This report by Jocelyn Tan provides insights into equipment dismantling, installation, risks, and mitigation strategies for the Linac4 and LIU-PSB. It includes a summary of equipment status and readiness assessment for December 2016. Risk assessment, minimum hardware commissioning time, and system validation details are highlighted. The technology used is reliable, ensuring a low-risk connection.
E N D
Linac4-PSB 160 MeV connection readiness review Tuesday 30 August 2016
BE-BI Jocelyn Tan • Table of Contents: • Equipment dismantling • Equipment installation • Risks / Mitigation • Summary Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI
Equipment dismantling Dose rates source: https://espace.cern.ch/rpps/public-portal/Shared%20Documents/Linac2/2016-04-13_Linac2.pdf https://espace.cern.ch/rpps/public-portal/Shared%20Documents/PS_Booster/2016-06-07_Booster.pdf Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI
Equipment installation: Linac4 TLs Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI
Equipment installation: BI line (1) Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI
Equipment installation: BI line (2) Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI
Equipment installation: PSB Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI
Risks / Mitigation Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI
Summary • A list of 24 BI activities to be carried out with: • EN-EL, TE-VSC: heavily involved in over 20 activities • EN-HE, TE-ABT, HSE-RP, BE-OP. • Readiness for December 2016: • Linac4 instruments: Ready • BI line and new injection region: Ready • PSB orbit and intensity: Ready • The tune PUs shall be ready for Q1 2017. • Risk assessment • Minimum HW commissioning time requested • Some new systems need validation with beam: H0/H- current meas. with HST, BTMS • Technology used is well known and robust • Risk is low • No showstopper for Linac4-PSB 160MeV connection Equipment status (Linac4 and LIU-PSB) Jocelyn Tan - BE/BI