1 / 6

April 2008 (10 marks) From the following particulars, calculate material and labour variance

April 2008 (10 marks) From the following particulars, calculate material and labour variance. Calculation of standard quantity for actual output 800*3. 1000. =2400. Calculation of actual quantity: 800*3.125 =2500. MCV=(SQ*SR)- (AQ*AR) =(2400*2)- (2500*2.50)

kamran
Download Presentation

April 2008 (10 marks) From the following particulars, calculate material and labour variance

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. April 2008 (10 marks) From the following particulars, calculate material and labour variance

  2. Calculation of standard quantity for actual output 800*3 1000 =2400 Calculation of actual quantity: 800*3.125 =2500

  3. MCV=(SQ*SR)- (AQ*AR) =(2400*2)- (2500*2.50) =4800-6250 =-1450 (ADVERSE) MPV=(SR-AR) * AQ = (2- 2.50) * 2500 =-0.50 * 2500 = -1250 (ADVERSE) MUV= (SQ- AQ) * SR = (2400-2500) * 2 = - 100 * 2 = - 200

  4. Calculation of std hours for actual output: 800*600 1000 = 480

  5. LCV=(SH*SR) –(AH*AR) =(480*3) – (400*2.50) = 1440 – 1000 = 440 (FAVOURABLE) LEV= (SH-AH) * SR = (480-400) * 3 = 80 * 3 = 240 (FAVOURABLE) LRV= (SR-AR) * AH = (3 -2.50) * 400 = 0.5 * 400 = 200 (FAVOURABLE)

  6. THANK YOU KAVYA DIANA SPN110309