Pacific Aviation Directors Workshop March 13 – 15, 2012 PowerPoint Presentation
Download Presentation
Pacific Aviation Directors Workshop March 13 – 15, 2012

Loading in 2 Seconds...

play fullscreen
1 / 14

Pacific Aviation Directors Workshop March 13 – 15, 2012 - PowerPoint PPT Presentation


  • 106 Views
  • Uploaded on

F ederal A viation A dministration. Pacific Aviation Directors Workshop March 13 – 15, 2012 Hosted by: A B Won Pat International Airport - Guam. DEPARTMENT OF PUBLIC WORKS & TRANSPORTATION YAP INTERNATIONAL AIRPORT PRESENTATION. Introduction.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Pacific Aviation Directors Workshop March 13 – 15, 2012' - kele


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Federal Aviation Administration

Pacific Aviation Directors Workshop

March 13 – 15, 2012

Hosted by: A B Won Pat International Airport - Guam

DEPARTMENT OF PUBLIC WORKS & TRANSPORTATION

YAP INTERNATIONAL AIRPORT PRESENTATION

slide2

Introduction

1. Completed Projects within the Last five (5) years

2. UPCOMING PROJECT

3.ONGOING PROJECT

4. PROPOSED PROJECT

slide4

Y.I.A. Aircraft Rescue and Firefighting Facility Project

  • (April 2008 – February 2010

FRONT VIEW OF THE BLDG. FACING RUNWAY.

TURN-OVER CELEBRATION

SOUTHEAST SIDE OF THE BLDG.

SOUTHWEST SIDE OF THE BLDG.

slide5

Apron Reconstruction Project (February 2008 – December 2009

APRON EAST SIDE

APRON WEST SIDE

APRON WEST SIDE

APRON EAST SIDE

slide6

Rehabilitation, Installation of Perimeter Fencing and Upgrading of

  • lightings and signs
  • (January 2006 – September 2007)
slide7

Y.I.A Terminal Facility Rehabilitation (July 2006 – September 2007).

FRONT VIEW OF THE BUILDING FACING VEHICLE PARKING AREA (SOUTHSIDE).

NEW DEPARTURE LOUNGE.

slide8

UPCOMING PROJECTS

  • Departure Lounge Remodeling
  • New Hanger
slide9

Ongoing Projects

AIRPORT MASTER PLAN

slide10

Proposed Projects

  • Yap Neighboring Island Airport Projects

Ulithi Airport

Fais Airport

Woleai Airport

Parking Lot Solar Panel Installation

ARFF Building Solar Panel Installation

slide11

PERIMETER FENCING AROUND THE RUNWAY.

2 (TWO) WIND CONES.

RUNWAY LIGHTINGS.

REHABILITATION OF DAMAGED ITEMS AT THE TERMINAL.

STRIPING ALONG THE RUNWAY.

ULITHI AIRPORT

slide12

PERIMETER FENCING AROUND THE RUNWAY.

2 (TWO) WIND CONES.

PAVEMENT RESURFACING.

RUNWAY LIGHTINGS.

CONSTRUCT NEW AIRPORT TERMINAL.

FAIS AIRPORT

slide13

PERIMETER FENCING AROUND THE RUNWAY.

2 (TWO) AIRFIELD WIND CONES.

PAVEMENT RESURFACING.

RUNWAY LIGHTINGS.

CONSTRUCT NEW AIRPORT TERMINAL.

WOLEAI AIRPORT

end of presentation
END OF PRESENTATION

“THANK YOU”

“KAMMAGAR MAGAR”