An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Plan ReviewJamie Allen - Cost & Flight Performance Lead, StructuresJohn Castro - Leader, Aerodynamics, S&CBrian Darr - Propulsion Lead, S&C Jatin Mehta - Aerodynamics Lead, Cost & Flight Performance Jon Peterman - Co-Leader, Aerodynamics, Propulsion Andy Wiratama - S&C Lead, Structures Phoenix Aerospace AAE 451 – Fall 2001

  2. Objectives & Schedule Overview • Objective: • Determine a reasonable schedule that will allow a continuous, fluid design period while meeting critical design and review dates. • Schedule Overview – Key Dates: • Preliminary Design reviews - Sept. 27 – Oct. 25 Aerodynamics, Propulsion, Structures, Performance, and Planning • Component Testing - Oct. 16 – Oct. 28 • Critical Design Review - Oct. 30 Design finalized & Construction begins • Flight Readiness Review - Nov. 15 Construction nearly completed (95%) • Official First Flight - Nov. 20 • Project Summary Presentation - Nov. 29 • Thiokol Final Design Report - Dec. 6 Phoenix Aerospace AAE 451 – Fall 2001

  3. Aerodynamics Schedule • Critical Dates: • Sept. 23: Preliminary drag estimate & possible airfoils chosen • Sept. 29: Airfoils selected, wing & tail geometry chosen, general configuration & 3-view completed • Oct. 2: Aerodynamics PDR #1 • Oct. 11: Revisions of PDR #1 material complete • Oct. 16: Trimability and controlability considerations complete • Oct. 18: Aerodynamics PDR #2 • Oct. 21: Stability considerations complete, trimability and controlability revisions complete • Oct. 23: Flight Performance, Stability, and Control PDR • Oct. 28: Aerodynamic design & revision complete • Key Tasks: • Airfoil selection & XFOIL analysis • Geometry selection • Stability & Control considerations • CMARC analysis of tandem wing interaction Phoenix Aerospace AAE 451 – Fall 2001

  4. Propulsion Schedule • Critical Dates: • Sept. 25: Initial propeller, gearbox, & motor selection • Sept. 27: Propulsion PDR #1 • Oct. 11: Revisions of PDR #1 material complete • Oct. 14: Propeller properties and battery analysis complete & propulsion system chosen • Oct. 16: Propulsion PDR #2 • Oct. 16 – 28: Revisions & Propulsion testing • Oct. 28: Propulsion system design complete • Key Tasks: • Propeller selection and analysis • Motor / speed control selection • Battery selection and design • Testing of propulsion system Phoenix Aerospace AAE 451 – Fall 2001

  5. Structures Schedule • Critical Dates: • Sept. 25: Preliminary geometric layout selected & material properties collected • Sept. 29: Landing gear design and analysis complete • Oct. 2: Analysis of wing loads and weight estimations complete • Oct. 4: Structures and Weights PDR • Oct. 16 - 28: Revisions and testing • Oct. 28: Structural design & revision complete • Key Tasks: • Material selection & testing • Structural design, analysis, & testing Phoenix Aerospace AAE 451 – Fall 2001

  6. Stability & Control Schedule • Critical Dates: • Oct. 9: Block diagram, dynamic models, physical constants, nominal feedback gain, & flow chart completed • Oct. 11: Dynamic Modeling PDR • Oct. 16: Flight performance estimations complete • Oct. 21: Stability & Control approximations complete & stability considerations obtained from Aerodynamics • Oct. 23: Flight Performance, Stability & Control PDR • Oct. 28: Stability & Control design and revision complete • Key Tasks: • Dynamic model creation • Nominal gain selection • Stability & control considerations (Aero) Phoenix Aerospace AAE 451 – Fall 2001

  7. Testing & Overall Schedule • Testing Schedule: • Oct. 14: Propulsion computer analysis completed (eg. Gold.m) • Oct. 16: CMARC & additional XFOIL analysis completed • Oct. 21: S&C Simulink analysis completed • Oct. 16-28: Propulsion testing • Thrust & Power tests • Battery & Battery endurance tests • Oct. 16-28: Structural testing • Materials testing • Wing testing (including building methods) • Other structural testing (Fuselage, Tail, …) • Landing gear & possible drop / cart mechanism test • Overall Schedule: • Sept. 29: Concept A or B chosen • Oct. 4: Trade Study #1 • Oct. 18: Trade Study #2 • Oct. 25: Fabrication, Economic, & Test plan PDR • Oct. 28: Design completed • Oct. 30: CDR & construction started Phoenix Aerospace AAE 451 – Fall 2001