News UPO August 9, 2013 Didier Contardo , Jeff Spalding. HI contributions to the three TDR projects. From last UPO. Proposals from CMS-HI to DOE-NP to provide support for HI work on the three TDR projects Trigger

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'News UPO August 9, 2013 Didier Contardo , Jeff Spalding' - joella


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

News

UPO August 9, 2013

Didier Contardo, Jeff Spalding

hi contributions to the three tdr projects
HI contributions to the three TDR projects

From last UPO

  • Proposals from CMS-HI to DOE-NP to provide support for HI work on the three TDR projects
    • Trigger
      • contributions to interim calo trigger for HI running in 2015: algos and boards
      • proposal already approved – and funds committed
    • HCAL
      • Upgrade ZDC front-end and cables, and HF-like uTCA BE
    • Pixels
      • Studies for HI with new pixels, work on new DAQ and commissioning pilot blades
  • Proposals for HCAL/ZDC and Pixels to be submitted by the end of August, along with a status report on the Trigger work
  • We need the 3 projects to endorse the contributions
  • HI will present the three at the next UPO on August 9
next for 2013 rrb document
Next for 2013 RRB Document

From last UPO

  • Timeline

(a) Cost Exercise

    • We are late on the timeline we showed at the last UPO
    • Pre-final cost input is urgently needed
    • Guidelines are here https://cms-docdb.cern.ch/cgi-bin/DocDB/RetrieveFile?docid=11981&version=1&filename=Guidance_Phase2_Cost%20Exercise_v1.docx
    • Status…

(b) Text

    • Also late

Document Version 1

    • Must be in reader group review by ~Aug 15
    • Send to MB/FB Aug 26, present at Taipei September 9
    • Send to CERN immediately after Taipei CMS Week
    • Presentation to LHCC in Sept.

Document version 2

    • Update with input back from CERN, LHCC and studies for ECFA
    • Send to RRB after ECFA in early October

Still true

Still true

october upgrade week oct 21 25
October Upgrade Week (Oct 21-25)

From last UPO

As for Upgrade Week at DESY, propose working sessions/plenaries:

  • Answer specific technical questions
  • Define content, and the plan to develop material for sections of the TP
    • Recall: TP should be in CWR at end of July 2014

Focus on TP, but include LS1 planning and progress of TDR projects

*

“TP Sections”:TUE

  • Overall performance
    • Overall physics goals, reach… build on ECFA work
    • Simulations supporting emphasis on Triggering (track trigger and bandwidth) and Endcap region (calorimetry and muons). Performance of specific choices should be included in relevant sections
  • Non-competing parallel-plenary: TC considerations
    • Radiation, shutdown logistics etc
  • See next slide for sessions.
  • Consider vidyo-workshop(s)
  • between Oct & April UpgWeeks
october upgrade week oct 21 251
October Upgrade Week (Oct 21-25)
  • “TP-sections”: Wed-Thu
  • Detector Sections
  • TK (strips, pixels and forward pixels)
  • FEE (EB, DT, CSC) and Other Systems: Power, cooling… (as much as possible on M&O)
  • Trigger and DAQ
  • Calorimeters
  • Muon Systems
  • TC: shielding changes, tooling
  • Note: the timeline and cost information for each of these will be compiled into a dedicated section
  • We need a draft table of contents and template for the document
  • And provide guidance for these sections

Note: this is everything for the TP content, so including longevity etc, upgrade considerations, design choices and concept, R&D and study plans, cost and scope of work