Finding Reliable Power Supply for the Erongo Region

Loading in 2 Seconds...

play fullscreen
1 / 22

Finding Reliable Power Supply for the Erongo Region - PowerPoint PPT Presentation


  • 163 Views
  • Uploaded on

Finding Reliable Power Supply for the Erongo Region. Arandis Investment Conference PI Shilamba MD: NamPower 4 November 2011. Content. Supply and Demand in Namibia Challenges Update on Projects Successfully Concluded Under Construction In Feasibility NamPower’s focus.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Finding Reliable Power Supply for the Erongo Region' - kamuzu


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
finding reliable power supply for the erongo region

Finding Reliable Power Supplyfor theErongo Region

Arandis Investment Conference

PI Shilamba

MD: NamPower

4 November 2011

content
Content
  • Supply and Demand in Namibia
  • Challenges
  • Update on Projects
    • Successfully Concluded
    • Under Construction
    • In Feasibility
  • NamPower’s focus
supply demand situation
Supply & Demand Situation
  • Installed generation capacity of 414 MW (Including Anixas)
    • increase with 92 MW by March 2012 (Ruacana Unit 4)
  • Transmission Network connected to
    • Botswana and RSA
    • Zambia connected via Caprivi Link and providing alternative route to Zimbabwe, DRC and Mozambique
  • Maximum Demand of 511 MW (incl. Skorpion 580 MW) – Jun 2011
  • Imports up to 80% of energy requirements in some periods
  • Demand growth 2011
    • Energy (MWh) = 3.7% (forecast 2012 : 4.4%)
    • Peak demand (MW) = 3.5% (forecast 2012 : 4.6%)
challenges for the next 5 7 years
Challenges for the next 5-7 years
  • Same as SAPP Challenges
    • General energy shortage
    • High Demand growth & step loads
    • Rural Electrification (New connections)
    • Shortage of resources (HR and Financial)
    • Struggle to agree electricity pricing path to reflect cost of new build requirements
    • Little private investment into the Power Sector
    • The process of ensuring security of supply has been getting steadily harder for several years, but it has not been obvious because NamPower has been effective in dealing with it up to now.
    • Approaches used successfully to date must now be augmented by new activities
short term critical supply project stcs
Short Term Critical Supply Project (STCS)
  • Any base load power station for commissioning only by 2015/2016
  • Power supply deficit of 80 MW as from the 2012 winter, increasing to 300 MW by 2015.
  • Worsened by expiry of ZESA agreement in 2013
  • A dedicated team appointed to the project
  • Solutions will include one or a combination of the following:
  • New power purchase agreements with SAPP trading partners
  • New renewable and PPA with renewable IPP’s
  • Increased DSM programs
  • Upgrading of existing plants
  • PPA’s with other IPP (Arandis Power)
  • Final project plan expected by Dec 2011
critical to implement base load power plant
Critical to implement base load power plant
  • Capacity constraint due to absence of any new base-load plant
  • A base-load power station is essential by January 2016
  • Not many indigenous large plant option available
    • Guidelines: Energy White Paper => Serve 75% of energy and 100% peak
  • All base-load plants have Forex components that need to be accounted for
  • Electricity Tariffs
    • Recent average tariffs increase of 18.28%
    • Upcoming capital investment of up to N$14 billion over the next 4 to 5 years
    • It is estimated that the cost of supply to NamPower in 2015/16 can double to N$1,00/kwh compared to the current levels of 45c/kwh
    • Need for GRN, ECB and NamPower to agree on a smooth upward pricing path with the view to avoid future price shocks, especially when a base-load power station will be commissioned by 2016
slide9

Conceptualization:

Nuclear,

Municipal Waste, CSP

F

U

N

N

E

L

Investigation:

Wave Energy

P

R

O

J

E

C

T

Feasibility:

LOHEPS, Recycled fuel,

Erongo Coal, Baynes, Kudu Gas, Wind, Solar PV, Zizabona, Biomass, Van Eck Rehabilitation

Implementation:

4th Unit Ruacana

Operation:

Hwange, DSM, Caprivi Link, Anixas

hwange investment
Hwange Investment

PPA (150 MW) effective as from 2008

A good example of regional cooperation

Project declared “Power Deal of the Year“ - 2010 Africa Investors: Infrastructure Investment Awards

caprivi link interconnector
Caprivi Link Interconnector
  • Second largest investment in Namibia (NAD 3,2 billion)
  • Project completed below budget
  • 300 MW transfer capacity: completed June 2010 with official commissioning on 12 November 2010
  • Opportunity to implement phase 2 (additional 300 MW)
  • Africa Energy Award for “Best Fast Track Energy Project”
anixas
Anixas
  • 22.5 MW Diesel Generators at Walvis Bay
  • Project cost N$ 375 million
      • NAD 250 million grant from GRN
      • NAD 125 million from NamPower balance sheet
  • Additional land adjacent to Paratus to build Anixas and new Transmission Station
  • Design Philosophy to allow for future extensions
  • COD - 21 July 2011
  • Official inauguration 03 November 2011
slide13

4th Unit Ruacana

  • Installation of a 4th unit at Ruacana Hydro Power Station
  • Increase capacity with 92 MW
  • Project Cost NAD 750 million
    • Project Dates:
    • Commencement date was 27 March 2009
    • Work on site commenced during July 2010
    • Commercial operation is expected first quarter of 2012
erongo coal power station
Erongo Coal Power Station

Establishment of a coal fired power station in the Erongo region has been identified as part of NamPower’s Security of Supply plan

NamPower seriously in consideration of this option as it can be fast tracked

Medium sized capacity (150 to 300) MW)

Modular development allowing phased developments up to 800 MW

progress and timelines required
Progress and timelines required
  • Project definition to be confirmed by Jan 2012
    • EIA Scoping to be concluded and Technical concept confirmed (including environmental mitigation requirements)
    • Coal options confirmed and Coal value chain optimised
    • Land procurement started
    • Water supply solution determined
    • Indicative costing (+- 25%) of complete project (power station, transmission, other infrastructure)
    • Indicative project schedule to implement complete project
  • Ready to start Tender/procurement process – April 2012
  • Final investment decision - June 2012
  • With good governance support Commercial Operation possible by 2015
critical considerations
Critical Considerations
  • Fast track options
  • Clean Coal Technology selection to allow fuel flexibility
  • Coal sourcing options and cost
  • Coal handling capacity at Walvis Bay port
  • Land Availability and timing to procure
  • Water availability and supply options
  • Proximity to existing infrastructure necessary to keep cost down
    • Infrastructure (road, rail, transmission grid, water supply etc)
  • Economic environment (incl. tourism and sustainable development plans of region/towns)
  • Environmental issues such as protected areas and biodiversity

NamPower

16

environment and site selection
Environment and Site Selection

ESEIA study completed in June 2009, now update of study required:

Sites considered and evaluated through a comparative Multi Decision Making Criteria Model considering technical, biophysical and socio-economic issues:

Close to Walvis behind Dune 7

North of Swakop

Site East of Arandis

Site West of Arandis

Outcome of evaluation: Site East of Arandis ranked as most preferred

other generation projects
Other Generation Projects

Kudu Gas

NamPower mandated to develop power station in terms of the 2004 Cabinet resolution

Promising,cooperation with upstream parties, favourable gas price

Strong interest from Eskom and CEC

Well researched data available

FID expected by middle 2012

Baynes Hydro

500 MW mid-merit/peaking Power Station on Kunene River

Techno-economic and EIA studies underway, to be completed by the end of 2011

Political will from both parties to expedite project

Coordinated by the governments of Angola and Namibia through the PJTC

Could be commissioning by 2018

renewable power
Renewable Power
  • Wind
    • Diaz Power - +/-44MW at Luderitz
    • Innowind – +/-50MW at Walvis Bay
  • Large Solar PV
    • 3 x +/-10MW throughout Namibia
  • Small Solar PV connected to grid (Net-metering)
    • Discussions ongoing with ECB on integration of such systems
  • Medium Solar PV Hybrid Systems
    • Tsumkwe recently commissioned
    • Lessons learned will be implemented on next project
  • Biomass (Invader Bush)
    • Draft Feasibility study to be concluded end 2011
    • Harvesting of woodchips
    • Transport and/or on-site processing e.g. Torrefaction process
west coast developments
Concluded

Add capacitor banks at Omburu Substation as required during certain operating conditions

2nd Omburu-Khan 220kV required for contingency constraint

220kV Khan-Trekkopje and 132kV Trekkopje-WlotzkaBaken development

Planned

Kuiseb Substation upgrade to 220/132kV (current 220/66kV)

Provide for upgrades to customers in area (Walvis Bay, mining, wind farms)

Timing determined by first customer upgrade (Walvis Bay 2012/3)

220kV Khan-Kuiseb link

System strengthening and supply to proposed uranium mines

Timing determined by customer development (Husab 2014)

In Tendering Phase

Replace old 220kV line between Rössing and Walmund with 220kV double circuit

West Coast Developments
nampower s objectives and priorities
NamPower’s Objectives and priorities

Next 4 years

Commissioning of a base load power station

Successful management of the short term critical power supply situation

Increased contribution to rural electrification

Improvement of Corporate social responsibility

Continuation of internal productivity and efficiency measures

This financial year (2011/12)

Keep lights on through out the year (no load shedding)

Investment decision on a base load power plant

PPA with IPP’s (wind, solar PV, HFO/slop)

Tariffs to reflect Cost of Supply

nampower
NAMPOWER

Thank you