Professional Practice Management

I. B .U. Architecture Undergraduate Program ARCH472. Professional Practice Management. Spring, 20 13. CONSTRUCTION ADMINISTRATION Construction Operations Dr. Alaattin Kano ğ lu. Outline. Authority and r esponsibility of a ll p arties Opening a p roject Administrative a ctivities

Download Presentation

Professional Practice Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. I.B.U. Architecture Undergraduate ProgramARCH472 Professional Practice Management Spring, 2013 CONSTRUCTION ADMINISTRATION Construction Operations Dr. Alaattin Kanoğlu

  2. Outline • Authority and responsibility of all parties • Opening a project • Administrative activities • Suspension or termination of the work CONSTRUCTION MANAGEMENT & ECONOMICS

  3. Authority and responsibility of parties Depending upon the type of contract the owner may be authorized: • to award other contracts in connection with the same work, • to require contract bonds from the contractor, • to approve the surety proposed, • to retain a specific portion of the contractor’s monthly progress payments, CONSTRUCTION MANAGEMENT & ECONOMICS

  4. Authority and responsibility of parties • to make changes in the work, • to carry out portions of the work with the owner’s own forces in case of contractor default or neglect, • to withold payments from the contractor for adequate cause, and • to terminate the contract for cause. CONSTRUCTION MANAGEMENT & ECONOMICS

  5. Authority and responsibility of parties The right of the owner: • to inspect the work as it progresses, • to direct the contractor to expedite the work, • to use completed portions of the work before contract completion, and • to make payment deductions for incomplete or faulty work, are also common contractual provisions. CONSTRUCTION MANAGEMENT & ECONOMICS

  6. Opening a project Opening a project requires many details to be completed before the contractor even moves a single piece of equipment onto the project site. CONSTRUCTION MANAGEMENT & ECONOMICS

  7. Opening a project Immediately after award of the contract, the contractor is expected: • to make arrangements for the required policies of insurance, • to obtain permits, • to order long-lead purchase items, • to check the site to determine the availability of storage and work staging areas, • to make arrangements for off-site disposal of surplus or waste materials, and • to take care of numerous other tasks. CONSTRUCTION MANAGEMENT & ECONOMICS

  8. Opening a project • It is desirable for the owner, either directly or through the design firm or construction manager, to issue a written Notice to Proceed to the contractor, which will designate the actual beginning of the contract. CONSTRUCTION MANAGEMENT & ECONOMICS

  9. Opening a project • This is important when attempting to establish the amount of Liquidated Damages where the contractor has exceed the contract time. • The Notice of Award can not serve as a valid Notice to Proceed, as no contract will have been executed between the owner and the contractor at that time. • The notice to proceed sets a precise date that the job began and eliminates any later argument over the time of the contract. CONSTRUCTION MANAGEMENT & ECONOMICS

  10. Suspension or termination of the work • Work may be suspended in whole or in part, and the nature of a suspension is to cease all or part of the work without actual contract termination. • The owner may order the contractor in writing to suspend, delay, or interrup all or part of the work. • However, if the work is delayed or suspended for a longer period than specified, the contractor may claim an adjustment in price for delay damages as well as additional time. CONSTRUCTION MANAGEMENT & ECONOMICS

  11. Suspension or termination of the work • Motives for suspension of the work vary. The owner may have budgetary limits and decide to stop work in certain areas or work may be suspended due to bankruptcy of the contractor. CONSTRUCTION MANAGEMENT & ECONOMICS

  12. Suspension or termination of the work • Some contract documents contains provisions allowing the owner to discontinue all or any part of the work being done by a contractor. • Such termination may be for reasons such as abondoning the work, bankruptcy or insolvency, unnecessary delay of the work. CONSTRUCTION MANAGEMENT & ECONOMICS