html5-img
1 / 23

CCG Meeting Angaston 3 rd June 2009

CCG Meeting Angaston 3 rd June 2009. Mine Operation Update – June 2009. Eastern Area Dressing of upper levels of west face to reduce colour variation Seed bombs being used to grass the upper levels (see photograph) Recent rain has allowed tree planting to commence

kasa
Download Presentation

CCG Meeting Angaston 3 rd June 2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CCG Meeting Angaston 3rd June 2009

  2. Mine Operation Update – June 2009 Eastern Area Dressing of upper levels of west face to reduce colour variation Seed bombs being used to grass the upper levels (see photograph) Recent rain has allowed tree planting to commence Completed crushing of upper aggregate inventory & moved the mobile crusher down to the next lower level – see photo Western MPL 118 Rain has delayed topsoil removal but continuing, expected to be completed now by mid June The accessible topsoil mound is continuing to be sown with sterile rye grass Overburden being placed in first level (see photo) Overburden volume moved 417,500t

  3. Eastern Area Sheeting of western slopes to reduce visual impact Seeding of western slopes on eastern dump Donovans Earthcare innovating seeding method using clay ‘bombs’ Mine Operation Update

  4. Mine Operation Update Eastern area Mobile crusher moved from RL394 to lower level RL384. Buffer height lifted to limit visual impact. Due to heavy NEXY demand we are short in crusher capacity – assessing options to increase crushing rate

  5. Mine Operation Update

  6. Truck Tarp Survey Conducted Monday 1st June 2009 Full compliance with tarps in place -- 88% Non Compliance no tarps – 6.5% Partial compliance (either truck or trailer not tarped in dual configuration) – 5.4% Entry Exit Road tarping & parking lanes for safe traffic movement requires movement of the telecom line, 3 new lights and removal of 9 trees subject to Native Vegetation Act requirements with a new plantings ratio of 5 – see photo Tarp Commitment – Adelaide Brighton Cement Trucks to have and use tarps for movements to ABC Angaston – recommended by 30th June 2009

  7. Front Entrance upgrade Intermediate actions Widen road for truck tarping area - narrow entrance safety concern 9 trees to be removed, replaced with 45 new plantings – this is compliant with Native Vegetation Act Telstra and power cable relocation Street lighting installation at front gate and truck wash area

  8. Front Entrance Upgrade Design plans submitted to Council for approval Refer handout for details Drag out control Road Sweeper minimum daily sweep (more if required) Washing down of entrance

  9. Community Environmental Issues Refer handout for Complaints Glass limestone compressor room

  10. Mine Operation Update – June 2009 Other Meeting requested with PIRSA to finalise the Overburden options report with KRC including a site visit Agreed to new $140k rehabilitation work for FY2010 covering Kalimna rd, West MPL 1st level, MPL vehicle track, West side rail embankment, & west side of east mound Still chasing NRM Board approval of Jaeckeli Ck Management Plan to commence Later train loading continuing EIP Dust mitigation plan - see later Investigating Mine closure concept plans (subject to hydrology outcome) – see later Mine Planning study continuing with a visit from geotechnical experts (KRC) to better determine pit shape into the future

  11. Mine Operation Update – June 2009 Other New Mine manager & Maintenance manager positions to be filled to strengthen management, planning, maintenance and project work, a further commitment to the mine and the community. Preference is for living locally Increased activity due to derailment and ABC Birkenhead increased drag out Remedial Action – limited use of truck-wash due to water drag out Use of water cannon several times to wash road, with apologies to council

  12. Results taken from the Silt Trap Overflow: 28/4/09

  13. Penrice Community ParkConcept Mine Closure Plan

  14. Dust Emission Reduction Initiatives - EIP

  15. Dust Emission Reduction Initiatives

  16. TSP & PM10 Dust results May

  17. Dust Emissions – on site monitoring

  18. Dust Suppression & Noise Abatement Initiatives Penrice Rd residents meeting with residents Site Noise Modeling by Bassett Acoustics – commence in 2nd week June. This will include the new mobile crusher location in the east mound Crushing capacity not been met within the current hours – longer hours will be investigated subject to environmental footprint, safety and labour requirements Dust suppressant trials – see photo Green dust suppressant (as per photo) has worked well and not affected by rain. It forms a crust on the stockpiles and prevents the stockpiles from eroding (water and wind). This is not a cost efficient option and we will continue to trial products that best meet common objectives 4 products have been trialed to date Tallow not effective on roads and will be assessed for stockpiles Polocitrus is in use on train and aggregate crushing plant successfully Green dust suppressant effective for stockpiles but cost prohibitive Polycom has been applied to selected routes around the weighbridge successfully and trials are ongoing

  19. Dust Suppressant Trial – ABC stockpiles

  20. The Barossa Council – Better Development Plan • Submission tendered by PIRSA, EPA and Penrice • Will be able to be viewed via the Council web • Public hearing 10th June 2009 • Key Penrice Issues • Extractive Industry is a legitimate land use • The EPA guidelines for Separation should be followed in any building activity including current zones – see photo • The proposed rezoning will conflict with the mine operations • Penrice opposes key elements of the Better Development plan

  21. Traffic Counter Derailment meant truck haulage to Osborne from 17/5 to 23/5 resulting in approx 80 extra truck movements per day

More Related