An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2nd Workshop on Energy for Sustainable Science at Research Infrastructures Report on Parallel Session A4: Energy Quality and Operation __________ Roberto Visintini

  2. Energy Quality and Operation – 1 High Temperature cooling of cryoplant and klystrons (J. Jums – ESS) • “4R-based” energy concept at ESS • 40 MW of electrical power, most of it turned into waste heat  recycle heat! • Lund District Heat System = source and customer • 71% of all & 100% of high grade heat: RF & Cryoplants • Focus on RF & Cryoplants • Balance the risk of klystron collector high temperature (80-90 C) cooling with benefits from heat recovery • There are risky choices but many benefits are possible Report on Parallel session A4

  3. Energy Quality and Operation – 2 Three years of operation of the Elettra tri-generation plant (R. Visintini – Elettra) • At the Elettra Center the second tri-generation plant has started operation. • About 6400 hours/year of operation • Mains disturbances affect 1-2% of downtime (max allowed 5%) • Elettra Storage Ring benefits from the increased power from UPS fully protecting its superconducting cavity • More power is now available from TGP2 • Feasibility study for protecting additional critical plants, in the Storage Ring, in particular the 4 RF plants Report on Parallel session A4

  4. Energy Quality and Operation – 3 Design and simulation of a SMES for grid primary control (H-J. Eckoldt – DESY) • Make use the many assets of DESY for a study on an innovative SMES (Superconductive Magnet Energy Storage) • Large power & energy storage (+/- 40 MW – 25 MWh) • Superconductive coil design derived from the one of ITER • Notwithstanding its size, the energy capacity is relatively low • Best application: regulation of grid frequency • Simulation results confirm SMES feasibility as Primary Control Power • Cost analysis: 14 years for amortization Report on Parallel session A4

  5. Energy Quality and Operation – 4 Advanced Simulation tools in support of the design of the Power System architecture of the European Spallation Source (ESS) (J. Tang– RWTH Aachen) • 2-year project on ESS and Lund regional grids simulation • Models for the regional Lund and internal ESS grids to evaluate mutual impact • Use of Real-Time co-simulation software and hardware, complementary simulation tools (RTDS, Opal RT, MATLAB/Simulink) • Various scenarios have been tested, in normal and fault conditions • The simulation of two LINAC charging schemes show large impact on the quality of the Lund grid. Report on Parallel session A4