This summary covers updates on vacuum infrastructure, dust mitigation plan coordination, progress against milestones, and reviews discussed during the October 9, 2007, meeting. Key decisions include roles, graphite usage, coolers specification, and upcoming reviews.
E N D
Issues from TB: 2007-10-09 • Vacuum infrastructure: • Wing Lau to be asked whether he can take on coordination/overview role • Target: dust mitigation plan: • MICE Note 180: C.Booth: plan endorsed: • Diamond-like graphite • Propose limited number of pulses (>2M) • Enough for running January to May • Liquid-hydrogen test cryostat: • Jacketing plan proposed by Y.Ivanyushenkov accepted • Focus-coil tender exercise: • Proposed offer/vendor accepted • Agreed that pulse-tube cooler would be specified
Issues from TB: 2007-10-09 • Progress against milestones: • TOF: • Anticipate ToF0&1 will arrive at RAL 15Nov07 • Some uncertainty owing to INFN management • ToF2: • Goal to deliver ToF2 by Jun08 • KL: • KL fully equipped in Roma III – End Nov07 • KL fully tested in Roma III – mid-Dec 07 • Expect to integrate in cosmic test before Xmas • CKov – postponed
Issues from TB: 2007-10-09 • Reviews: • Beam-line review: November/December • Poole (ASTeC, Chair), Petit-Jean (PSI), Gardner (ISIS) • Diffuser review • Lau meeting with Perrin this week at CERN. • DAQ/controls review • ABr/JSG to draft charge/agenda today. • WBS/Schedule review • December • Next meeting: • 16Nov07: 14:30 BST