1 / 20

NAIOP

NAIOP . Building Permitting Process for the City Albuquerque. . Electronic Plan Review. The Website http://www.cabq.gov/planning/our-department/building-safety. Application . Sign In. Upload Drawings and Documents. Uploaded Drawings. Markup . Review Markups. Status of Plan Review .

kyros
Download Presentation

NAIOP

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NAIOP Building Permitting Process for the City Albuquerque.

  2. Electronic Plan Review

  3. The Website http://www.cabq.gov/planning/our-department/building-safety

  4. Application

  5. Sign In

  6. Upload Drawings and Documents

  7. Uploaded Drawings

  8. Markup

  9. Review Markups

  10. Status of Plan Review

  11. Who is Reviewing the Drawings? • Zoning • Environmental Health • Consumer Health Protection Division - CHPD • Environmental Services Division-ESD • Solid Waste • Transportation Hydrology • Fire Marshall • Building • Plumbing • Mechanical • Electrical • Boiler (If applicable) • Elevator (If applicable)

  12. Review Time • Average to notification: • FastTrax Commercial: 5 Days • FastTrax Residential: 2 Days • Traditional Commercial: 17 • Traditional Residential: 11 • ePlan: 6 ½ Days

  13. Fees • Supply the square footage and building type • Estimate the value • Materials and labor only ------------- • The City will calculate the fees by: • 2003 ICC Building Valuation Data to calculate the value • For commercial projects; a .9 regional modifier will be applied • UAC Table 112-A to calculate the fees based on the value • Commercial modifier .67 • Residential .5 • Add Zoning and Hydrology fees ----------- • At Permit issuance • Add Impact fees

  14. Fee calculation example • New 2000 square foot restaurant • Estimated cost of materials and labor $100,000.00

  15. Fee calculation example • 2005 ICC BVD = 100.25 * .9 = 90.225 (81% of 2012 BVD) • 90.225 * 2000 SqFt = $180,450 • Compared to Las Vegas, Phoenix, SLC, C-Springs: • Albuquerque Residential 23% lower, Commercial 60%.

  16. Fee calculation example • Permit fee • Calculation: $993.75 + $5.60 * 81 = $1447.35 • Modifier: $1447.35 * .67 = $969.72 • Plan Review • Permit fee $969.72 * .65 = $630.32 • Flood Plain Ordinance $50 Zoning = $25 • Total fees $1,675.04, excluding impact

  17. Things to Avoid

  18. Incomplete submittal • Energy Code Checklist • IBC • Professional Stamps for Commercial Drawings • Design Criteria / Code Data • Site Plan • Floor Plan • Foundation Plan • Roof and Floor Framing Plan • Mechanical, Electrical and Plumbing • Zoning • Fire • Solid Waste • Environmental Health • Traffic and Hydrology

  19. Authorization • Revise drawings • Pick up permit sets • Residential: Owner or designee • Commercial: Contractor or designee