An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Status on PRR recommendationsand actions Guillaume Prévôt APC, Paris • - Recommendations status • - PRR Review report: actions • - Conclusion

  2. Recommendations • 3 recommendations: • - Project organization • - First flight as soon as possible • - Schedule control • Project organization • “ Defining the CNES organization, introducing an electrical architect, identifying all the activities relative to the harness, clarify the participations to the AIT, the instrument GSE responsibilities.” • Action 1.1: The team has provided the updated organization. • Action 1.2: The team has provided the updated development plan to CNES. Status on PRR actions

  3. Recommendations • First flight as soon as possible • “In consequence, the review panel supports the Euso-Balloon Project in its demand to obtain the first flight as soon as possible considering the project schedule and the opportunities of the CNES Balloon campaigns. A first launch before mid 2014 is recommended.” • Schedule control • “In consequence, the review panel supports the Euso-Balloon Project in its demand to obtain the first flight as soon as possible considering the project schedule and the opportunities of the CNES Balloon campaigns. A first launch before mid 2014 is recommended.” • Action 3.1.1: The 3 laboratories have done a proposition for a new project manager and it has been accepted by CNES. • Action 3.4.1: The team has provided the updated instrument planning to CNES. Status on PRR actions

  4. PRR Review report: actions • 41 actions have been taken with answers from the project team expected for the design review. • Updates of: • The TechnicalSpecifications document (EUSO-TS-INST-206-LAL_V2.0) • The Instrument Definition document (EUSO-DF-INST-204-LAL_V2.0) • The Organization Note (EUSO-ON-INST-201-LAL_V2_6) • The Compliance Matrix (EUSO-PA-INST-203-LAL_V2.0) • The RiskAnalysis document (EUSO-RI-INST-404-IRAP V1.1) • The Development Plan (EUSO-DP-INST-207-LAL_V2.0) • Writingof: • A Thermal Analysis document (EUSO-TA-INST-409-IRAP V1.0) • A Mission Analysis document (CNES) • ICD documentation (EUSO-IC-INST-407-IRAP_V1.0 (electronics) and EUSO-MI-INST-408-IRAP_V1.0 (mechanics)) • A AIT Plan document (EUSO-AI-INST-251-LAL_V1.0) • A calibration Note (EUSO-CN-INST-003-APC_V1.0) Status on PRR actions

  5. PRR Review report: actions • 39 actions have been closed by the team. • 2 actions are open (about cleanliness strain). • FB-14 and OLM-14 are open and they will be dealt with on a specific note delivered at the AIT Key Point. Status on PRR actions