An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sustainability of Coal Supply and Demand J.Goel, Chief General Manager(S&M) Coal India Limited ASSOCHAM New Delhi 24th February 2009

  2. Coal & Energy sector – India & the World

  3. Coal reserve – India and the World

  4. Coal production in India - Highlights 30Mt in the year of independence 77 Mt prior to nationalization of coal sector 3.7% growth in pre-nationalization period Oil shock of Seventies - faster growth in coal sector prerequisite for planned growth of the Country leading to Coal sector nationalization From 78Mt in 1973-74 to 457 Mt in 2007-08 5.3% growth in post-nationalization period

  5. Coal production– India and the World

  6. PLANWISE PRODUCTION AND ANNUALISED GROWTH OF CIL

  7. Reaching coal to consumers – CIL’s dedicated service of 35 years CIL developed extensive logistics infrastructure over the years- commensurate to growth in Production • 161 operating Railway sidings catering coal loading of 473 operating mines • CIL contributes 27% originating traffic of IR • Contributing freight revenue of 24%-- more than the combined contribution of Cement, Fertilizer, food grains and POL • Manual/CHP loading largely replaced by Mechanical loading through pay-loaders • Rake loading time reduced from 16 hours to 2.5 hours • All loading points, both rail & road, have electronic weighing facilities and quality assessment facility

  8. Emerging demand of energy-- sustainability of Coal supplies • Coal provides 56% of primary energy of the Country against 29% Globally • 61% of power generation India depends on coal against 40% internationally • Sustainability of coal supplies, the single most important issue for continuing desired growth rate. • Policies on coal production and distribution need to highlight priority areas

  9. Contribution of Coal in power generation – India & World

  10. Shift in contribution in indigenous production

  11. Policy issue – shift in contribution in indigenous production • From a level of 90% in the post-nationalization period (IV Plan), CIL’s contribution in Country’s coal production reduced to 84% in X Plan. • Coal blocks allotted for captive consumption • Production of CIL to reduce drastically to 76% in XI Plan and to 63% in XII Plan. • Negative growth in production of CIL from XIII Plan. Production to reduce to 640Mt in 2021-22 from 664Mt in 2016-17, share in indigenous production below 50% level

  12. Challenges on CIL for XI Plan • CIL to produce 520.5Mt coal in 2011-12 – growth from a level of 5.4% in X Plan to 7.6% in XI Plan. • 33% of coal production to come from new projects • To accomplish the task acquisition of 50,000 Ha land required per year. • Prompt statutory approval from State and Central Statutory Authorities………….. – no instance of denial of approval • no instance of timely approval too

  13. Coal distribution policy – role of CIL New Coal distribution policy (NCDP) introduced in October’07. Policy provisions: • Distinction between core & non-core sectors abolished • Coal supply through legally enforceable Fuel Supply Agreement & LOAs for new consumers • Power, including Captive Power & Fertilizer sectors to get 100% coal requirement • Other sectors to be provided with 75% coal requirement • CIL to meet entire requirement of coal of the Country, if required, even by importing coal … And at the same time, share of CIL in Indigenous production to reduce

  14. Major events post October’07: changed demand scenario on CIL • 505 units cleared by SLC (LT) for issuance of letter of assurances (LOA) • 400 units already deposited Commitment Guarantee (CG) –10% of coal value • 300 units ready for coal consumption • Time limit extended by Government for depositing CG • Large numbers of fresh applications still pending with SLC (LT) for grant of further clearances for LOA/FSA • Units from different industries not covered by SLC (LT) also waiting for LOAs

  15. All India Coal demand & Indigenous availability scenario – as envisaged in XI Plan (2011-12)

  16. Existing Sector-wise commitment on CIL and production Plan for 2011-12 Figs. In Mt

  17. Demand-supply – current scenario • Committed demand on CIL in 2011-12 already touched 749 Mt – gap between demand-availability 229Mt. • Demand to further increase to 861 Mt by 2012-13, widening the gap to 315 Mt. • Supply already committed for XI Plan exceeds CIL’s production projection of XI and XII Plans by 229Mt and 85Mt respectively

  18. Impact of effective shortfall on CIL -- 100% FSA supplies to existing TPSs as in 2007-08 with trigger for compensation at 90% -- For New power projects only 77 Mt of coal left after providing FSA quantity to other consumers -- Trigger for Compensation for new consumers shall logically go down to 24% -- Additional new demand of 64Mt from non-power consumers – most of them ready to take coal immediatly -- e-auction needs to continue to meet spot market demand apart from catering 25% coal requirement of FSA holders of other than Power -- LOA policy for non-SLC (ST) consumers is in pipeline – widening of gap likely to expose CIL for large scale compensation payment

  19. Imports –sustained supply – emerging issues Requirement to start with – say 200Mt Issues involved • Available Port Capacity in the Country • Hinterland coal movement possibilities • Optimization of transport capacity -- scheduling import • Blending facilities at consumption centers • International coal trade possibilities -- effect of additional demand from India

  20. Port Capacity of the Country • Current coal handling capacity at Ports not exceeding 100Mt • 30Mt Coastal shipment from East to South likely to cross 50Mt by XI Plan • 25 Mt of current imports of coking coal projected to increase to 40Mt by 2011-12 • 25Mt steaming coal already being imported • Residual capacity, if any, for captive use only

  21. Hinterland coal movement capacity • Only indigenous coal movement would require 300 rakes/day by 2011-12 • Rail connectivity of up-coming coalfields – Karanpura, Gopalpur, Rai-Mandgarh already identified as critical area for indigenous coal movement • 200 Mt of import would require additional movement of 150 rakes/day • East-North Dedicated freight corridor – prerequisite yet not sufficient and not likely to come up in XI Plan

  22. Optimization transport capacity -- scheduling import • About 20% seasonal fluctuations in coal production – rake requirement to increase to 360 rakes/day in peak period – December-March. • Peak freight movement, including fertilizer and foodgrains, clashes with coal • Imports to be scheduled for optimum utilization of transport capacity -- corresponding flexibility at port also to be made available for handling cargo

  23. Blending facilities at consumption centers • Power stations, by and large, not capable using more than 20% imported coal • Rake movement model ideally should be 4:1 for indigenous and imported coal at Power stations • Average rake movement ratio likely being 2:1, blending yards to be developed with provision for supplementing indigenous coal transportation • Blending arrangement for smaller consumers even difficult – exposure to cost increase and adulteration

  24. International coal trade -- effect of additional demand from India • Ocean trade quantity for steaming coal about 700-750 Mt • Import of 200Mt by CIL/Indian Agencies – 30% surge in current demand leading to -- corresponding escalation in coal price -- constraints in availability of loading berth -- limited availability of vessels and freight hike – particularly in view of draft limitation in many of the Indian Ports

  25. Conclusions • The gap between demand of coal and its availability in the Country much more than the projections of XI Plan document. • Unlike earlier plans, demands more likely to fructify due to legal enforceability • Importing to bridge the gap – not attainable as a short-term strategy for logistics mismatch • Additional demand and consequent uncertainty of international market – import only for supplementing - not a means for sustainable coal supply

  26. Conclusion … contd. • Indigenous production, therefore, requires to grow at a faster rate to narrow down the gap • Issues related to curbing delay in project clearance from all statutory authorities and timely acquisition of land need policy initiative • CIL having limited scope in augmenting production, key role to be played by captive blocks • Status of CIL being shifted towards only one of the major players in coal sector, responsibility mandated by NCDP not matching with authority

  27. Conclusion … contd. • Demand side management needs special consideration • Improved fuel utilization technology could be rewarded by priority coal release • Let market force determine coal supplies – likely to goad captive blocks for faster and improved project utilization • Acquiring coal properties abroad may improve sustainability of imported coal supply • Infrastructure building, particularly ports and railways including dedicated vessels and rolling stock to be considered as thrust area • Allotment of indigenous coal blocks for CIL to be attuned to meet increased demand

  28. Thank you