An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FY13 11T project status (FNAL) A. Zlobin 11 December 2012

  2. Test Protocol Convergence and acceptance of the test protocols (due in December) • MBHSP01 test plan • Draft – May 2012 • Comments from CERN – May 2012 (Luca, Ezio, Marta, Stephan, Mikko, Bernhard) • 11 T test protocol (CERN) • Draft - Dec 7, 2012 • FNAL comments – Dec 21, 2012 • MBHSP02 test plan • Draft - January 15, 2012 • Discussion of Test Protocols and MBHSP02 test plan on FNAL-CERN video meeting on Jan 22 2013.

  3. 2-in-1 Mechanical Analysis Progress and interactions that took place for the Mechanical concept. • Comments on new CERN results – Nov 2012 • 2-in-1 design analysis (FNAL): • FNAL coil and structure • update with optimized iron cuts along field lines • iron yoke design for mechanical model • CERN coil and FNAL structure • visit to CERN – Nov 2012 (Igor, Fred) • coordinate coil and structure design and parameters • ANSYS file exchange • CERN mechanical model status • CERN closed yoke concept and skin welding • first results this week • Discussion on FNAL-CERN meeting scheduled for Dec 18 2012

  4. 2-in-1 Mechanical Model (FNAL) Plan: • Aperture #1 –available • present MM • Aperture #1– December-January • cut MBH02 • use MBHSP01 collar blocks • Iron yoke, skin, tooling • Design – December • Procurement – December-February • Assembly and test – March-April

  5. Quench Protection • Progress on the quench protection efforts. • What is done or planned on the 1 m model to study/address open questions about quench protection • what are the foreseen next steps in January and February. • Discussion with Bernhard over Skype of quench protection note from CERN – October 2012 • Result comparison – CERN results are now closer to FNAL results (2011) • Preparation of quench protection experimental study in MBHSP02 – December-January • WAMSDO – 11 T dipole – QP modeling and experimental studies • Discussion on FNAL-CERN video meeting in January 2013

  6. FY2013 baseline plan

  7. MBHSP01 autopsy Autopsy steps (September 2012): • Cutting end plates and skin • Clamp and yoke removal • collar-yoke interface, shim inspection • Collar removal • keys, collar-protection shoe interface, ground insulation, heater inspection • Coil inspection • mid-plane shims, all surfaces, leads • Coil size measurements Timeline: September-December Status: • Done, autopsy results and warm magnetic measurements have been presented at the 1st FNAL-CERN video meeting on November 27, 2012.

  8. MBHSP02 Status • MBHSP02 is a 1 m long version of MBHSP01 • Cable: • RRP-150/169 strand • 12x0.025 mm2 SS core • 3 ULs (~650 m) produced • Coils: • ~1 m long • optimized parts and process • MBH05 – done • MBH06 – damaged during IL curing • MBH07 – done • Structure: • Collar packs – modified MBHSP01 • Yoke – available from MBHSP01 • Skin – reinforced HQM bolted skin • MBHSP02 assembly: • coil instrumentation – complete • quench antenna – fabricated and installed • shim plan - complete • coil assembly - in progress with the installation of the ground insulation • collaring and keying - expected to be completed by next week

  9. Strand and Cable Strand: • 152 kg in November 2010 • Expected delivery - February 2012 • Delivered – ~90 kg in July, + ~60 kg in October 2012 • ~20kG – October 2012 (RRR issues) • ~40 kg – January 2013 (changed to Ti based ternary in November 2012) • 152 kg in April 2011 • Expected delivery – August 2012 • new delivery date – February 2013 (changed to Ti based ternary in December 2012) • Submitted PO for 120 kg+120 kg in August • RRP-108/127 (Ta based ternary) • Expected delivery date – February 2013 (if ordered in FY12) • Status: unknown • Possible changes – Ti based ternary (now), RRP-150/169 (after MBHSP02) Cable: • Plan (September 2012 review) • 3 UL of 220 m each (~120 kg) – October 2012 • 3 UL of 220 m each (120 kg) – March 2013 • 5 coils + UL to CERN • ~60 kg left – not enough for 5.5 m long coil! • Status (November 2012) • ~300 m Cu strand, 13.7 mm SS core, single pass – forming fixture commissioning • ~150 m RRP108/127 (+4 strands RRP114/127), 13.7 mm SS core, single pass (cable roping) • ~185 m RRP108/127, 13 mm SS core, single pass (cable roping) • 1 UL ~210 m RRP108/127, 13 mm SS core, two passes with intermediate anneal • 2 m long coil #1 – Dec-Jan • 1 UL will be produced in January • 2 m long coil #2 – Jan-Feb • ~4 UL will be produced in March 2013 • Coils #3 and #4 + spare

  10. Coils • Components – available • End parts – being inspected • MBH08: • Coil winding tooling setup - complete • Cable insulation - underway and expected to be complete today • Coil winding - to begin this week

  11. Collar, yoke, skin • Collar: • RFQ’s, one for EDM and the other for stamping, both using 316 series stainless steel have been sent out and replies received • vendor visit is completed and vendor was selected to make collar laminations for next series of 2 m magnets • First article inspection – January 2013 • Procurement – February 2012 • Yoke laminations - available • Skin - fabrication of 2 m long bolted shell assembly parts has begun.

  12. Design work • Collar shoe thickness increased, drawing revised. • Lift features added to collar design, revised drawing in progress. • Adapter for collar lifting fixture to lift collared coil assembly is in progress. • Coil end part revision based on lessons learned for future coils is on hold. • 2-in-1 yoke design has proceeded as far as it can. Waiting for FEA in order to create and release drawings for the mechanical model. • 2m bolt on skin contact tooling design is in checking and nearly complete. • Long coil winding and curing design is at a very low priority. • Long coil reaction and impregnation assembly drawings continue is at a very low priority.

  13. Schedule update Baseline schedule First 2-in-1 1 m long model in FY13 2 coils Alternative schedule