An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Wenatchee Community Dock • Increase public access opportunities • Implement Riverfront Plan • Enjoy the Columbia

  2. Partnership • City of Wenatchee • Chelan County PUD • Wenatchee Row and Paddle Club • Community

  3. Riverfront Plan • Vibrant community • Water-based activities • Maintain character of riverfront

  4. Existing Facility • Built in late 1980s • High maintenance costs • Grounded most of the time • Limiting

  5. Project Budget • 1999 cost estimate $90,000 maximum • Fisheries requirements added substantial cost • 2004 cost “achievable”

  6. Project Budget Item units unit cost cost Piling 250 lf $125 $31,250 Excavation 35 cyd $75 $2,625 Concrete 5 cyd $400 $2,000 CSTC 22 cyd $100 $2,200 Asphalt 14 ton $150 $2,100 trail repair 20 ton $150 $3,000 Turf restore 1000 sq ft lump $2,500 ped control lump $750 sprinkler rep lump $500 mob docks lump $5,000 dock install lump $7,700 clean-up lump $1,000 Subtotal$60,625 Floats $53,000 Permitting lump $1,500 Construt admin 25 days $2,000* Subtotal$56,500 Contingency 30% $35,137 Total cost estimate$152,262

  7. IAC Water Access Grant $47,500 Wenatchee Row and Paddle Club $60,000 Erlandsen & Associates PUD Staff Assistance Project Contributions

  8. Current Status • Permitting package submitted August 2004 • Final design • Work window closes February 28 (in-water)

  9. Continue staff support Final approval of project Approval of up to $30,000 to complete project PUD Request