Avera Therapy Addition December 2011 Update. Walls Framed. All of the interior walls are framed on the addition and drywall installation will be about 1/3 complete by the new year. Mechanical/Electrical Wall Rough in Ongoing. Electrical and plumbing rough-in for the walls is complete
E N D
Walls Framed • All of the interior walls are framed on the addition and drywall installation will be about 1/3 complete by the new year
Mechanical/Electrical Wall Rough in Ongoing • Electrical and plumbing rough-in for the walls is complete • Fire Sprinkler rough-in will be started by the first of the year • Mechanical above ceiling will be complete except for drops and diffusers by the new year
Masonry Façade Complete • Exterior masonry will be complete for the new year • South elevation of addition is architecturally appealing with a mixture of brick, stone and precast
A Great Job by BWBR Architects, Avera St. Lukes, Huff Construction and the rest of the design and construction team!