1 / 76

LST Installation Readiness Review

LST Installation Readiness Review. Mechanical Installation Preparation H. James Krebs May 5, 2004. Mechanical Installation Preparation. IR-12 is the location of most mechanical preparation work during 2004 & 2005 Why IR-12? IR-12 Hall is very similar to IR-2 Hall Same floor plan

jjudy
Download Presentation

LST Installation Readiness Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LST Installation Readiness Review Mechanical Installation Preparation H. James Krebs May 5, 2004 H.J. Krebs

  2. Mechanical Installation Preparation • IR-12 is the location of most mechanical preparation work during 2004 & 2005 • Why IR-12? • IR-12 Hall is very similar to IR-2 Hall • Same floor plan • Identical 50/10 ton crane combination • We need space • IR-12 was empty • IR-2 is presently occupied with BaBar related items H.J. Krebs

  3. IR-2 H.J. Krebs

  4. IR-12 - Before H.J. Krebs

  5. IR-12 Today H.J. Krebs

  6. IR-12 Activities • Pre-installation preparation of brass plates • Radius corners • Drill & tap threaded holes for slide swivel shackles • Camber plates as needed • Stage plates for assembly • BaBar model • Build a fairly crude but full scale mock-up of the forward end of BaBar including: • Barrel assembly simulating corner blocks removed • FWD end doors • FWD PEP pier H.J. Krebs

  7. Full Scale BaBar Model H.J. Krebs

  8. 12” Thick (Z) Sextant Prototype H.J. Krebs

  9. Sextant Iron Cable Channel H.J. Krebs

  10. IR-12 Activities • Purpose of Model • Construct elevator platform • Test function • Check for interferences with end doors, beamline and PEP pier • Load test • Modify as necessary for corrections or improvements • Brass installation preparation • Test installation hardware • Practice brass plate installation • Brass push test • LST detector installation preparation • Test installation hardware • Practice LST detector installation • A full length XZ gap (layer 8) model is being constructed for this H.J. Krebs

  11. IR-12 Activities • Steel handling fixtures • Train technical support staff • Check centers of gravity • Determine appropriate rigging • Load test • Function test, if possible • Modify as needed • Perform a field job hazards analysis H.J. Krebs

  12. Elevator Platform • Due to SLAC internal problems, the purchase req for the elevator platform was issued two months later than planned. • Expect upper elevator components beginning of June • Expect lower elevator components mid June • Still enough time to erect, test and modify these platforms • Very little schedule float remains on these items H.J. Krebs

  13. RPC Pulling Clamps H.J. Krebs

  14. Brass Handling Fixtures • Brass positioners • Purpose • Adjusts the orientation of the brass absorber plates to align with openings in the flux return steel. The positioners for the lower sextant are different than those for the upper sextant. • Needed 2004 • Responsible person • Allen Constable • Status • Design and drawings are complete • Fabrication of upper positioners complete • Fabrication of lower positioners in process • Need to function test using BaBar mock up H.J. Krebs

  15. Upper Brass Positioners H.J. Krebs

  16. Upper Brass Positioners H.J. Krebs

  17. Brass Handling Fixtures • Brass plate pushers • Purpose • To push the brass absorber plates into the gaps in the steel flux return. • Needed 2004, 2005 • Responsible person • Jim Krebs • Status • Design and drawings are complete • Fabrication is nearing completion • Need to function test using full length XZ gap mock up H.J. Krebs

  18. Brass Plate Pushers H.J. Krebs

  19. 24” Brass Plate Pusher H.J. Krebs

  20. Brass Pull Test H.J. Krebs

  21. Brass Pull Test (315.3 lb Plate) H.J. Krebs

  22. Steel Handling Fixtures • Side Gap Plate Fixture • Purpose • Remove and reinstall the side gap plates on the FWD and BWD ends to enable removal of RPCs, installation of brass absorber plates and LSTs, and access to RPC electronics • Needed 2004, 2005 • Responsible person • Jim Krebs • Status • Fabrication complete • CG tested in unloaded and loaded conditions (have used many times in the past) H.J. Krebs

  23. Side Gap Plate Fixture H.J. Krebs

  24. Side Gap Plate Fixture H.J. Krebs

  25. Steel Handling Fixtures • Center Gap Plate Fixture • Purpose • Remove and reinstall the upper and lower center gap plates on the FWD end to enable removal of RPCs and installation of brass absorber plates and LSTs • Needed 2004 • Responsible person • Jim Krebs • Status • Fabrication complete • CG tested in unloaded condition • Rigging procedure and job hazards analysis written and reviewed • Load tested to 168% of design load H.J. Krebs

  26. Center Gap Plate Fixture H.J. Krebs

  27. Center Gap Plate Fixture H.J. Krebs

  28. Center Gap Plate Load Test H.J. Krebs

  29. Center Gap Plate Load Test H.J. Krebs

  30. Center Gap Plate Load Test H.J. Krebs

  31. Steel handling Fixtures • Solenoid Support Arm Fixture • Purpose • Remove and reinstall the upper and lower solenoid support arms on the FWD end used to react axial loads. This will enable removal of the upper and lower FWD corner blocks. • Needed • 2004, 2005 • Responsible person • Jim Krebs • Status • Design and drawings complete • Fabrication complete • CG tested in unloaded condition • Rigging procedure and job hazards analysis written and reviewed • Load tested to 236% of design load H.J. Krebs

  32. Solenoid Support Arm Fixture H.J. Krebs

  33. Solenoid Support Arm Fixture H.J. Krebs

  34. Solenoid Supt Arm Load Test H.J. Krebs

  35. Steel Handling Fixtures • Corner Block Adaptors • Purpose • Moves corner block rigging connection in Z direction to more convenient location. There are two basic adaptors corresponding to the mid & lower corner blocks and right and left hand units to correspond with east and west. • Needed • 2004 (lower), 2005 (mid & lower) • Responsible person • Jim Krebs • Status • Design and drawings complete for lower adaptor • Fabrication complete • Load tested to 139% H.J. Krebs

  36. Lower Corner Block Adaptor H.J. Krebs

  37. Lower Corner Block Adaptor H.J. Krebs

  38. Steel Handling Fixtures • Adaptor Installation Fixture • Purpose • Used to install and remove the adaptors on the mid & lower corner blocks. • Needed • 2004, 2005 • Responsible person • Jim Krebs • Status • Design and drawings complete • Fabrication complete • CG tested in unloaded and loaded conditions • Rigging procedure and job hazards analysis written and reviewed • Load testing believed to be unnecessary H.J. Krebs

  39. Adaptor Installation Fixture H.J. Krebs

  40. Steel Handling Fixtures • FWD Lower Corner Block Fixture • Purpose • Supports the FWD lower corner block dead load from crane during removal and reinstallation process. • Needed • 2004, 2005 • Responsible person • Jim Krebs • Status • Design and drawings complete • Fabrication complete • CG tested in unloaded condition • Rigging procedures and job hazards analysis have been written and reviewed • Load tested to 129% of design load H.J. Krebs

  41. FWD Lower Corner Block Fixture H.J. Krebs

  42. FWD Lower Corner Block fixture H.J. Krebs

  43. Lwr Crnr Blk Fixture Load Test H.J. Krebs

  44. Steel handling Fixtures • BWD Lower Corner Block Fixture • Purpose • Supports the BWD lower corner block dead load from crane during removal and reinstallation process. • Needed • 2004, 2005? • Responsible person • Richard Boyce • Status • Design is in process H.J. Krebs

  45. Steel handling Fixtures • FWD Upper Corner Block Fixture • Purpose • Supports the FWD upper corner block dead load from crane during removal and reinstallation process. • Needed • 2004, 2005 • Responsible person • Jim Krebs • Status • Design and drawings complete • Fabrication complete • CG tested in unloaded condition • Rigging procedures and job hazards analysis have been written and reviewed • Load tested to 132% of design load H.J. Krebs

  46. FWD Upper Corner Block Fixture H.J. Krebs

  47. FWD Upper Corner Block Fixture H.J. Krebs

  48. FWD Upr Crnr Blk Load Test H.J. Krebs

  49. Steel Handling Fixtures • Corner Block Bolt Storage Bins • Purpose • Stores corner block bolts and organizes bolts to reinstall them in their original locations. Six storage bins will be fabricated. • Comments • A written torquing sequence and torquing procedure is in process • Needed • 2004, 2005 • Responsible person • Jim Krebs • Status • Design and drawings complete • Fabrication complete H.J. Krebs

  50. Corner Block Bolt Storage Bins H.J. Krebs

More Related