An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Team Mulberry Andrew Smith, Joseph Entler, Bill Miller

  2. Project Proposal Overview • PV array at Phoenix International Airport • Goal: Using savings from current array: • Reduce grid consumption by adding arrays • Minimize additional space required by additional arrays • Set a 20 year plan to install arrays • Have 100% of power consumption at airport come from solar arrays

  3. Location Specifics • Phoenix, Arizona • Coordinates • 33 degrees 26’ 03 N • 112 degrees 00’ 42 W • Largest Airport in Southwest • 9th largest in United States

  4. Weather • Near ideal climate for solar power • High Irradiance • 85% of Sunshine annually • 211 days of clear skies • Between 10 and 14.5 hours • Clear skies 86% of the time

  5. Weather (cont.)

  6. Solar Data • Direct Nominal- Annual • 2518.6 kWh/m2 • Global Horizontal- Annual • 2117.0 kWh/m2

  7. PV Technology (SunPower E20 Series) • SunPower SPR-435NE-WHT-D • 21.06% Efficiency • 1 x 2.067 meters • Roughly 392 strings of 6 panels

  8. Inverter Technology (Satcon Equinox) • Satcon Technology Corporation • 2 x EQX0500US480T 480V [CEC 2012]

  9. Environmental Considerations • Environmental Impact • Aircraft Emissions • 165,319 lbs CO2/A320 aircraft(full tank) • 2.09 x 108 lbs CO2/A320 aircraft (full tank) • 7.64 x 1010 lbs CO2/year (full tank) • Solar Offset Emissions • 1.2 lbs CO2 / kWh • No noticeable impacts with solar when we compare to alternatives

  10. Long Term Goals • Use the 4.7 million that will be saved from the 2008 array project to build additional arrays • Offset the emissions of the year round aircraft traffic for the future and improve air quality • Have a sustainable energy source that would lower annual energy costs • Provide a project that can be reproduced at similar locations

  11. Building Specifics • Roof of Airport Hangers/Terminals • Horizontal plane • Little to no shade • Large area to build on (Est. 20,000 m2)

  12. Array Details • Current Array • 5.4 MW high efficiency • 16,000 solar panels • Offsets 1000 cars per year of emissions • Array size to be repeated • 1.9 MW high efficiency • 4861.6 square meters • 2352 solar panels

  13. System Cost • Each Array project cost • 4,239,287.29 • Additional project will be based off of savings from previous projects • Increasing in size and payback each year

  14. Life Cycle Analysis • $556,199.51 NPV/LCS at year 20

  15. Payback • Array #1 • $4,239,287.29 • 5.5 years • Array 2-10 • Payback would dramatically decrease with added arrays

  16. Financial Overview • $4,239,287.29 • Analysis Period: 20 years • Discount Rate: 3% • Inflation rate: 2% • Nominal discount rate: 5.06% • Federal Income : 35%/year • State Income: 6.7%/year • Sales tax: 0% (Incentive) • Insurance: 0.5% • Incentives • $0.04/kWh (PTC) • 30% (Fed ITC) • 10% (State ITC) • $1.75/W (CBI) • $0.14/kWh (PTI)

  17. Conclusion • It makes financial and environmental sense to proceed with project • Payback is within a feasible period (5.5 years) • This project fits into the city’s priorities of increasing sustainable energy while savings money • Allows for savings to be spent on more array or sustainable projects