1 / 14

PPP Projects in the Education & Health Sectors January 26, 2011 Kyrgyz Republic

PPP Projects in the Education & Health Sectors January 26, 2011 Kyrgyz Republic. Art Smith Vice Chair, UNECE Team of Specialists asmith@mainet.com. Education Case Study. James F. Oyster School Washington, DC. James F. Oyster School. Public elementary school in Washington, DC

kalei
Download Presentation

PPP Projects in the Education & Health Sectors January 26, 2011 Kyrgyz Republic

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PPP Projects in the Education & Health SectorsJanuary 26, 2011Kyrgyz Republic Art Smith Vice Chair, UNECE Team of Specialists asmith@mainet.com

  2. Education Case Study James F. Oyster School Washington, DC

  3. James F. Oyster School • Public elementary school in Washington, DC • Only bilingual school in Washington public school system; dual-language immersion programme • 350 students • Built in 1926 • By the mid-1900s, the school building was in dire need of replacement/renovation

  4. James F. Oyster School • The Washington, DC School System was unable to meet the needs at Oyster School • Fiscal constraints meant that there was virtually no funding available for school construction and modernization • The District had not built a new school in more than 20 years • The District had operated for more than 20 years without a long-range facilities plan • The parents of the Oyster School students organized to pressure the DC government into action, and formed a nonprofit organization, the 21st Century School Fund, to assist the government in this effort.

  5. The James F. Oyster School Property 29th Street School Playground Calvert Street 1.7 acres

  6. James F. Oyster School The 21st Century School Fund and the District of Columbia Public Schools (DCPS) worked together to gain support for a public-private partnership from the Mayor, City Council, and Board of Education The Fund and DCPS envisioned leveraging an underutilized asset, the undeveloped half of the Oyster School lot, to obtain a new school. Proposals were solicited from the private sector in 1998, using a competitive bidding process.

  7. James F. Oyster School • The key aspects of the selected partnership were: • The District deeded the excess land to the developer, who built a 211-unit, nine-story apartment building on the site. • The private developer financed, designed (with DCPS and community input), and built a 47,512 square foot state-of-the-art school on the site of the old Oyster School. The new school included a computer lab, gym, library, and underground parking garage. • The developer financed the school through a 35-year tax-exempt bond issue, which is being retired by payments in lieu of taxes by the apartment building owner. • Upon completion of the new $11 million school, the developer turned it over to the DCPS. The school opened for classes in the fall of 2000.

  8. The New James F. Oyster School Constructed without public debt or financing

  9. The James F. Oyster School and Adjacent Apartment Building Source: Google Map

  10. Healthcare Case Study Uzbekistan Health Project

  11. Project Objectives • The Government of Uzbekistan seeks to improve national medical diagnostics by introducing advanced technology and international best practices. • The proposed solution is a PPP: • The private partner will design, finance, build, equip, and operate medical diagnostic centers. • Each site would provide diagnostic imaging, lab tests, specialist outpatient care, and day surgery. • Four locations identified: Tashkent, Samarkand, Fergana, and Navoi. • Private partner assumes demand risk.

  12. Current Medical Diagnostic Prices(September 2010. Prices in Uzbek Som; ~1,600 Som = US $1

  13. Enabling Affordable PPP Service Delivery • The Government of Uzbekistan will provide: • Free long-term land leases, with locations near utilities and public transportation • Government utilities provided free of charge • Tax incentives • Custom fee incentives • Ability to provide additional services • Application for grant from the Global Partnership for Output Based Aid • The selected private partner(s) will pay $125,000 per diagnostic center to the consultants providing PPP technical support to Uzbekistan.

  14. Uzbekistan Health Project • Project outcome not yet known • Investors Conference held in Tashkent, December 13-17, 2010 • Seven companies have expressed interest in bidding; those are from: United States – 3 Russian Federation – 2 Uzbekistan – 1 Canada – 1