PROJECT PROFILE. MAPEX INFRASTRUCTURE PVT. LTD. PANAGARH- PALSIT SECTION OF NH 2. (Km 520.103 TO Km 584.929). The Project:. Organization Structure:_______________ “INSTITUTIONAL”. PROJECT ADMINISTRATION:-______. NHAI :-

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'PROJECT PROFILE' - karyn-vaughan


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

PROJECT PROFILE

MAPEX INFRASTRUCTURE PVT. LTD.

PANAGARH- PALSIT SECTION OF NH 2

(Km 520.103 TO Km 584.929)

project administration
PROJECT ADMINISTRATION:-______
  • NHAI:-

The National Highway Authority of India, a statutory body constituted under the provisions of the National Highway Authority of India, Act, 1988 and having it’s principle office at Plot No. G-5 & G-6, Sector 10, Dwaraka, New Delhi 110 045, hereinafter referred to as NHAI.

●Concessionaire:

Mapex Infrastructure Pvt. Ltd.:-

M/s. Mapex Infrastructure Private Limited, a company incorporated

under the provisions of the Companies Act, 1956, having its

registered office Arihant Building, 2nd Floor, 53A, MirzaGhalib Street, Kolkata-700 016, West Bengal, India. hereinafter referred to as the “Concessionaire”

slide5
EPC Contractor :

GAMUDA-WCT :-

Gamuda-WCT Private Limited, a company incorporated in Republic of Mauritius under Companies Act, 1984.

Registered office :-

Arihant Building, 2nd Floor, 53A, MirzaGhalib Street, Kolkata-700 016, West Bengal, India

  • Independent Engineer:

Unihorn India Pvt. Ltd.

Project Office :-

C/o, Bankim Timber Works (AmarSwapna),

Opposite of Jaguar Shop,

Near Purvasha Bus Terminal,

Alisha, G. T. Road, Post - Joteram,

Burdwan - 713 101, West Bengal

salient milestones
SALIENT MILESTONES:_______________
  • Project Implementation Period :
      • Starting Date: 21.11.2001
      • Completion Date: 09.06.2005
  • Operation & Maintenance Period:
      • Starting Date: 10.06.2005
salient features
SALIENT FEATURES:_________________
  • Minor Bridges : 5
  • ROB : 1 ( Span- 496.917 m)
  • Underpass : 14
  • Culverts : 64
  • Interchanges : 1
  • Signalized Junction : 2
  • Grade Separator: 1
operation and maintenance for the proposed highway
OPERATION AND MAINTENANCE FOR THE PROPOSED HIGHWAY:____________________
  • The 15 years operation and maintenance of the project consists of:
      • Periodic maintenance
      • Routine maintenance
  • Periodic maintenance have been provided during 5th year,

10th year and 15th year from commercial operation date.

  • Routine maintenance works are standard and is generally expected

to follow the operational and performance criteria as specified in

relevant IRC/MORTH standards and specification.

project assets and facilities
PROJECT ASSETS AND FACILITIES:____
  • Maintenance Yard (Km. 531+196)
  • Wayside Amenity (Km. 531+757)
  • Truck-Lay-Bye (Km. 557+895)
  • Gobinda Setu (Km. 563+119)
  • Grade Separator SH-7 (Km. 566+221)
  • Shaktigarh ROB (Km. 581+718)
  • PIU Complex (Km. 584+926)
  • Palsit Interchange (Km. 584+696)