Paul Roberts Senior Thesis 2010 Construction Management

Paul Roberts Senior Thesis 2010 Construction Management. Presentation Agenda. Project Overview. Introduction of Analyses. Analysis 1: Schedule Deceleration. Analysis 2: Lighting Redesign. Analysis 3: Water Management. Conclusions. Questions?. Paul Roberts Construction Management.

kuss
Download Presentation

Paul Roberts Senior Thesis 2010 Construction Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Paul Roberts Senior Thesis 2010 Construction Management

  2. Presentation Agenda Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  3. Paul Roberts Construction Management Project Overview Presentation Agenda Project Overview Location: Middleburg, Virginia. 340 acres Size: 230,000 square feet Future Use: Hotel, spa, equestrian center Dates of Construction: Spring 2007 – Spring 2012 Building Cost: $93 million Project Delivery Method: Design Bid Build with GMP Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  4. Paul Roberts Construction Management Project Overview Presentation Agenda Project Overview Project Team Owner - Salamander Hospitality Architect - Architecture Inc. Design Architect - Wimberly Allison Tong and Goo Interior Designer - Forrest Perkins Structural Engineer - Rathgeber/Goss Associates MEP Engineer - RG Vangerweil Engineers Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  5. Paul Roberts Construction Management Project Overview Presentation Agenda Project Overview • Design • 168 guest rooms • Spa, restaurant, and ballrooms • Stone and stucco façade • Extensive landscaping • LEED Features • EcoSlate roofing • Low emitting paints, carpets, and window treatments • Conserve 250 of the 340 acres Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign • Electrical System • From utility, main 3200A 480/277V – 3 phase 4W switchboard • Uninterrupted Power Supply (UPS) for main building • Indoor emergency diesel generator (650kW 480/277 – 3 phase 4W) Analysis 3: Water Management • Structural System • Concrete and structural steel • Composite metal decking • Post-tensioned concrete beams Conclusions Questions?

  6. Paul Roberts Construction Management Project Overview Presentation Agenda Project Overview Introduction of Analyses 1: Schedule Deceleration 2: Guest Room Lighting Redesign 3: Water Management Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  7. Paul Roberts Construction Management Introduction Presentation Agenda Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  8. Paul Roberts Construction Management Schedule Deceleration Presentation Agenda Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Lodge Analysis 2: Lighting Redesign Spa Main Building Analysis 3: Water Management Conclusions Questions? Original Schedule Completion Date: Spring 2011

  9. Paul Roberts Construction Management Schedule Deceleration Presentation Agenda Project Overview Revised Schedule Completion Date: Spring 2012 Introduction of Analyses • Problems with Deceleration • Renegotiate subcontractors contracts • Lost revenue • Additional general conditions • Public image Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  10. Paul Roberts Construction Management Schedule Deceleration Presentation Agenda Project Overview • Possible Alternatives • Complete project on schedule • Stop construction of project for 12 months Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  11. Paul Roberts Construction Management Schedule Deceleration Presentation Agenda Project Overview • - Allocation of activities • - 10-month break • December 21, 2009 to October 18, 2010 Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  12. Paul Roberts Construction Management Schedule Deceleration Presentation Agenda Project Overview • General Conditions • Field personnel • General Expenses • Temporary Security • Temporary Utilities • 10% power • 20% lighting • 10% heating Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  13. Paul Roberts Construction Management Schedule Deceleration Presentation Agenda Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  14. Paul Roberts Construction Management Introduction Presentation Agenda Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Guest Room Lighting Redesign Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  15. Paul Roberts Construction Management Lighting Redesign Presentation Agenda Project Overview 168 guest rooms - 151 King/Queen rooms - 17 Suites Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign • Current System • Halogen downlights, ceiling/wall fixtures • 2,500 hour average rated life • 45 to 50 W per lamp • $5.50 to $7.95 per lamp Analysis 3: Water Management Conclusions Questions?

  16. Paul Roberts Construction Management Lighting Redesign Presentation Agenda • Proposed System • LED lamps • - 50,000 hour average rated life • - 6 to 9 Watts per lamp • - $70 to $90 per lamp • Lighting control system • Unoccupied 10 am – 4 pm • Occupied 7 hours Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management 760 VA per room in King/Queen and Suites Conclusions Questions?

  17. Paul Roberts Construction Management Lighting Redesign Presentation Agenda Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  18. Paul Roberts Construction Management Lighting Redesign Presentation Agenda Energy Cost Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  19. Paul Roberts Construction Management Lighting Redesign Presentation Agenda Halogen Replacement Cost Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  20. Paul Roberts Construction Management Lighting Redesign Presentation Agenda LED Initial Investment Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  21. Paul Roberts Construction Management Lighting Redesign Presentation Agenda Operating Costs Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration *Included in annual replacement cost ^per year for 17 years Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  22. Paul Roberts Construction Management Introduction Presentation Agenda Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 3: Water Management Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  23. Paul Roberts Construction Management Water Management Presentation Agenda Project Overview Introduction of Analyses Goals Increase use of native plants Utilize rainwater collection for irrigation Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  24. Paul Roberts Construction Management Water Management Presentation Agenda Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  25. Paul Roberts Construction Management Water Management Presentation Agenda Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  26. Paul Roberts Construction Management Water Management Presentation Agenda Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Assume .75 in/week natural rainfall Analysis 2: Lighting Redesign Analysis 3: Water Management Gallons/week = .6 x area (sq. ft.) Conclusions Collectable rainwater (gal) = .5 x rainfall (in) x area (sq. ft.) Questions?

  27. Paul Roberts Construction Management Water Management Presentation Agenda Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Area 1: (4) 1200 gallon tanks Questions?

  28. Paul Roberts Construction Management Water Management Presentation Agenda Area 2: (2) 1200 gallon tanks Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Area 1: (4) 1200 gallon tanks Questions? Area 3: (2) 1700 gallon tanks

  29. Paul Roberts Construction Management Water Management Presentation Agenda Cost Analysis Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  30. Paul Roberts Construction Management Water Management Presentation Agenda Cost Analysis Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  31. Paul Roberts Construction Management Conclusion Presentation Agenda Project Overview Analysis 1: Schedule Deceleration Over $250,000 in savings Analysis 2: Guest Room Lighting Redesign Payback period: 2.37 years Annual savings: over $100,000 Analysis 3: Water Management $18,000 savings Increased sustainability Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  32. Paul Roberts Construction Management Acknowledgements Presentation Agenda Project Overview • Penn State AE Faculty • Turner Construction • Salamander Hospitality • Industry members at PACE 2009 • Fellow AE students Introduction of Analyses Analysis 1: Schedule Deceleration Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?

  33. Paul Roberts Construction Management Presentation Agenda Project Overview Introduction of Analyses Analysis 1: Schedule Deceleration Questions? Analysis 2: Lighting Redesign Analysis 3: Water Management Conclusions Questions?