planning 2 shifts 5/7 days for access Chamonix: No shifts (Access covered by TI?) 3 shifts 7/7 days DSO tests

  4. General layout • PC condemnation • ElQA monitoring of multi-kA circuits and spool pieces • RRR measurements during warm-up/cool-down • ElQA after re-cooldown • PC de-condemnation • QPS-IST with selective quench heater firing (only where disconnected) • Powering tests (special tests on RB.A56 to validate simulations) • Heat runs and GPM test • Cycling, cycling, cycling….

  5. Key-drivers for ElQA • It was decided to perform the electrical integrity validation only on high current circuits, despite the thermal excursions • The MSs and ITs will certainly go (far) above 80 K → full ElQA • MIC will be done on MSs and ITs • The ElQA team and equipment: • Equipment for testing up to 4 sectors in parallel • 5 teams available inside the ElQA team (2 teams per sector + 1 (per MIC) needed) –> up to 2 sectors in parallel

  6. Powering test streamlining • Main focus on protection interlocks (QPS/EE, PIC, PC) --> Almost all tests to verify the correct operation of interlock loops will be performed • Reduced number of other tests, according to expert requirements • Heat run for all circuits will be performed (8hours) as last step

  7. Powering procedures (MP3) • Optimization • Modularity to be applied to all kind of situations (full commissioning, technical stop, components replacement,…) • Example: Courtesy of N. Catalan

  8. Circuit specificities and NCs • List of non-conformities and powering singularities • RQTD and RQTF validation time extended to 190ms, can it remain for 4TeV? • RQS validation time extended to 190ms, can it remain for 4 TeV? • Higher order correctors in triplet? for higher E, lower beta? • RU • RCBX, limited to 350A due to difficulties to make the interlock on the square sum operating, issue with dI/dt • RPMBA.UA83.RQT13.L8B1 • RPMBA.UA27.RQTL11.R2B1 • RQS.A45B1 and RQS.A45B2 have a high value • Large part of 600A circuits were commissioned to the value required for 5 TeV • A few circuits have some issues, and were operated at lower current • The IPQ and IPD circuits were limited to 3.5TeV because of the missing splice resistance measurements • RB.A81 dI/dt needs to be set correctly • RQ6 – RQ10.R6 parameters HW limit set differently • RCBYHS5.R8B1 has an issue and is limited to 20A • RQX.R1: QHPS voltage reduction and capacitance increase Re-visiting and taking a critical look (new current limits for 4/5 TeV operation)

  9. Resources • 2-3 weeks with 24/7: can the experts operate like that? • EPC will provide full support • PIC will be on best effort (most is automated) • QPS will mainly be on extended working hours • MP3 on full time (to be confirmed) • OP is already organizing the shifts

  10. What LMC has recently endorsed • Installation of the snubber-capacitors on DQS for the dipole circuits • Discussion ongoing about their connection (to be tested for one sector, to be decided for the others) • Experts says they are needed for 4 TeV operation • Not needed for the RQD/F Energy change and snubbers → extraction time to be increased to 68s (12.5 s for the RQs) • Upgrade of all IPQ’s and IPD’s for 10V input and 500 Hz PM acquisition frequency • Decommissioning of the existing main bus-bar protection systems and respective reconfiguration of the main circuit protection. • Various software upgrades for the DQGPU’s • RRR measurements Courtesy of K. Foraz

  11. Safety-related aspects

  12. AUG and transformers replacement AUG tests Point 1 :Sunday 19th December – No access from point 1 to mid-arcs Point 18: Wednesday 5th January – No access in PM18, UJ18 Point 2: Thursday 20th January  – No access from point 2 to mid-arcs Point 3: Wednesday 8th December – No access from point 3 to mid-arcs Point 4: Thursday 6th January – No access from point 3 to mid-arcs Point 5: Tuesday 4th January – No access from point 5 to mid-arcs Point 6: Monday 10th January – No access from point 6 to mid-arcs Point 7: Tuesday 11th January – No access from point 7 to mid-arcs Point 8: Monday 20th December – No access from point 8 to mid-arcs Stop of ventilation in the arcs (transformer exchange) Arc 34 and arc 45: From Monday 17th January to Friday 21st January Arc 56 and arc 67: From Tuesday 11th January to Friday 15st January

  13. Work Acceptance Tool Virtually, no more need for access operators Courtesy of K. Foraz

  14. Beyond HwC BIS RF LBDS MKI/injection/TLs Collimators BI instrumentation Controls DSO tests Machine check-out

  15. Concluding remarks • Tough planning (profitezbien des vacances!) • HC team is working on all test-related aspects: • Powering test streamlining • Powering procedures (MP3) • NCs • Implications of energy increase • Almost regular meetings with experts • Safety aspects are being considered • WAT will keep people away from the access consoles  • Tracking of performed activity in the tunnel is the key for a fast restart • Machine check-out can start after the DSO tests

More Related